Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Define the term - permanent load, Define the term - permanent load Wher...

Define the term - permanent load Where the permanent load is less than or equal to 25% of the design imposed load, deflections may be calculated using any elastic method. When

Calculate uniform annual cost for maintenance and repair, A contractor purc...

A contractor purchased a Caterpillar D-13 dozer for $100,000 and owned it for five years. The annual cost for maintenance and repair is provided in the Table. With annual interest

Bricks properties, what is the application of silica,aluminaand magnesium i...

what is the application of silica,aluminaand magnesium in bricks?

Principles and Practices of Management, How Will You Influence People to St...

How Will You Influence People to Strive Willingly for Group Objectives in Your Organization (Target Based Industry)? Apply Your Interpersonal Influence Through Communication Proces

Explain the soil texture and soil structure, (a) Explain the 'Soil Texture'...

(a) Explain the 'Soil Texture' and 'Soil structure'. What are the various terms used to explain the above properties of the soil? (b) A clay sample having natural moisture conte

Timber design, design of timber in flexural members in terms of extreme fib...

design of timber in flexural members in terms of extreme fibre stress in bending, maximum horizontal shear stress, deflection and bearing stress perpendicular to the grain. the ful

Show the stresses during pile driving, Q. Show the Stresses during pile dri...

Q. Show the Stresses during pile driving? Stresses during pile driving In pile driving operation, proper selection of piling hammers is necessary to prevent the damage of

Jetties, JETTIES: A jetty is a structure projecting into the sea from ...

JETTIES: A jetty is a structure projecting into the sea from the shore line for receiving ships. They are made of RCC trestles with a deck to accommodate railway track and roa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd