Lifting of girders : For greasing the bearings girders are required to be lifted. But the gap between the bottom flange of plate girders and the bed block generally varies from 100 mm to 150 mm. The standard jacks normally available have a closed height of at least 300 mm. These jacks, therefore, can't be used for lifting the girders without making special jacking arrangements.
Following jacking arrangement can be adopted for different types of girders:
1. For plate girders upto 6.1 m span, jacks can be directly applied below end sleeper ensuring firm hook bolt connection, since load to be lifted is about 4 to 5 ton only.
2. Jacking arrangement for span 9.15 m plate girder requires provision of a hard wood beam below inner top flange.
3. Jacking arrangement for span 12.2, 18.3, 24.4 and 30.5 m plate girder requires provision of a steel beam.
Q. Process of Lubrication of Girder Bearing? Oiling and greasing of bearings is done to ensure that the bearings are well lubricated and working freely to permit expansion and
what aare the parts and function of steel tape ?
What is bench mark
can we provide base isolation for high rise buildings ? Can we provide it for diagrid structures? if; yes Up to which no of storeys
Explain the Column Effective Length 1. For a single column, the effective length is simply the unbraced length * the k factor: 2. When comparing an effective length fo
what you mean by civil engineering
Define Water jets for underwater inspection of bridge? These tools are widely used and produce a bright metal finish in one operation. Grit entrainment is available and makes t
Q. How to design banks? When approach banks are of medium height upto 3 m, the material may be homogeneous. For bigger heights zoned section with impervious core and pervious o
What is Partial Prestressing It is a form of prestressing in which tensile stresses are permitted, upto a limited extent, in concrete under working loads. As the permitted tens
Determine the Head Loss Due To Friction Determine the head loss due to friction using the Darcy-Weisbach equation. The water is pumped at 3.0 gallons per minute, has a temperat
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd