Meter field testing and installation practices, Electrical Engineering

Assignment Help:

Meter Field Testing and Installation Practices

Here, we discuss the installation, commissioning and field testing of meters.

Energy Meters - Installation and Commissioning

The meters are linked before the consumer's isolating device (Main Switch) that might be a moulded case miniature circuit breaker, circuit breaker, or an ironclad switch fuse unit. At the time of commissioning, every meter is tested at site through the owner. A reference standard meter of 0.2 classes or better is used for testing.

Supply Side Wiring

The supply side wiring is the responsibility of the utility and the subsequent must be ensured although carrying it out:

a) The supply wires given are of suitable rating.

b) In case of more than one meter on one service line, it is preferable to use bus-bars. While a number of meters are linked to single distributing mains for registering electricity supplied to various consumer loads, separate service lines - phase(s) and neutral, are used for every meter. Each independently metered consumer load is directly linked to distributing mains by its meter connected in specified phase sequence so as to meet accuracy requirements of relevant standard.

c) The supply wire is properly terminated.

d) The connection is as per links diagram mentioned on meter.

e) Utility should use its own earthing for its devices.

Utility gives phase and neutral supply to the consumers. The neutral is used for carrying return current only. The neutral of one consumer should not be linked to other consumers who have independent and separate supply connection. Utility provides separate neutral to every consumer up the metering point and similar is used through the consumer. The consumer ensures in which all the correct wiring practices are followed and neutral is not looped along with another consumer or meters in the similar premises.  Consumer should not earth the neutral after the metering point. While there are multiple meter installations, bus bar arrangement is used for neutral, so that looping is prevented.


Related Discussions:- Meter field testing and installation practices

Evaluate hysteresis loss, Q. A magnetic circuit is found to have an ac hyst...

Q. A magnetic circuit is found to have an ac hysteresis loss of 10 W when the peak current is Im = 2 A. Assuming the exponent of Bm to be 1.5, estimate Ph for Im = 0.5A and 8A.

What are the five stages in a dlx pipeline, The five stages of DLX pipeline...

The five stages of DLX pipeline is:- ? Operand location ? Number of explicit operands per instruction ? Operand storage in the CPU ? Operations ? Type and size of o

Explain basic working of integrators, Q. Explain basic working of Integrato...

Q. Explain basic working of Integrators? Figure shows a noninverting integrator, which can be seen to be a negative impedance converter added with a resistor and a capacitor. N

Sommerfield’s free electron theory, Write down basic postulates of sommerfi...

Write down basic postulates of sommerfield’s free electron gas model. Show that the number of energy states per unit energy is given by g(E) = 4Rv/h 3 (2m) 3/2 E 1/2 .  What is

Illustrate power semiconductor devices, Q. Illustrate Power Semiconductor D...

Q. Illustrate Power Semiconductor Devices? Since the advent of the first thyristor or silicon-controlled rectifier (SCR) in 1957, tremendous advances have been made in power se

Sinusoidal, Give the examples of sinusoidal with two equations?

Give the examples of sinusoidal with two equations?

Draw the circuit of a two stage rc coupled amplifier, Q. Draw the circuit o...

Q. Draw the circuit of a two stage RC coupled amplifier?

Customer indexing scheme, Customer Indexing Scheme: Customer indexing ...

Customer Indexing Scheme: Customer indexing and asset codification system provides a platform to enable the utilities to generate verifiable and validated data of consumers an

Competition, how to be prepare for gate....

how to be prepare for gate....

Meters and measurements, The subject of electrical measurements is such a l...

The subject of electrical measurements is such a large one that entire books have been written on the topic. Only a few basic principles will be introduced here. Practical measurem

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd