Given EVM data, estimate the cost at completion of a project using the method "EAC based on Combined Cost and Schedule Performance." Reference Figure 11-3. (Answers are approximate) BCWS = $82.2M BCWP = $70.5M ACWP = $95.5M BAC = $105.5M Assume PMB validity is maintained

$150M

$160M

$170M

$130M

Use Excel spreadsheet with this problem with sums embedded.

Reference no: EM1343220

Questions Cloud

Relationship of variables as relate to project management : Project planning need only be a one-time exercise in order to get an idea of the project and its major ramifications.
Adjunct professor teaching project management : What five essential theoretical lessons would you share with your students that you feel are the most important in assuring professional success as a project manager?
What is the incremental profit : What is the incremental profit and to get a rough idea of the project's profitability, what is the project's expected rate of return for the next year and should the firm make the investment
Benefits of project management and safety stock : What are the benefits of project management and provide an example of how you have relied on project management
Eac based on combined cost and schedule performance : Given EVM data, estimate the cost at completion of a project using the method "EAC based on Combined Cost and Schedule Performance.
Implement ppm for projects already in process : Project Management- Implement PPM for projects already in process - When a firm decides to implement PPM into its way of managing projects, one of the first questions that comes to mind is what will happen to those projects already in progress and/..
What items need to be addressed in defining the scope : The project scope describes what will be delivered as part of the project, and in some ways, it can be likened to the term vision.
What would you use to determine if project was successful : A project to bake a cake would measure what and what would you use to determine if the project was successful
What types of information can we learn about a project : What types of information can we learn about a project by reviewing the project schedule and all the information used to generate it?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd