Meter field testing and installation practices, Electrical Engineering

Meter Field Testing and Installation Practices

Here, we discuss the installation, commissioning and field testing of meters.

Energy Meters - Installation and Commissioning

The meters are linked before the consumer's isolating device (Main Switch) that might be a moulded case miniature circuit breaker, circuit breaker, or an ironclad switch fuse unit. At the time of commissioning, every meter is tested at site through the owner. A reference standard meter of 0.2 classes or better is used for testing.

Supply Side Wiring

The supply side wiring is the responsibility of the utility and the subsequent must be ensured although carrying it out:

a) The supply wires given are of suitable rating.

b) In case of more than one meter on one service line, it is preferable to use bus-bars. While a number of meters are linked to single distributing mains for registering electricity supplied to various consumer loads, separate service lines - phase(s) and neutral, are used for every meter. Each independently metered consumer load is directly linked to distributing mains by its meter connected in specified phase sequence so as to meet accuracy requirements of relevant standard.

c) The supply wire is properly terminated.

d) The connection is as per links diagram mentioned on meter.

e) Utility should use its own earthing for its devices.

Utility gives phase and neutral supply to the consumers. The neutral is used for carrying return current only. The neutral of one consumer should not be linked to other consumers who have independent and separate supply connection. Utility provides separate neutral to every consumer up the metering point and similar is used through the consumer. The consumer ensures in which all the correct wiring practices are followed and neutral is not looped along with another consumer or meters in the similar premises.  Consumer should not earth the neutral after the metering point. While there are multiple meter installations, bus bar arrangement is used for neutral, so that looping is prevented.

Posted Date: 2/6/2013 8:08:25 AM | Location : United States







Related Discussions:- Meter field testing and installation practices, Assignment Help, Ask Question on Meter field testing and installation practices, Get Answer, Expert's Help, Meter field testing and installation practices Discussions

Write discussion on Meter field testing and installation practices
Your posts are moderated
Related Questions
Q. A 150-kVA, 2400/240-V, 60-Hz, single-phase transformer has the following parameters: R 1 = 0.2 , R 2 = 0.002 , X 1 = 0.45 , X 2 = 0.0045 , RC = 10 k, and Xm = 1.55 k,

A 3 phase 60 hertz induction motor has 8 poles and operates with a slip of .05 for a certain load. Compute in r.p.m. the (a)speed of the rotor with respect to the stator, (b)spe

Q. Illustrate Transformer coupling? In this method the primary winding of the transformer acts as a collector load and the secondary winding transfers the a.c. output signal di

The basic operation of battery  A simple cell comprises two dissimilar conductors (electrodes) in an electrolyte. Such a cell comprises copper and zinc electrodes. An electric

Define some Huntington postulates - Boolean Algebra? Postulates 1. Commutative Law (a) A + B = B + A (b) A B = B A 2. Distributive Law (a) A (B + C) = A B + A

1. The circuit shown below is a DC charging and discharging circuit. a. At t = 0 sec, switch S1 is thrown to position 1 ("pos1"). Write the mathematical expressions for V

Electrical Fundamentals 1. An aircraft company has decided to replace the copper cables to the main aircraft generators onboard it's Boeing 747s with aluminium cables that are

Q. What is Pinch - off voltage?  The reverse bias is relatively large near the source. As a result, the depletion region intrudes into the channel near the drain, and the effec

Explain the properties of low resistivity materials. Low resistivity materials: The conducting materials containing resistivity from 10 -8 to 10 -6 ohm-m come under this cl

In this Project you will simulate a Security Alarm system using the Quick flash board. A switch is placed as shown in the figure below. The main goal of this project is: Task 1: