What is the Sludge Volume Index?

Two 1 L samples of mixed liquor are taken from a lagoon. After settling for 30 min in a graduated cylinder, 250 mL of solids have settled out in the first sample. The total suspended solids concentration (MLSS) in the second sample is found to be 2300 mg/L.

(a) What is the sludge volume index?

(b) What is the theoretical required sludge recycle rate?  

Ans:

(a) From eq for SVI, SVI = 1000Vsettled, mL/L/ Xmg/L

= (1000mg/g)(250ml/L)/2300mg/L = 109mL/g

(b) From Eq for, R = Vsettled, mL/L/ 1000-Vsettled, mL/L

250mL / 1000mL - 250mL = 0.33


Related Discussions:- What is the sludge volume index

Explain the departure of a line - transportation, Explain the Departure of ...

Explain the Departure of a line - Transportation Departure of a line is the distance that the line extends in an east or west direction. A line that runs towards east has a pos

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Function of reinforced concrete infill, Function of reinforced concrete inf...

Function of reinforced concrete infill in marine piling system of steel tubular pile with reinforced concrete infill Reinforced concrete is designed to fill void space inside

Particle size distribution - soil compaction, Particle Size Distribution (G...

Particle Size Distribution (Gradation): The particle size distribution is determined by passing the aggregates through a set of standard IS sieves (Figure) and determining th

Define the finish to finish activity, A finish-to-finish activity is best d...

A finish-to-finish activity is best described as: The "from" activity must finish before the "to" activity can finish The "from" activity must finish before the "to" acti

Explain the clearance interval - signalized intersections, Explain the Clea...

Explain the Clearance Interval - Signalized Intersections  Also known as "Red Clearance Interval" and "All Red"        r = (w+L) / V - If there is no pedestrian traffic r

Design of steel structure, design acolumn spice for column sections SC 250 ...

design acolumn spice for column sections SC 250 and SC 220 carrying a load of 500 KN

Determine the thermal stress in the bar, Determine the thermal stress in th...

Determine the thermal stress in the bar: A stepped bar made of aluminum is held between two supports. The bar is 900 mm in length at 38ºC, 600 mm of which is having a diameter

Parabola, how to draw a parabola

how to draw a parabola

Solid mensuration, the two sides of a triangle are 17cm and 28 cm long, and...

the two sides of a triangle are 17cm and 28 cm long, and the length of the median drawn to the third side is equal to 19.5. find the distance from an endpoint of this median to the

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd