Example of magnetic dip, Civil Engineering

Assignment Help:

Example :

Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what magnetic bearing the line should be set now?

Solution: Referring to given figure, it is clear that

1294_magnetic bearing.png

Present magnetic bearing of line AB

= 3° 30′ + 2° 30′ + 136° 45′

= 142° 45′        Ans.


Related Discussions:- Example of magnetic dip

Transition curves - geometric design of roads, Transition Curves: If ...

Transition Curves: If a vehicle travelling on a straight enters a horizontal curve abruptly, it will cause shock and sway. To avoid this, it is customary to provide a transit

Torpedo splice triple wedges, Torpedo splice triple wedges In a Torpedo...

Torpedo splice triple wedges In a Torpedo splice triple wedges, shown in Figure, are provided to firmly hold tendon wires. Whole assembly of the splice is housed in a sleeve. L

Formation of holes in pipelines, Question While branch pipelines are co...

Question While branch pipelines are connected to pipelines, now and then Y-junctions or fitting branched pipelines to key pipelines by formation of holes in pipelines are u

How to determine the frequency of flood, Q. How to determine the frequency ...

Q. How to determine the frequency of flood? Flood frequency may be estimated preferably from flood records, if available, for a number of years or they may be based on rainfall

Survey, how can find forebearing

how can find forebearing

Open foundation, what is savest foundation in the soft sanded earth

what is savest foundation in the soft sanded earth

Advantages of unbonded post-tensioning systems, Advantages of unbonded post...

Advantages of unbonded post-tensioning systems Similarly, some advantages of unbonded post-tensioning systems over bonded post-tensioning ones may be written as under :  (a)

Determine the total active thrust by rebhann''s method, A retaining wall 3....

A retaining wall 3.6 m high supports a dry cohesion less backfill with a plane ground surface sloping upwards at a surcharge angle of 20° from the top of the wall. The back of the

Temporary repairs to rail fracture, Q. Temporary Repairs to rail fracture? ...

Q. Temporary Repairs to rail fracture? If a welding party is not readily available, the fracture shall be repaired by using a cut-rail (not less than 4 meter long) and clamped/

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd