Neglecting bearing at the tip of the piles, Civil Engineering

Assignment Help:

A square pile group of 9 piles of 25 cm diameter is arranged with a pile spacing of 1m. The length of the piles is 9 m. Unit cohesion of the clay is 75 kN/m2.

Neglecting bearing at the tip of the piles Verify the group capacity.

Assume adhesion factor of 0.75.

 


Related Discussions:- Neglecting bearing at the tip of the piles

#support reactions, calculate the support reaction as shown in figure;

calculate the support reaction as shown in figure;

Reason in checking the ratio, Reason in checking the ratio (i.e. design flo...

Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design For checking of self-cleansing velocity for pipes, there is another criterion t

Design the curtain to touch the seabed, Question For fixing of silt cur...

Question For fixing of silt curtains, what is the reason that it does not desirable to design the curtain to touch the seabed ? Answer Silt finished are resistant ve

Optimum moisture content to grab maximum density, Question For compacti...

Question For compaction of free-draining sands or gravels, what is optimum moisture content to grab maximum density ? Answer Compaction curve of dirty materials is com

Non destructive inspection steel/cast iron substructure, Explain the Non De...

Explain the Non Destructive Inspection Steel/Cast Iron Substructures Some of the structural defects in steel structures may not be visible during visual inspection. In that eve

Define the hazard ranking system (hrs), Define the Hazard Ranking system (H...

Define the Hazard Ranking system (HRS) - A procedure for ranking uncontrolled hazardous waste sites in terms of the potential threat based upon the containment of the route of

Explain the statements about the differential levelling, Explain the Statem...

Explain the Statements about the Differential Levelling I.  Bench mark (BM) - relatively permanent point of known elevation as indicated on the Contract drawings  II. Back s

Distomat, Feactures and uses of distomat

Feactures and uses of distomat

Assignment, Need assignment for structure concrete work

Need assignment for structure concrete work

Engineering project control, need help with my assignment. An Asian Pacific...

need help with my assignment. An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Pref

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd