Example of magnetic dip, Civil Engineering

Assignment Help:

Example :

Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what magnetic bearing the line should be set now?

Solution: Referring to given figure, it is clear that

1294_magnetic bearing.png

Present magnetic bearing of line AB

= 3° 30′ + 2° 30′ + 136° 45′

= 142° 45′        Ans.


Related Discussions:- Example of magnetic dip

Define creep settlements, Creep occurs (secondary compression) after consol...

Creep occurs (secondary compression) after consolidation settlements. We defined consolidation settlement, as that compression during which excess pore pressure exists in the strat

Problems formed while design of pre-stressed concrete, Determine the proble...

Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by  the engineer engaged in the design of pre-stressed concrete membe

Telecommunication, Blocked process list is not maintioned in priority order...

Blocked process list is not maintioned in priority order why

State the coulomb earth pressure theory, A masonry wall with vertical back ...

A masonry wall with vertical back has a backfill 5 m behind it. The ground level is horizontal at the top and the ground water table is at ground level. Measured the horizontal pre

What is initial prestress, What is Initial Prestress From the transfer ...

What is Initial Prestress From the transfer stage, tensile stresses in tendons apply compressive stresses in concrete. The initial value of  these stresses (in tendons or in co

Plants aeration period, Plants aeration period: Problem: What i...

Plants aeration period: Problem: What is the plant's aeration period? Solution The plant's aeration period is the number of hours that the wastewater is aerated

Stress, stress and there types

stress and there types

Concrete compaction in piling works, Question What is the reason that v...

Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i

Determine about the prestressed concrete, Determine about the prestressed c...

Determine about the prestressed concrete In prestressed concrete the most important parameter is the prestressing force. Ifthe prestressing force reduces with time, prestresses

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd