Reason in checking the ratio, Civil Engineering

Assignment Help:

Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design

For checking of self-cleansing velocity for pipes, there is another criterion to check design flow Q to full bore flow Qfull> 0.5. If this criterion is met, it may be assumed that design flow is always greater than self-cleansing velocity.

The reason behind it is that from the chart of circular pipes when Q/ Qfull>0.5 then ratio of design velocity V to full bore velocity Vfull>1. After confirming Vfull>1m/s then it leads to V>1m/s. Therefore minimum velocity at full bore flow must be checked.


Related Discussions:- Reason in checking the ratio

Plinth wall, is it necessary for to put plinth wall in buildings

is it necessary for to put plinth wall in buildings

What are the limits of any soil classification system, Draw neatly the IS p...

Draw neatly the IS plasticity chart and label the symbol of several soils. What are the limits of any soil classification system? Explain the following tests with their meani

Define surface communication-underwater inspection of bridge, Define Surfac...

Define Surface Communication - Underwater Inspection of Bridge? It is not necessary to have voice communication in all situations, particularly for shallow dives where the dive

Compass survey, define compass survey and mention its objectives

define compass survey and mention its objectives

Impact of possible energy, a) Take into consideration the boiler efficiency...

a) Take into consideration the boiler efficiency, and verify the cost of heating the building, during the heating season, using present oil and gas prices.  b) Investigate the i

How to calculate the combined stresses, Compute the stresses at top and bot...

Compute the stresses at top and bottom fibers in a simply supported pre-stressed concrete beam with a rectangular cross section, 250 mm wide and 450 mm deep, as shown in Figure, at

Grillage foundation, what are the advantages of grillage foundation and why...

what are the advantages of grillage foundation and why people prefers that?

Analysis of prestress and bending stresses, Normal 0 false fa...

Normal 0 false false false EN-IN X-NONE X-NONE

Bituminous macadam, What is the working capacity of a road paver per hour f...

What is the working capacity of a road paver per hour for bituminous macadam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd