Disparity between working stress and limit state approach, Civil Engineering

Assignment Help:

Question

What is key disparity between working stress approach and limit state approach?

Answer

Working stress approach, service loads are used in whole plan and strength of material is not utilized in full extent. In this means of plan, stresses acting on structural members are intended based on flexible way and they are designed not to beat certain acceptable values. In fact, whole structure during lifespan may only knowledge loading stresses far below ultimate state and that is reason why this means is known as working stress approach. In such scenario, most economical plan can hardly be obtained by using working stress advance that is now commonly used in design of temporary works.

For maximum state approach, for each material and load, a biased safety factor is assigned independently depending on material properties and load lands. So, each element of load and material properties is exactly assessed resulting in an extra refined and accurate analysis of structure. In this relation, material strength be capable of be utilized to its greatest value during its lifespan and loads be capable of be assessed with practical probability of occurrence. Boundary state approach is frequently used for majority of reinforced concrete design as it ensures utilization of material strength with least construction price input.

 


Related Discussions:- Disparity between working stress and limit state approach

Instruments, description and details about distomat

description and details about distomat

Hoyers long line system pre-tensioning, Hoyers long line system pre-tension...

Hoyers long line system pre-tensioning When concrete attains the required strength,  jacks  are released and tendon wires in-between various units are cut.

Casing has to be left in for mini-piles, Question What are thought in d...

Question What are thought in determining whether casings have to be left in for mini-piles ? Answer Contrary to most of pile design, design of min-piles is controlled

Settlement due to increasing load on surrounding soil, Q. Settlement due to...

Q. Settlement due to Increasing Load on Surrounding Soil? When any portion of the ground surface  has been loaded, it causes  the surface  of adjacent soil also to tilt and set

Large scale integration chips have between the components, Large scale int...

Large scale integration chips have between the  components? Answer : It is between 100 and 1000 components.

Construction health & safety, List different access equipment & their uses ...

List different access equipment & their uses wih pictures

Explain the confined aquifer and piezometric surface, Explain the Confined ...

Explain the Confined Aquifer and Piezometric Surface Confined Aquifer Groundwater is confined by impervious geologic stratums on all sides. The water may be under pressure.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd