Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

EDTA, how to find total hardness by EDTA

how to find total hardness by EDTA

Damp proofing, how to remove dampness in mud houses?

how to remove dampness in mud houses?

Explain the terms void ratio, (a) Distinguish among Black cotton soil and L...

(a) Distinguish among Black cotton soil and Laterite from an engineering point of view. (b) Explain the terms 'Void ratio', 'Degree of saturation' and 'Water content', define th

Calculate the cubic volume of crushed stone, Calculate the Cubic Volume of ...

Calculate the Cubic Volume of Crushed Stone A symmetrical running track is being constructed in the configuration and dimensions as shown.  The cubic volume (CY) of crushed st

Raft base of pumping stations, Question Why are voids filled with light...

Question Why are voids filled with lightweight infilling material in raft base of pumping stations ? Answer To decrease dead load and therefore to decrease settleme

Courswork, looking for someone good at structure analysis and design cours...

looking for someone good at structure analysis and design courswork

Show method of greasing, Method of Greasing : Greasing of fixed end require...

Method of Greasing : Greasing of fixed end requires 20 to 25 minutes. The lifting is hardly 10 mm, ensuring that the gap is created between saddle block and knuckle pin. Saddle is

What is the meaning of term - slip in anchorage, What is the meaning of ter...

What is the meaning of term -Slip in Anchorage In the case of post-tensioned concrete, when the tendons are anchored at the ends of concrete members, a slip of  tendons takes

Arrangement of piles in a pile cap to reduce bending moment, Arrangement of...

Arrangement of piles in a pile cap to reduce bending moment induced in piles Let's consider that piles are designed to intersect at a single common point in a pile cap. The re

Coagulation, Incoming water contains 2.5 mg/L as a substance of natural alk...

Incoming water contains 2.5 mg/L as a substance of natural alkalinity (HCO3-). The flow rate is 9.5 ML/day). (a) What feed rate is required if the alum dose is 7 mg/L and is avail

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd