Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Geodesy, what is the difference between geodesy and plane survey

what is the difference between geodesy and plane survey

Explain about viscous flow loss, Q. Explain about Viscous flow loss? Ab...

Q. Explain about Viscous flow loss? Absorptive material comprises interconnected voids and pores into which sound energy will propagate. When sound waves pass throughthe materi

Explain the createthread function used in the windows nt, Explain the Creat...

Explain the CreateThread Function used in the Windows NT CreateThread(security, size, MyThreadFunction, arg, flag,&tID ) The CreateThread function call is used to start an i

How is skin friction and point resistance of a pile computed, Describe the ...

Describe the basic difference in the bearing capacity computation of shallow and deep foundations. How are skin frictions and point resistance of a pile computed?

Sway porta frame, how to sway portal frame both end fixed due to eccentric ...

how to sway portal frame both end fixed due to eccentric loading with diagram

What should be the hydrometer reading, A litre of suspension containing 0.5...

A litre of suspension containing 0.5 N of soil with a specific gravity of 2.70 is prepared for a hydrometer test. When no temperature correction is considered necessary, what shoul

Of obstacles to both chaining and ranging.., #questof obstacles to both cha...

#questof obstacles to both chaining and ranging. ion..

Determine the value of the coefficient of permeability, Determine the value...

Determine the value of the coefficient of permeability A glass cylinder 5 cm internal diameter with a screen at the bottom is used as a falling head permeameter. The thickness

Necessity for road drainage - road drainage, Necessity for Road Drainage: ...

Necessity for Road Drainage: Poor drainage can cause damage to the various components of a road in the following manner: (a) Water can enter the various pavement layers th

Define masonry substructure- underwater inspection of bridge, Define Masonr...

Define Masonry substructure- underwater inspection of bridge? In early days, masonry, particularly stone masonry was extensively used for bridge piers and abutments. Typically,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd