Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

#title., Ask question #Minimum 100 words accepted2812539076# you

Ask question #Minimum 100 words accepted2812539076# you

Explain cercla and sara - hazardous waste regulations, Explain CERCLA and S...

Explain CERCLA and SARA - Hazardous Waste Regulations In 1980, the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) was enacted to address tho

Determine the in-situ dry unit weight, Q. The following observations were r...

Q. The following observations were recorded in a Field density determination by sand-replacement method: Volume of Calibrating can = 1000 cm3 Weight of empty can = 10 N We

List the factor that affect the permeability of a given soil, List the fact...

List the factors that affect the permeability of a given soil. Determine the precautions that should be taken so that satisfactory permeability data may be obtained. Explaining

Determine the required stirrup size and spacing requirement, A rectangular ...

A rectangular concrete beam is subjected to a factored design shear force of 200 kips.  For the beam shown below, determine the required stirrup size and spacing requirement. H = 3

Raking piles of bridge abutment placed under an embankment, Question It sho...

Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with div

Basic Structural Design, A flitched beam consists of a wooden joist 150 mm ...

A flitched beam consists of a wooden joist 150 mm wide and 300 mm deep strengthened by steel plates 12 mm thick and 300 mm deep one on either side of the joist. If the maximum st

Steel and timber structures, design a tension member subjected to a pull of...

design a tension member subjected to a pull of 300KN using a channel section. the length of a joint available is only 400mm.check the condition of using lug angle for end connecti

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd