Explain measured shovel packing, Civil Engineering

Assignment Help:

Explain Measured shovel Packing

Measured shovel Packing essentially consists of accurate measurements of track defects particularly the unevenness and voids caused in the course of service and attending the same by placement of measured quantity of small sized stone chips under the sleeper to bring the track to predetermined levels. The compaction of chips is obtained by passage of traffic. The extent to which the track is required to be lifted is calculated by measuring the longitudinal unevenness in the track after applying corrections for cross levels and voids under the sleepers. The longitudinal levels are measured with the help of optical instruments called viseur and mire and the voids under the sleeper bed are assessed by a ball ended rod called canne a boule and checked with the help of a mechanical device called dansometer. The track is lifted by 40 mm by special type of non infringing jacks and a measured quantity of stone chips is then placed in the sleeper bed with the help of special type of packing shovels. The jacks are than tripped off and the alignment is finally corrected. It may be clarified here that track to be maintained by MSP needs a well settled ballast cushion bed and stable formation and such MSP should neither be used immediately after track renewal and deep screening nor after renewal of a large number of sleepers nor when the lift required is more than 80 mm.


Related Discussions:- Explain measured shovel packing

Calculate the cost to finance the construction project, A contractor is bid...

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Is kerb necessary in road pavements, Question Is kerb necessary in road...

Question Is kerb necessary in road pavements? Answer In universal, kerbs are crucial in road pavements due to next cause- (i) They supply strength to sides of road

Conics, what is the eccentricity of ellipse

what is the eccentricity of ellipse

What is objective method of assessment, Q. What is objective method of asse...

Q. What is objective method of assessment? Track recording consists of objective method of assessment of the quality of track with the help of sophisticated equipments. A conti

Design an equalization basin with a safety factor, A storm occurs with rain...

A storm occurs with rain of varying intensity falling over a commercial area. The area has a combined sewer system. Two interceptor sewers direct flow to the wastewater treatment p

State the moulds in prestressed concrete, State the Moulds in Prestressed C...

State the Moulds in Prestressed Concrete Moulds for pre-tension work should be sufficiently strong and rigid so that they can withstand the effects of placing and compacting th

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

#titl, Two readings ie 1.64m and 0.73m were taken during leveling procedure...

Two readings ie 1.64m and 0.73m were taken during leveling procedure to define the slope of a centerline of a bridge at points A and B. If distance AB=50 m, find the slope of line

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd