Meter field testing and installation practices, Electrical Engineering

Assignment Help:

Meter Field Testing and Installation Practices

Here, we discuss the installation, commissioning and field testing of meters.

Energy Meters - Installation and Commissioning

The meters are linked before the consumer's isolating device (Main Switch) that might be a moulded case miniature circuit breaker, circuit breaker, or an ironclad switch fuse unit. At the time of commissioning, every meter is tested at site through the owner. A reference standard meter of 0.2 classes or better is used for testing.

Supply Side Wiring

The supply side wiring is the responsibility of the utility and the subsequent must be ensured although carrying it out:

a) The supply wires given are of suitable rating.

b) In case of more than one meter on one service line, it is preferable to use bus-bars. While a number of meters are linked to single distributing mains for registering electricity supplied to various consumer loads, separate service lines - phase(s) and neutral, are used for every meter. Each independently metered consumer load is directly linked to distributing mains by its meter connected in specified phase sequence so as to meet accuracy requirements of relevant standard.

c) The supply wire is properly terminated.

d) The connection is as per links diagram mentioned on meter.

e) Utility should use its own earthing for its devices.

Utility gives phase and neutral supply to the consumers. The neutral is used for carrying return current only. The neutral of one consumer should not be linked to other consumers who have independent and separate supply connection. Utility provides separate neutral to every consumer up the metering point and similar is used through the consumer. The consumer ensures in which all the correct wiring practices are followed and neutral is not looped along with another consumer or meters in the similar premises.  Consumer should not earth the neutral after the metering point. While there are multiple meter installations, bus bar arrangement is used for neutral, so that looping is prevented.


Related Discussions:- Meter field testing and installation practices

Tariff filing, Tariff Filing Asset-wise details for each business ...

Tariff Filing Asset-wise details for each business of licensee; Audited accounts and financial statements, including cash flows for the preceding years and monthly bal

Purpose of customer review in project management, Q. Purpose of Customer Re...

Q. Purpose of Customer Review in project management? The Customer in conjunction with the Project Manager/ Engineer decides the timing of the IFA review. This review is cond

Second Order Precesses, A second-order process with one pole at the origin ...

A second-order process with one pole at the origin has the transfer function 3/(s(2s + 1)) Find the output as a function of time, for a unit step input change. Sketch the expected

Control system, I need some help for doing the assignment

I need some help for doing the assignment

Describe schmitt trigger, a) Describe Schmitt trigger with the help of tran...

a) Describe Schmitt trigger with the help of transfer characteristics. b) Also get the expression of hysteresis voltage VH and output waveform for sinusoidal input signal

Grounding and shielding used in electronic instruments, Q.   How and why ar...

Q.   How and why are the grounding and shielding used in electronic instruments? Sol. In electronic instruments grounding and Shielding techniques are available in order to a

Obtain the node voltages and current through each element, Q. For the circu...

Q. For the circuit shown in Figure, develop and execute a PSpice program to obtain the node voltages and the current through each element.

Form factor, Significance of form factor,why we decide the power handing ca...

Significance of form factor,why we decide the power handing capacity in transmission with the help of form factor?

Compute the kvar and the power factor of the motor, Q. A three-phase balanc...

Q. A three-phase balanced load draws 100 kW at 0.8 power factor lagging. In order to improve the supply power factor to 0.95 leading, a synchronous motor drawing 50 kWis connected

Selection of proper fuse in electricity and gas hazards, Selection of Prope...

Selection of Proper Fuse : Fuse is a safety device or a wire of metal in a cut-out which may be fused by an excessive current. The current drawn by an appliance is restricted by t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd