Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design
For checking of self-cleansing velocity for pipes, there is another criterion to check design flow Q to full bore flow Qfull> 0.5. If this criterion is met, it may be assumed that design flow is always greater than self-cleansing velocity.
The reason behind it is that from the chart of circular pipes when Q/ Qfull>0.5 then ratio of design velocity V to full bore velocity Vfull>1. After confirming Vfull>1m/s then it leads to V>1m/s. Therefore minimum velocity at full bore flow must be checked.
Roads in Hilly Areas: (a) The alignment selected should attain the changes in elevation by adopting the ruling gradient to the maximum length. Limiting and exceptional
Keywords of Road Pavements: Pavement : That part of a road which structurally supports the vehicles travelling on a road. Flexible Pavement : A layered system of pave
A piece of clay taken from a sampling tube has a wet weight of 1.553 N and volume of 95.3 cm . After drying in an oven for 24 hours at 105°C, its weight is 1.087 N. The liquid and
Determine about the long-term deflections For long-term deflections, the total long-term deflection due to the prestressing force, dead load and any sustained imposed load may
Please help me to write a c program to find strength and efficiency of lap joint, single cover butt joint, double cover butt joint
describe setting out right angle at given point on a chain line and when the point lies outside the chain line
Q. Cutting edge in well foundation? The function of cutting edge on well foundation is basically to cut through the earth which being sunk. The angle of well curb pushes the ea
A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square
what is the advanantage& dis advantage
How a water bound macadam road is maintained
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd