Define the in-depth inspections for bridge, Civil Engineering

Assignment Help:

Define the In-depth inspections for Bridge?

In-depth inspection is a detailed inspection of one or more members below the water level to detect any deficiencies not readily apparent using routine inspection procedures. The marine growth, if any, needs to be cleaned for surface inspection and such cleaning is generally restricted to sample areas of the entire structure.

One or more of the following conditions may dictate the need for an in-depth inspection.

- Inconclusive results from a routine inspection

- Critical structures whose loss would have significant impact on life or property

- Unique structures whose structural performance is uncertain

- Prior evidence of distress

- Adverse environmental conditions such as brackish and polluted water.


Related Discussions:- Define the in-depth inspections for bridge

Why are steel plates inserted inside bearings, In designing of elastomeric ...

In designing of elastomeric bearings, why are steel plates inserted inside Bearings?

Explain about best hydraulic section, Q. Explain about Best hydraulic secti...

Q. Explain about Best hydraulic section? The best hydraulic section of an open channel is considered by provision of maximum discharge with a given cross sectional area. Chann

Show the differences between GGBS and PFA, Q. Show the Differences Between ...

Q. Show the Differences Between GGBS and PFA? The use of GGBS as substitute of cement improves smaller reliance on PFA. Particularly GGBS is supposed to be more compatible with

Finite Element Analysis- MATLAB problem, I am currently enrolled in a gradu...

I am currently enrolled in a graduate Civil Engineering course in Finite Element Analysis. The final assignment and project both deal with coding in MATLAB and I am having great di

Define dupuit equations for unconfined aquifers, Define Dupuit Equations fo...

Define Dupuit Equations for Unconfined Aquifers Using natural log: Q = ΠK((h 2 ) 2 - (h 1 ) 2 )/ln(r 2 /r 1 )     Using log 10 : Q = K((h 2 ) 2 - (h 1 ) 2 )/((1,055)l

State the process to calculate the transmission length, State the process t...

State the process to calculate the Transmission Length It is the distance required at the end of a concrete member for developing the maximum tendon stress by bond.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd