What is the sludge volume index, Civil Engineering

Assignment Help:

What is the Sludge Volume Index?

Two 1 L samples of mixed liquor are taken from a lagoon. After settling for 30 min in a graduated cylinder, 250 mL of solids have settled out in the first sample. The total suspended solids concentration (MLSS) in the second sample is found to be 2300 mg/L.

(a) What is the sludge volume index?

(b) What is the theoretical required sludge recycle rate?  

Ans:

(a) From eq for SVI, SVI = 1000Vsettled, mL/L/ Xmg/L

= (1000mg/g)(250ml/L)/2300mg/L = 109mL/g

(b) From Eq for, R = Vsettled, mL/L/ 1000-Vsettled, mL/L

250mL / 1000mL - 250mL = 0.33


Related Discussions:- What is the sludge volume index

WATER RESOURCES SYSTEM PLANNING AND MANAGEMENT, Two crops are grown on land...

Two crops are grown on land of 20ha.The cost of raising crop 1 is 3unit/ha, while for crop 2 it is 1 unit/ha.The benefit from crop 1 is 5unit/ha and from crop 2, it is 2 unit/ha. A

Engineering indicators in case of multi speed restriction, Multi Speed Rest...

Multi Speed Restriction (i.e. existence of two or more than two speed restrictions in continuation) When work of deep screening or sleeper renewal is in progress, there is situ

Zero energy building, This is our final year project can u suggest some tip...

This is our final year project can u suggest some tips to do well...

Steel structures, how does battening differ from lacing?

how does battening differ from lacing?

Explain the soil texture and soil structure, (a) Explain the 'Soil Texture'...

(a) Explain the 'Soil Texture' and 'Soil structure'. What are the various terms used to explain the above properties of the soil? (b) A clay sample having natural moisture conte

Calculate the number of trucks for fleet working, A contractor was awarded ...

A contractor was awarded a Contract to excavate and haul 200,000-yds 3 of silty clay (USCS classification ML) with a bulking factor of 30%.  The contractor's fleet of dump trucks

How to calculate the total loss of prestress, How to calculate the total lo...

How to calculate the total loss of prestress As a general guide, it may be taken that total loss of prestress may be in the range of 20 to 25 percent of the initial prestress,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd