How to design marginal embankments, Civil Engineering

Q. How to design Marginal Embankments?

Design aspects of marginal embankments are similar to those of approach banks. The aspects needing special attention are dealt with below.
Distance of marginal embankment from the river bank should neither be too short nor too long. If the embankment is too near the river, velocity along the bank can become high.

Normally this velocity is not allowed to be more than 0.9 to 1.2 m/s. On the other hand if the embankment is far too away, the very purpose of providing the embankment can be defeated. Current Indian practice is to roughly maintain a distance of 3 times the width given by Lacey formula in between the flood embankments on either banks of the river, though this thumb rule may not be applicable in case of all alluvial rivers. The flood embankment is carried on a ridge or high bank. In alluvial rivers a ridge or high ground is often formed near the bank line due to deposition of suspended sediment when river overflows the bank. Protrusions and sudden changes in alignment forming kinks are as far as possible avoided. Structures like bridges and barrages obstruct free downstream movement of meanders. Immediately upstream of such structures, the meander belt, therefore, widens and becomes almost double. While fixing location of marginal banks, this field experience needs to be kept in view.

Posted Date: 6/5/2013 5:58:51 AM | Location : United States







Related Discussions:- How to design marginal embankments, Assignment Help, Ask Question on How to design marginal embankments, Get Answer, Expert's Help, How to design marginal embankments Discussions

Write discussion on How to design marginal embankments
Your posts are moderated
Related Questions

Determine the flow velocity in 2,000 ft of 8 inch diameter piping flowing full. The energy lost in piping is 54 ft. Use nominal pipe diameter and C = 140.     Solution: Use v =

Please help me to write a c program to find strength and efficiency of lap joint, single cover butt joint, double cover butt joint

State about the pre-tensioned concrete beam A pre-tensioned concrete beam, 200 mm wide and 300 mm deep, is prestressed by straight wires carrying an initial force of 150 kN at

Define the Cost of shock transmission unit? There is a keen competition among the few STU manufacturers. For the second Bassein Creek Bridge, the average cost of two STUs of ca

define scale and sludge and mention the scale and sludge forming substance and explain the prevention methods


what is grouting?

what is difference between design moment, nominal, required, resisting and ultimate moment ?

TERMINOLOGY 1. Focus: The point on the fault where slip begins is the focus. It is also called as hypocentre 2. Epicentre: The point vertically above the focus on the su