Inspection and quality control certificate, Civil Engineering

Q. Inspection and Quality Control Certificate :

A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certified. In case of any defect in the bearing, the whole 'lot' shall be rejected by the inspector and certified accordingly.

The bearings shall be transported to the bridge site after final acceptance and should be accompanied by an authenticated copy of the test certificate. An information card giving the following details should be appended to the test cerftificate:

1. Name of manufacturer

2. Date of manufacture

3. Grade of elastomer

4. Bearing dimensions

5. Production Batch No.

6. Accpetance lot No.

7. Date of testing

8. Specific bridge location

9. Explanation of markings on the bearing, if any.

Posted Date: 6/12/2013 8:04:36 AM | Location : United States







Related Discussions:- Inspection and quality control certificate, Assignment Help, Ask Question on Inspection and quality control certificate, Get Answer, Expert's Help, Inspection and quality control certificate Discussions

Write discussion on Inspection and quality control certificate
Your posts are moderated
Related Questions
Side clearance of pipes in trenches From the design point of view, it's predominant to minimize the width of pipe trenches due to thebelow reasons: (i)  Higher cost of exca

Explain the Selected Bridges - Underwater Inspection? Those bridges, which require underwater inspection must be noted for individual inspection and inventory records as well b

any new innovative metods to protct building from disater

Explain the Typical Wastewater Characteristics? Total Suspended Solids = 100 - 350 mg/L (200 mg/l is the typical value)    BOD 5 = 100-300 mg/L (200 mg/L is the typical val

tack rivet figures with connections

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

briefly explain the stacking of materials in the site for general building?

what are The regulations and specification that followed for compaction works for earth dam in Oman.

Determine the moment of inertia with respect to the x axis for the shaded area shown (Figure 2) . The dimension is a = 2.00m .

A credit card advertises a nominal rate of 18% compounded monthly. If no monthly payments are made, the effective annual interest rate is most nearly: The actual rate is, (18%