A purchasing manager at a local manufacturing company was quoted an estimated time of 47 labor hours to produce a prototype for a new product. The supplier also estimated the learning rate to fall between 82 and 85 percent.
a. What percentage decrease should the purchasing manager expect in required manufacturing by the fifth unit?
b. Suppose an expected decrease of approximately 37 percent over the first units was 30 percent. What should the purchasing manager infer about the suppliers efficiency?
One of your Taiwanese suppliers has bid on a new line of molded plastic parts that is currently being assembled at your plant. The supplier has bid $0.10 per part, given a forecasted demand of 220,000 parts in year 1; 330,000 in year 2; and 490,000 i..
This week, through our readings and discussion, we explored how we can make the most of failure, how we can expand our horizons, and the notion of ethical awareness. Additionally, we have begun to explore the following course outcomes: identify the i..
”Psychological Testing at Dayton Hudson,” one of the criticisms was that: ___________
Demonstrate how information systems can help businesses use synergies, core competencies, and network-based strategies to achieve competitive advantage.
list the general requirements of an LLC, partnership and corporation. Find an example of a business organization that is an LLC.
Amy’s project is to produce 300 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Quantify cost variance. Is the project ahead or behind budget? Quantify schedule variance. Is the..
the following information is gathered for a project.activityactivity time daysimmediate predecessorsa2-b4ac5ad2be1bf8b
Cars arrive at the drive-thru windows at a local fast food at the rate of 4 every 10minutes. The average service time is 2 minutes. The Poisson distribution is appropriate for the arrival rate and service times are exponentially distributed. What is ..
Calculate by hand how many labor-hours would be available in January and February. Calculate by hand the total costs in January and February.
Evaluate the ethical issues associated with downsizing an organization by reducing its labor force to increase the organization’s long-run chance of survival. What other ethical issues can you identify in the practice of organizational change, as you..
Research 3 companies and determine how the business could develop cost estimates for a specific product or service that they offer and discuss whether this would impact their project outcomes?
PERT Method of project scheduling - PERT requires three time estimates for scheduling a given activity. PERT assumes that the actual activity times are distributed according to the beta probability distribution.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd