We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other means. Thermo-electric prestressing is just another method of stretching the tendon wiers. We know that if we increase the temperature of a metal, it expands. As the name suggests, in Thermo-electric prestressing, temperature of tendon wires is increased by passing electric current for a short duration. This temperature increase, taking place within 3-5 minutes, may be of an order of 300-400°C. The bars, which may undergo an expansion of about 0.4-0.5% in length, try to shorten at cooling butare checked by fixed anchors at the two ends. 


Related Discussions:- What is thermo-electric prestressing

Explain information processing and perception, Explain Information Processi...

Explain Information Processing and Perception - Driver Performance The time required to respond successfully to any driving situation, such as an emergency, involves four stage

State the loss of prestress, State the Loss of prestress Loss of prestr...

State the Loss of prestress Loss of prestress due to elastic shortening definitely occurs in pre-tensioned concrete members. But in post-tensioned members it does not occur if

Determine about the long-term deflections, Determine about the long-term de...

Determine about the long-term deflections For long-term deflections, the total long-term deflection due to the prestressing force, dead load and any sustained imposed load may

Self compacting concrete, what will be the w/c ration and cement/fly ash ra...

what will be the w/c ration and cement/fly ash ration for the particular mix design

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Calculate the settlement at the centre of the mat, A mat foundation of 15...

A mat foundation of 15 m x 15 m and weighing 20000 N/m 2 is to be constructed on the surface of a soil strata. The profile is given in Figure. The number of squares enclosed i

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

#title beam design, how to calculate loads acting on a simple supported bea...

how to calculate loads acting on a simple supported beam of 220width by 425 depth #Minimum 100 words accepted#

Well foundation in bridges, what is the purpose of 6mm ms sheet for stainin...

what is the purpose of 6mm ms sheet for staining in various conditions at inner &outer of well

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd