Meter field testing and installation practices, Electrical Engineering

Meter Field Testing and Installation Practices

Here, we discuss the installation, commissioning and field testing of meters.

Energy Meters - Installation and Commissioning

The meters are linked before the consumer's isolating device (Main Switch) that might be a moulded case miniature circuit breaker, circuit breaker, or an ironclad switch fuse unit. At the time of commissioning, every meter is tested at site through the owner. A reference standard meter of 0.2 classes or better is used for testing.

Supply Side Wiring

The supply side wiring is the responsibility of the utility and the subsequent must be ensured although carrying it out:

a) The supply wires given are of suitable rating.

b) In case of more than one meter on one service line, it is preferable to use bus-bars. While a number of meters are linked to single distributing mains for registering electricity supplied to various consumer loads, separate service lines - phase(s) and neutral, are used for every meter. Each independently metered consumer load is directly linked to distributing mains by its meter connected in specified phase sequence so as to meet accuracy requirements of relevant standard.

c) The supply wire is properly terminated.

d) The connection is as per links diagram mentioned on meter.

e) Utility should use its own earthing for its devices.

Utility gives phase and neutral supply to the consumers. The neutral is used for carrying return current only. The neutral of one consumer should not be linked to other consumers who have independent and separate supply connection. Utility provides separate neutral to every consumer up the metering point and similar is used through the consumer. The consumer ensures in which all the correct wiring practices are followed and neutral is not looped along with another consumer or meters in the similar premises.  Consumer should not earth the neutral after the metering point. While there are multiple meter installations, bus bar arrangement is used for neutral, so that looping is prevented.

Posted Date: 2/6/2013 8:08:25 AM | Location : United States







Related Discussions:- Meter field testing and installation practices, Assignment Help, Ask Question on Meter field testing and installation practices, Get Answer, Expert's Help, Meter field testing and installation practices Discussions

Write discussion on Meter field testing and installation practices
Your posts are moderated
Related Questions
Normal 0 false false false EN-IN X-NONE X-NONE RECTIFIERS AND INVERTERS

A bandpass filter design can be accomplished through the cascade connection shown in Figure, where the frequencies between the two cutoffs fall in the passband of both filters and

Describe in brief how email system works Following is a simple description of how email system works: -  Sender composes a message (and attaches a file if required) and send

Describe the term (i) Automation (ii) Automated lines 04 List out the reasons for automation and discuss in detail the process of work part transport.

Q. Explain Television signal transmission? Television signals in television signal transmission are the electric signals generated by converting visual images through raster (T

Data analysis in GIS: Therefore, GIS consists of the following: 1.  Database - for storage and retrieval of information. The database forms the foundation of the GIS syst


Q. Explain the conditions under which an RC circuit behaves as Integrator? Integrator is a circuit in which the output voltage is proportional to the integral of the input. Out

Q. Consider the synchronous counter shown in Figure of the text. (a) Draw its timing diagram. (b) Show the implementation of the same synchronous counter using D flip-flops.

L=0.0053nH, C=15µF find the operating frequency of series LC circuit. What factors decides capacitance ..