Write definition of afflux and skew bridge, Civil Engineering

Assignment Help:

Write definition of the following -

(i) Afflux. ( ii ) Free Board. ( iii ) Clearance. ( iv ) Via duct. ( v ) Skew Bridge ( vi ) Cause Way. ( vii ) Clear Span. ( viii ) Effective span. ( ix ) Over all Span ( x ) Score. ( xi ) Water Way.

Ans.- Afflux - It is the rise in the flood level of the river up stream of the bridge as a result of obstruction to natural flow caused by the construction of the bridge.

Free Board - This is the vertical distance between the high flood level inclusive of afflux and the formation level.

Clearance - This is the vertical distance between the high flood level inclusive of afflux and the bottom most part of bridge super structure like slab girder etc.

Via duct - When the bridge is constructed to cross a valley for railway instead of filling it the bridge as called via duct.

Skew Bridge - When the bridge is not right angle to the axis of river or other such opening it is called a skew bridge.

Cause Way - It is a bridge constructed to pass a flood water over the railway track is called cause way.

Clear Span - It is the clear distance between any two bridge supports like abutments piers etc. Effective span - It is the distance between centers of two adjacent bridge supports.

Over all Span - It is the over all length of girder.

Score - It is the rise in the distance from rail level and bottom of rivers.

Water Way - The area of the opening of a bridge blow super structure through which water flows is called water way.


Related Discussions:- Write definition of afflux and skew bridge

Calculate the amount of waste, Calculate the Amount of Waste A municipa...

Calculate the Amount of Waste A municipal solid waste department plans to separate a portion of the ferrous metal, newsprint and cardboard from its MSW waste stream. The depart

Strength of materials, what are the different between stress and strain

what are the different between stress and strain

Corrosion, How is corrosion perverted...?

How is corrosion perverted...?

Foundations, Design a footing of a bridge pier

Design a footing of a bridge pier

Hoyers long line system pre-tensioning, Hoyers long line system pre-tension...

Hoyers long line system pre-tensioning When concrete attains the required strength,  jacks  are released and tendon wires in-between various units are cut.

State the term axial prestressingin - Concrete, State the term Axial Prestr...

State the term Axial Prestressingin Concrete If the centroid of cross-sectional areas of tendons is at the location of the centroid of the cross-section of the concrete member,

Explain the maximum spacing of piles, Q. Explain the Maximum spacing of pil...

Q. Explain the Maximum spacing of piles? One of the factors which affect the distribution of loads from the structures to each pile is assumption of flexibility of the pile ca

Mechanics of solids, if we take brass & steel and on applying temperature t...

if we take brass & steel and on applying temperature the brass contracts the steel expands how it is possible

Define resultant force on a given area of a horizontal plane, Resultant For...

Resultant Force on a Given Area of a Horizontal Plane By equation, the total vertical force applied to an area A on the plane is: Resultant Force R = ΡA = (lb/ft 2 )(ft 2 )

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd