How to design marginal embankments, Civil Engineering

Q. How to design Marginal Embankments?

Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below.
Distance of marginal embankment from the river bank should neither be too short nor too long. If the embankment is too near the river, velocity along the bank can become high.

Normally this velocity is not allowed to be more than 0.9 to 1.2 m/s. On the other hand if the embankment is far too away, the very purpose of providing the embankment can be defeated. Current Indian practice is to roughly maintain a distance of 3 times the width given by Lacey formula in between the flood embankments on either banks of the river, though this thumb rule may not be applicable in case of all alluvial rivers. The flood embankment is carried on a ridge or high bank. In alluvial rivers a ridge or high ground is often formed near the bank line due to deposition of suspended sediment when river overflows the bank. Protrusions and sudden changes in alignment forming kinks are as far as possible avoided. Structures like bridges and barrages obstruct free downstream movement of meanders. Immediately upstream of such structures, the meander belt, therefore, widens and becomes almost double. While fixing location of marginal banks, this field experience needs to be kept in view.

Posted Date: 6/5/2013 5:58:51 AM | Location : United States







Related Discussions:- How to design marginal embankments, Assignment Help, Ask Question on How to design marginal embankments, Get Answer, Expert's Help, How to design marginal embankments Discussions

Write discussion on How to design marginal embankments
Your posts are moderated
Related Questions

Stone Soling: One of the early practices in road construction was to provide a stone soling 150-225 mm in thickness. The stones are laid by manual labour, and stone spalls ar

how do I draw sections(longitudinal and cross sections)?

Define Scour - Underwater Inspection of Bridges? Whenever a bridge crosses a waterway, even a small or intermittent one, scour is a dangerous effect that can damage bridge pier

does felid scope in civil eng. if we start consiltancy job

Question What are the major functions of following features observed in a typical manhole ? Answer (i) Groove near benching, (ii) R.S.J. (iii) double seal manhole cove

Question Design of concrete structures, normally most aggregate sizes are adopted with scopes from 10mm to 20mm. Does an increase of most aggregate size advantage structures ?

Question What is the major purpose of carrying out water absorption test for precast concrete pipes? Answer Cement will mix with additional water than is compulsory t

Pls provide matlab design for transportation engg.

Example : Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what m