Reason in checking the ratio, Civil Engineering

Assignment Help:

Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design

For checking of self-cleansing velocity for pipes, there is another criterion to check design flow Q to full bore flow Qfull> 0.5. If this criterion is met, it may be assumed that design flow is always greater than self-cleansing velocity.

The reason behind it is that from the chart of circular pipes when Q/ Qfull>0.5 then ratio of design velocity V to full bore velocity Vfull>1. After confirming Vfull>1m/s then it leads to V>1m/s. Therefore minimum velocity at full bore flow must be checked.


Related Discussions:- Reason in checking the ratio

Explain the steady and uniform flow, Explain the Steady and Uniform Flow ...

Explain the Steady and Uniform Flow Steady flow: Flow quantity does not change over time. Uniform flow: The slopes of the energy grade line S = dE/dL, the hydraulic grade li

Transportation issues, "We have one other pressing challenge that you could...

"We have one other pressing challenge that you could review for us," Alistair Wu says. "As you know, the Shanghai plant was our first facility in China, but we also have two other

Estimation, What are the various methods of recording measurements? List fi...

What are the various methods of recording measurements? List five items each for various methods of recoding measurements?

Theory of elasticity and plasticity, derivation for strain energy stored in...

derivation for strain energy stored in a body due to torsion

Explain detention or retention ponds - hydrology, Explain Detention or Rete...

Explain Detention or Retention Ponds Detention/Retention Ponds: Designed to reduce and contain the peak runoff from developed areas (more impervious). Attempt to limit the runo

Remedial measures for problems in turbid water - absorption, Define Remedia...

Define Remedial measures for Problems in Turbid Water - Absorption? The process of absorption of light can be overcome by using higher powered lighting, or by using more light

#titl, Two readings ie 1.64m and 0.73m were taken during leveling procedure...

Two readings ie 1.64m and 0.73m were taken during leveling procedure to define the slope of a centerline of a bridge at points A and B. If distance AB=50 m, find the slope of line

Sampling distribution and approximations of distributions, Sampling Distrib...

Sampling Distribution And Approximations Of Distributions: 1) Learnt three approaches for deriving the probability distributions of functions of one or more random variables v

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd