Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Explain the concept of performance management system, Question 1: "HRM ...

Question 1: "HRM is regarded by some personnel managers as old wine in new bottles". (Armstrong, 1987). Discuss. Question 2: "The contribution of HR function is insig

Secondary stakeholders and major risks in WAM organisation, The WAM Organis...

The WAM Organisation is one of the very successful supermarket chains within its own country. Reputation for innovation of it is unparalleled into its own country along with the wi

Different steps in an environmental impact assessment, Question 1: (a) ...

Question 1: (a) Distinguish between Life Cycle Assessment (LCA) and Environmental Management System (EMS) and outline the benefits of implementing an Environmental Management

Produce a project management plan - gantt chart, For this unit (Computer Pr...

For this unit (Computer Project), you are required to plan, analyse, design, implement, test, document and demonstrate a prototype of your choice.  Once you have identified a fo

Quality measurement procedure - tqm techniques, Quality Measurement Procedu...

Quality Measurement Procedure: Quality as a strategic issue implies (i) acceptance of the importance of customer requirements throughout the organization,  (ii) the identifica

Strategies that a project manager implement to project risk, Explain TWO st...

Explain TWO strategies that a project manager might implement to address a project risk.   Risk avoidance - this strategy would be 'exiting the method that is giving rise to

Explain the time-cost optimization algorithm, Question 1: What do you m...

Question 1: What do you mean by crash duration? Explain the Time-Cost Optimization algorithm crash duration/crash time - explanation including figures  Steps of Time-C

Concept of values to an individual, An organisation's capacity to maintain ...

An organisation's capacity to maintain a sustainable competitive advantage depends largely on its core competencies as well as the ability to refine and enhance them in the context

Rules-planning function, Rules Rules are prescriptions for how members ...

Rules Rules are prescriptions for how members of a group ought to or not to behave. They are specific and allow no discretion. In any group situation, and more so in the formal

Research reports and design documents, Project management-related deliverab...

Project management-related deliverables: business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status reports, final project presentation, final pro

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd