For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

1999_Calculate the amount of import or export.png

Solution:

By inspection, the project has a combination of areas where there are imports and exports to bring the entire site to elevation 90-ft.Further, the multiple choices given for the answer should be analyzed.There is a spread of approximately 20% among the choices which suggests a broad perspective analysis to determine the solution. 

The figures to the right illustrate a broad based analysis.  Assume one grid:

  Existing          90.50-ft

  Proposed        90.00-ft

  Cut                 0.50-ft

  Total Export = [150-ft x 300-ft x 0.50-ft] ÷ 27ft3/yd3 = 833-yd3

 


Related Discussions:- Calculate the amount of import or export

Street originate in the plumbing term street ell, How did street originate ...

How did street originate in the plumbing term street ell? Ans) A "street ell" may have gotten its name due to it describes a 90° fitting particularly useful in tight, street dit

Physics, about lenses & mirrors for assignment

about lenses & mirrors for assignment

What is bore hole, What is Bore Hole In exploration of  area of  limit...

What is Bore Hole In exploration of  area of  limited extent  the borings should preferably be located near the comers of  the area. A minimum of three holes should be made un

Bond performance of bar reinforcement, Question Does occurrence of rust hav...

Question Does occurrence of rust have adverse collision to bond performance of bar reinforcement ? Answer In fact, presence of rust in bars cannot have adverse impact to the bo

Calculate the net annual profit - construction management, A heavy equipmen...

A heavy equipment rental company uses a high interest rate of 30% for the rental of a specialty heavy haul dump truck.  The net annual profit for this investment is most nearly:

Estimate the jam density in one lane of trucks, At a large port facility ne...

At a large port facility near New York City tractor-trailer trucks are lined-up in long queues as their drivers wait to have their containers inspected and documents processed.  As

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd