What is the sludge volume index, Civil Engineering

Assignment Help:

What is the Sludge Volume Index?

Two 1 L samples of mixed liquor are taken from a lagoon. After settling for 30 min in a graduated cylinder, 250 mL of solids have settled out in the first sample. The total suspended solids concentration (MLSS) in the second sample is found to be 2300 mg/L.

(a) What is the sludge volume index?

(b) What is the theoretical required sludge recycle rate?  

Ans:

(a) From eq for SVI, SVI = 1000Vsettled, mL/L/ Xmg/L

= (1000mg/g)(250ml/L)/2300mg/L = 109mL/g

(b) From Eq for, R = Vsettled, mL/L/ 1000-Vsettled, mL/L

250mL / 1000mL - 250mL = 0.33


Related Discussions:- What is the sludge volume index

Paint, painting wood work

painting wood work

Why is the statue of liberty made of copper, Copper is a very durable mater...

Copper is a very durable material when exposed to weather and is soft enough that it can be simply molded to curved shapes like those in the Statue of Liberty. It is also tradition

Define ways of providing the anti slip device - by stops, Define Ways of pr...

Define Ways of providing the anti slip device - By stops? In this method stopper plates or angles are welded to the underside of the girder and embedded in the bed block. It sh

Mechanics of solid, determine the end slope and deflection in the beam

determine the end slope and deflection in the beam

Geotechnical, send any civil engineering related questions . i will write t...

send any civil engineering related questions . i will write the answers , please tell us the process .

Examples of stabilised pavement layers, Examples of Stabilised pavement lay...

Examples of Stabilised pavement layers: Examples Sand-clay mixture Sand-gravel mixture Soil-aggregate mixture Soil-soft aggregate mixtures (b)

Reinforced Concrete Design, design a 3-meter cantilever slab to carry a uni...

design a 3-meter cantilever slab to carry a uniform total dead load of 8.2KN/m^2 and a concentrated live load at the free end of 30 KN/m. f''c=28Mpa fy=420Mpa.

Need survey paper, Write a Survey Paper: Write between 7 to 10 pages a...

Write a Survey Paper: Write between 7 to 10 pages a survey paper in one of the following topic :  ( The Future of HCI. )  For the paper the font size should be 12 points

Calculate the amount of cubic yards of soil, A proposed building site requi...

A proposed building site requires 135,000-ft 3 of imported fill.  A borrow site is located 5-miles Northeast of the project site where the soil has a shrinkage of 16%.  The amount

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd