Reason in checking the ratio, Civil Engineering

Assignment Help:

Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design

For checking of self-cleansing velocity for pipes, there is another criterion to check design flow Q to full bore flow Qfull> 0.5. If this criterion is met, it may be assumed that design flow is always greater than self-cleansing velocity.

The reason behind it is that from the chart of circular pipes when Q/ Qfull>0.5 then ratio of design velocity V to full bore velocity Vfull>1. After confirming Vfull>1m/s then it leads to V>1m/s. Therefore minimum velocity at full bore flow must be checked.


Related Discussions:- Reason in checking the ratio

Roads in hilly areas, Roads in Hilly Areas: (a)        The alignment s...

Roads in Hilly Areas: (a)        The alignment selected should attain the changes in elevation by adopting the ruling gradient to the maximum length. Limiting and exceptional

Keywords of road pavements, Keywords of Road Pavements: Pavement : T...

Keywords of Road Pavements: Pavement : That part of a road which structurally supports the vehicles travelling on a road. Flexible Pavement   : A layered system of pave

Determine the liquidity index and void ratio of the sample, A piece of clay...

A piece of clay taken from a sampling tube has a wet weight of 1.553 N and volume of 95.3 cm . After drying in an oven for 24 hours at 105°C, its weight is 1.087 N. The liquid and

Determine about the long-term deflections, Determine about the long-term de...

Determine about the long-term deflections For long-term deflections, the total long-term deflection due to the prestressing force, dead load and any sustained imposed load may

Strength of rivet joints, Please help me to write a c program to find stren...

Please help me to write a c program to find strength and efficiency of lap joint, single cover butt joint, double cover butt joint

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

Cutting edge in well foundation, Q. Cutting edge in well foundation? Th...

Q. Cutting edge in well foundation? The function of cutting edge on well foundation is basically to cut through the earth which being sunk. The angle of well curb pushes the ea

Calculate the square foot of contact area for the formwork, A concrete crew...

A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square

Fluid mechanics, How a water bound macadam road is maintained

How a water bound macadam road is maintained

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd