Delay of bituminous laying on top of sub-base,, Civil Engineering

Assignment Help:

Question

In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base?


Answer


When there is a delay between bituminous laying of different bituminous layers such as roadbase, base course. A tack coat is applied on top of bituminous layers as it helps to improve better bonding between bituminous materials. If there is not enough bonding between adjacent bituminous layers, they perform as separate independent layers which are able to barely resist traffic loads. When applying tack coat, it have to be sprayed uniformly on bituminous surface and allowed for enough curing. Hot bituminous material laid on top of coat would soften it, enabling tack coat to partly fill voids in bituminous materials. For emulsified asphalt category tack coats, they are usually diluted with water in order to achieve an additional uniform application without excessive usage of asphalt. After subsequent compaction is carried out, coat would be interlocked with bituminous materials. On other hand, care should be taken to make sure that excessive coat will not be laid, or else slippage or shear cracks in bituminous material would occur due to relative thick layer of tack coat applied.

Though, for sub-base surface, priming coat in its place of tack coat might be applied in event of a delay in laying of bituminous layer on top of sub-base layer. Function of primer serves to maintain existing surface condition for a longer period and it also provides an impervious surface to stop ingress of water or water beating by evaporation.

Besides, it fills surface voids and protects sub-base from adverse weather setting. In adding up, it and helps to promote adhesion between adjacent road layers and to harden surface.

 


Related Discussions:- Delay of bituminous laying on top of sub-base,

Describe principles of river protection works, Q. Describe Principles of ri...

Q. Describe Principles of river protection works? Determination of design discharge for a bridge is sometimes required to be based on flood marks left during unprecedented abno

Concrete cracking, Attached information shows construction details of a wat...

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped

Surveying, 3 types of obstacles in chaining detail

3 types of obstacles in chaining detail

Bridge, how to account for density?

how to account for density?

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Temporary repairs to rail fracture, Q. Temporary Repairs to rail fracture? ...

Q. Temporary Repairs to rail fracture? If a welding party is not readily available, the fracture shall be repaired by using a cut-rail (not less than 4 meter long) and clamped/

Write a short note on economic span of a bridge, Q. Write a short note on E...

Q. Write a short note on Economic Span of a Bridge? The span for which the total cost of bridge will be minimum is known as the economic span. The ratio of Cost of super str

Softening point test, Softening Point Test: The temperature at which ...

Softening Point Test: The temperature at which bitumen softens is determined by the "Ring and Ball" test (Figure). (a) Diagram of Apparatus at Beginning of Test  (b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd