Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design

For checking of self-cleansing velocity for pipes, there is another criterion to check design flow Q to full bore flow Qfull> 0.5. If this criterion is met, it may be assumed that design flow is always greater than self-cleansing velocity.

The reason behind it is that from the chart of circular pipes when Q/ Qfull>0.5 then ratio of design velocity V to full bore velocity Vfull>1. After confirming Vfull>1m/s then it leads to V>1m/s. Therefore minimum velocity at full bore flow must be checked.


Related Discussions:- Reason in checking the ratio

Maintenance of steel bearings, Q. Maintenance of steel bearings? Cleani...

Q. Maintenance of steel bearings? Cleaning and greasing of bearings is one of the important maintenance works to avoid premature failure of bearings and reduce recurring heavy

Settlement due to lowering of water table, Q. Settlement due to Lowering of...

Q. Settlement due to Lowering of Water Table? Water table is encountered with, whenever any excavations are made for foundations. The water is to be out for working conditions.

Determine the value of the coefficient of permeability, Determine the value...

Determine the value of the coefficient of permeability A glass cylinder 5 cm internal diameter with a screen at the bottom is used as a falling head permeameter. The thickness

Air pollution, chlorosis in plants is caused by

chlorosis in plants is caused by

Total maximum surface deflection of the pavement system, A stationary 40 kN...

A stationary 40 kN single axle load (applied on a circular contact area of radius = 152 mm = 6") is applied to each of the flexible pavement structures indicated below. Assuming li

Municipal Hydraulics, Hello I have an assignment due feb 1st at 3 pm. I wan...

Hello I have an assignment due feb 1st at 3 pm. I wanted to know if it was possible that it gets solved

Illustrate the design discharge for foundation, Q. Illustrate the Design di...

Q. Illustrate the Design discharge for foundation? To provide for an adequate margin of safety, the foundation and protective works of a bridge should be designed for a flood d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd