Optimum moisture content to grab maximum density, Civil Engineering

Assignment Help:

Question

For compaction of free-draining sands or gravels, what is optimum moisture content to grab maximum density?

Answer

Compaction curve of dirty materials is completely different from that of clayey materials. For sands, gravels, there are two states of affairs of utmost density, namely completely dry condition and complete water saturation. For humidity content of sand and gravels between two states, dry density obtained is lesser than that obtained in above-mentioned states. Occurrence of capillary forces account for difficulty of compaction sand at water contents between almost dry and saturated state. They are shaped in partially filled water invalid between soil particles and do as elastic ties cementing soil particles jointly.
Compaction curve for clay is appropriate for majority of soil types apart from sands and gravels since a little amount of clay in soils is enough to create soils impermeable.


Related Discussions:- Optimum moisture content to grab maximum density

Define contaminants - underwater inspection of bridge, Define Contaminants ...

Define Contaminants - underwater inspection of bridge? There are various substances that may be inadvertently incorporated into the concrete matrix (e.g. glass, coal, gypsum),

Define the categories of corrosion of steel structures, Define the Categori...

Define the Categories of Corrosion of steel structures? Corrosion of steel structures can be classified as under: -   Atmospheric corrosion -   Underwater corrosion -

Define the term - prestressing force, Define the term - prestressing force ...

Define the term - prestressing force It should be realized that the maximum amount of prestressing force which can be  transferred from tendons to concrete depends on the bond

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

Define the precedence diagramming methods, Define the Precedence Diagrammin...

Define the Precedence Diagramming Methods a) Activity on Node (AON) with arrows for dependencies b) Uses all forms of precedence relationships

Stormwater, Design of the stormwater drainage system for the sub-division ...

Design of the stormwater drainage system for the sub-division Work needed: The following tasks require to be performed for the drainage network: Compute stormwater r

Determine concentration of total solids and volatile solids, The following ...

The following test results were obtained for a 100 ml wastewater sample taken at the inlet to wastewater treatment plant.  The tests were performed using the standard methods. Dete

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd