Meter field testing and installation practices, Electrical Engineering

Assignment Help:

Meter Field Testing and Installation Practices

Here, we discuss the installation, commissioning and field testing of meters.

Energy Meters - Installation and Commissioning

The meters are linked before the consumer's isolating device (Main Switch) that might be a moulded case miniature circuit breaker, circuit breaker, or an ironclad switch fuse unit. At the time of commissioning, every meter is tested at site through the owner. A reference standard meter of 0.2 classes or better is used for testing.

Supply Side Wiring

The supply side wiring is the responsibility of the utility and the subsequent must be ensured although carrying it out:

a) The supply wires given are of suitable rating.

b) In case of more than one meter on one service line, it is preferable to use bus-bars. While a number of meters are linked to single distributing mains for registering electricity supplied to various consumer loads, separate service lines - phase(s) and neutral, are used for every meter. Each independently metered consumer load is directly linked to distributing mains by its meter connected in specified phase sequence so as to meet accuracy requirements of relevant standard.

c) The supply wire is properly terminated.

d) The connection is as per links diagram mentioned on meter.

e) Utility should use its own earthing for its devices.

Utility gives phase and neutral supply to the consumers. The neutral is used for carrying return current only. The neutral of one consumer should not be linked to other consumers who have independent and separate supply connection. Utility provides separate neutral to every consumer up the metering point and similar is used through the consumer. The consumer ensures in which all the correct wiring practices are followed and neutral is not looped along with another consumer or meters in the similar premises.  Consumer should not earth the neutral after the metering point. While there are multiple meter installations, bus bar arrangement is used for neutral, so that looping is prevented.


Related Discussions:- Meter field testing and installation practices

transmisson medium, Can I find out the salution of electrods Transmissio...

Can I find out the salution of electrods Transmission medium light sound uncoupling magnet for high dc cycle.

Matlab codes for transportation problem, i need matlab codes for the minimu...

i need matlab codes for the minimum cell cost method to start the initial feasible solution and the stepping stone method to find the optimum value

Determine the capacitor and inductor voltages, Experiment • Wire the circu...

Experiment • Wire the circuit shown in Figure. Connect the three oscilloscope channels as shown in Figure. • Select the sinusoidal waveform. Adjust the frequency of the input volt

Compute the maximum electromagnetic power, Q. A four-pole dc machine with 7...

Q. A four-pole dc machine with 728 active conductors and 30mWb flux per pole runs at 1800 r/min. (a) If the armature winding is lap wound, find the voltage induced in the armatu

Find the open-circuit voltage amplification of the circuit, (a) Figure show...

(a) Figure shows a circuit containing an amplifier block. Find the open-circuit voltage amplification of the circuit. (b) Let the output terminals be connected to a load resista

Disaster management, role of electrical engineer in disaster management

role of electrical engineer in disaster management

Dpr preparation, DPR PREPARATION: 1.  Asset Management 2.  System O...

DPR PREPARATION: 1.  Asset Management 2.  System Operations and Despatch 3.  Field Operations 4.  Customer Processes 5.  Corporate Processes The details covered

Configured the dual processor architecture, Configured dual processor archi...

Configured dual processor architecture  In centralized SPC, dual processor architecture can be configured to operate in following one of three modes: 1.  Standby mode: In

Revision of basics, Revision  of Basics Although  it is  assumed in th...

Revision  of Basics Although  it is  assumed in this book  that the  reader has  enough  knowledge of  various number systems ( binary, octal and hexadecimal and their relation

Plc, in industry

in industry

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd