Reason in checking the ratio, Civil Engineering

Assignment Help:

Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design

For checking of self-cleansing velocity for pipes, there is another criterion to check design flow Q to full bore flow Qfull> 0.5. If this criterion is met, it may be assumed that design flow is always greater than self-cleansing velocity.

The reason behind it is that from the chart of circular pipes when Q/ Qfull>0.5 then ratio of design velocity V to full bore velocity Vfull>1. After confirming Vfull>1m/s then it leads to V>1m/s. Therefore minimum velocity at full bore flow must be checked.


Related Discussions:- Reason in checking the ratio

Distance between concrete columns in 5 story building, distance between con...

distance between concrete columns in 5 story building and if there is distance 15 feet than what should be the column size and how many bars and diameter of each bar ?

Calculate surface loading rate for each clarifier, A wastewater plant is op...

A wastewater plant is operating at 10MGD with a suspended solids concentration of 200mg/L. It has 6 clarifiers operating in parallel. Each clarifier is 40 foot in diameter and 10 f

State active earth pressure behind a vertical wall, With the aid of Mohr's ...

With the aid of Mohr's circle diagram describe what means by active and passive Rankine states is in a cohesionless soil with a horizontal surface. As obtain an expression for the

Explain equation for change interval, Explain equation for Change Interval ...

Explain equation for Change Interval y = t + v / 2a + 64.4G Where:  y = length of yellow interval (sec)     t = driver perception/reaction time (1.0 sec generally used)

Som, derive the expression for stress in arbitrary plane in a body subjecte...

derive the expression for stress in arbitrary plane in a body subjected to bi axial stress condition

Explain situations that warrant a damage inspection, Explain Situations tha...

Explain Situations that warrant a damage inspection? - Floods - bridges located in streams, rivers and other waterways with known or suspected scour potential. - Build-up of

Rcc flooting, Explain the simple square footing, simple squral footing an...

Explain the simple square footing, simple squral footing and slop footing with the help of drawing

Explain is vadose zone - ground water, Explain is Vadose Zone - Ground wate...

Explain is Vadose Zone - Ground water In an unconfined aquifer, it is the area located above the water table and aquifer, where the soil and rock are not saturated with water.

Compare brick masonry versus stone masonry, Compare brick masonry versus st...

Compare brick masonry versus stone masonry advantage and disadvantage? Ans.- Comparison between Stone masonry and Brick masonry- Stone masonry Bri

Elaborate the term - prestressed concrete pipes, Elaborate the term - Prest...

Elaborate the term - Prestressed concrete pipes Liquid retaining structures, such as circular pipes, tanks and pressure vessels are suited for circular prestressing. The circum

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd