What is the sludge volume index, Civil Engineering

Assignment Help:

What is the Sludge Volume Index?

Two 1 L samples of mixed liquor are taken from a lagoon. After settling for 30 min in a graduated cylinder, 250 mL of solids have settled out in the first sample. The total suspended solids concentration (MLSS) in the second sample is found to be 2300 mg/L.

(a) What is the sludge volume index?

(b) What is the theoretical required sludge recycle rate?  

Ans:

(a) From eq for SVI, SVI = 1000Vsettled, mL/L/ Xmg/L

= (1000mg/g)(250ml/L)/2300mg/L = 109mL/g

(b) From Eq for, R = Vsettled, mL/L/ 1000-Vsettled, mL/L

250mL / 1000mL - 250mL = 0.33


Related Discussions:- What is the sludge volume index

Treatment plant - sewer construction, Treatment plant - sewer construction:...

Treatment plant - sewer construction: Problem: How many kg of primary and secondary dry solids needs to be processed daily from the treatment plant? Solution An a

Pcc, Specific Gravity & Water Absorption of Fine Aggregate

Specific Gravity & Water Absorption of Fine Aggregate

Explain about best hydraulic section, Q. Explain about Best hydraulic secti...

Q. Explain about Best hydraulic section? The best hydraulic section of an open channel is considered by provision of maximum discharge with a given cross sectional area. Chann

Timber, TIMBER Timber refers to wood utilized for construction works. A...

TIMBER Timber refers to wood utilized for construction works. Actually the word timber is derived from an old English word 'Timbrian' that means 'to build'. A tree that yields

Solid block -calculating for design mix, Good evening sir, solid block''s d...

Good evening sir, solid block''s design mix calculated generally please explain and derive .

How double drainage occur, The loading period for a building extended from ...

The loading period for a building extended from Feb., 1957 to Feb., 1959. In Feb., 1962, the average measured settlement was found to be 117 mm. The ultimate settlement was expecte

Explain precedence relationships - construction management, Explain the Pre...

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish

Define the term - post-tensioned concret, Define the term - post-tensioned ...

Define the term - post-tensioned concret In the Prescon and B.B.R.V. systems button heads are created at the ends of tendons. In the case of Prescon system, 2 to 130 tendon wir

Aggragates, what are the classification og aggregates?

what are the classification og aggregates?

Define inspection of steel or cast iron substructures, Define Inspection of...

Define Inspection of Steel or Cast Iron Substructures? Corrosion is the principal cause of deterioration in steel waterfront substructures. On bare un-protected steel pilings,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd