Amy’s project is to produce 300 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Performance data for the project at the end of week three is presented below:

190 total units were planned to be produced

200 units have actually been produced

The financial manager reported that the business had actually spent $15,000 on the project by the end of week three.

Answer the following questions; show all work:

1. Quantify cost variance. Is the project ahead or behind budget?

2. Quantify schedule variance. Is the project ahead or behind schedule?

3. Quantify cost performance efficiency. Is the project performing better or worse than planned?

4. Quantify schedule performance efficiency. Is the project performing better or worse than planned?

5. What is the forecast of project cost at completion assuming current cost performance efficiency remains the same? How much budget variance is expected at completion?

6. What is the forecast of funding needed to complete the project (from this point forward)?

7. What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?

8. As the project financial manager, what recommendations would you make?

Reference no: EM13780564

Questions Cloud

Importance on eyewitness memory : Describe at least one research study from a peer-reviewed journal that investigated how eyewitness memory can be affected by false memories.
Do you think the criminal justice system failed victims : In a 2 page paper, using APA style formatting, based on your readings and research, do you think the criminal justice system failed John Gardner's victims when his parole was not revoked
Write a paper discussing managerial issues : Write a paper discussing managerial issues associated with managing an organization's IS infrastructure.
Purpose and meaning of life : Why are we here? What can bring meaning and or purpose to our life? How would you answer these questions?
Quantify cost variance-is project ahead or behind budget : Amy’s project is to produce 300 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Quantify cost variance. Is the project ahead or behind budget? Quantify schedule variance. Is the..
What are the consequences of trying a juvenile as an adult : What are the consequences of trying a juvenile as an adult? Did the juvenile have the mental capacity to know right from wrong
Discuss the legal and ethical basis for advance directives : research and discuss the legal and ethical basis for Advance Directives such as the Living Will and Durable Power of Attorney for healthcare.
What developmental theory do you find most interesting : What developmental theory do you find most interesting? Most challenging? Most useful to your work as a human service professional? Explain why you feel this way and how you plan to use these concepts to support your clients.
Identifying major competitors products, trends and market : What is meant by "a Competitive Profile Matrix (CPM)"? How is this related to a company's strategy? --Construct a CPM for Royal Caribbean --Briefly identify the industry in which Royal Caribbean operates, identifying major competitors, products, tren..

Reviews

Write a Review

Operation Management Questions & Answers

  What is the percentage of productivity increase

Riverside Metal Works produces cast bronze valves on a 10-person assembly line. On a recent day, 160 valves were produced during an 8-hour shift.

  Construct the product structure tree

a) Construct the product structure tree for both fans and their component parts. b) Complete the MRP for the fans and their component parts.

  Critically discuss the likely impact of emerging trends

Critically discuss the likely impact of emerging trends and/or issue(s) on the future of the operations function within your organisation.

  It must have at least 8 rows for factors which you feel are

prepare in a table format a swott analysis on any real company in the auto industry. as you prepare your analysis it

  Discuss different roles people play in work groups

please discuss different roles people play in work groups? Please share the role you predominantly played in project or work groups. Make this a very short answer.

  Do you believe teamwork is important

Your response should be a combination of information you researched and your feelings and ideas about the value and importance of teams.

  Request information on cost justification and roi

Choose a major capital piece of equipment to be used in the radiology department of a hospital (e.g., CAT scan, MRI, nuclear medicine camera, etc.). Next, research and choose a vendor. Vendors such as GE, Siemens, or others can be located on the I..

  Wildlife and recreation program

Case Study International Paper’s Wildlife and Recreation Program

  What are the standard rules of overtime pay

What are the standard rules of overtime pay? Provide examples of why it is not always simple to administer. Address issues such as double pay, pyramiding, compulsory overtime, and fair distribution.

  Why is it important for national health information

Why is it important for national health information management organizations to agree on how to standardize paper and electronic medical forms?

  Compare and contrast the theories of scientific management

management and organizational environments please respond to the followingmiddot compare and contrast the theories of

  Case study - mountain states electric service

Mountain States Electric Service is an electrical utility company serving several states in the Rocky Mountains region. It is considering replacing some of its equipment at a generating substation.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd