Meter field testing and installation practices, Electrical Engineering

Meter Field Testing and Installation Practices

Here, we discuss the installation, commissioning and field testing of meters.

Energy Meters - Installation and Commissioning

The meters are linked before the consumer's isolating device (Main Switch) that might be a moulded case miniature circuit breaker, circuit breaker, or an ironclad switch fuse unit. At the time of commissioning, every meter is tested at site through the owner. A reference standard meter of 0.2 classes or better is used for testing.

Supply Side Wiring

The supply side wiring is the responsibility of the utility and the subsequent must be ensured although carrying it out:

a) The supply wires given are of suitable rating.

b) In case of more than one meter on one service line, it is preferable to use bus-bars. While a number of meters are linked to single distributing mains for registering electricity supplied to various consumer loads, separate service lines - phase(s) and neutral, are used for every meter. Each independently metered consumer load is directly linked to distributing mains by its meter connected in specified phase sequence so as to meet accuracy requirements of relevant standard.

c) The supply wire is properly terminated.

d) The connection is as per links diagram mentioned on meter.

e) Utility should use its own earthing for its devices.

Utility gives phase and neutral supply to the consumers. The neutral is used for carrying return current only. The neutral of one consumer should not be linked to other consumers who have independent and separate supply connection. Utility provides separate neutral to every consumer up the metering point and similar is used through the consumer. The consumer ensures in which all the correct wiring practices are followed and neutral is not looped along with another consumer or meters in the similar premises.  Consumer should not earth the neutral after the metering point. While there are multiple meter installations, bus bar arrangement is used for neutral, so that looping is prevented.

Posted Date: 2/6/2013 8:08:25 AM | Location : United States







Related Discussions:- Meter field testing and installation practices, Assignment Help, Ask Question on Meter field testing and installation practices, Get Answer, Expert's Help, Meter field testing and installation practices Discussions

Write discussion on Meter field testing and installation practices
Your posts are moderated
Related Questions
Q. What do you mean by Insurance? This is done by creating a common fund out of the contribution (known as premium) from several persons who are equally exposed to the same los

Q. What is basic working of MOSFET? The metal-oxide-semiconductor construction leads to the name MOSFET, which is also known as insulated-gate FET or IGFET. One type of constru

Q. A signal with bandwidth of 100 MHz is to be transmitted 40 km by LOS radio transmission. Taking B/fc = 1/30, and using a circular-aperture parabolic dish with 50-cm radius at ea

what does actually feredy law wants to proof.


Design a Mealy system whose output is 1 iff there have been exactly two 1's followed by a 0 and then a 1. (a) Assume overlapping is allowed (b) Assume overlapping is not

Case 2 ( A>B) Suppose XX = 05H ( stored  in A ) And  YY = 02H ( stored  in B). Then carry  flag will  reset by CMP instruction, since  A> B in this  case JNC  will transfer the

Q What is Dual Tone Multi Frequency? Dual Tone Multi Frequency (DTMF) was first introduced in 1963 with 10 buttons in Western Electric 1500 -type telephones. DTMF was originall

Q. Elucidate the process of inter-register signalling. Ans: Registers are used in common control exchanges to store as well as analyze routing data. They are provided on a