Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Operating characteristic curve, O perating characteristic curve The op...

O perating characteristic curve The operating characteristic curve for a sampling plan quantifies the risks. The OC curve for an attribute plan is a graph of the percentage de

How to, i get stuck being on time and orginzed. please help. is this money?...

i get stuck being on time and orginzed. please help. is this money? thanks isabella

Client master plan, The Client Masterplan includes introduction, rationale,...

The Client Masterplan includes introduction, rationale, client objectives and stakeholder management. This should be a rationalisation of the requirements. Guidelines

Three dimensional model, Three Dimensional Model These are scale model...

Three Dimensional Model These are scale models of a facility and more nearer to the real situation as besides length and width they show height of the facility also. Models ar

Define the critical path analysis in risk management, Define the critical p...

Define the critical path analysis in risk management. Critical path analysis (CPA) or network analysis: Gantt charts are a poor time management tools while projects are l

What do project managers do, Q.  What do project managers do? First of ...

Q.  What do project managers do? First of all project managers have to take responsibility for leading the project effort towards the stated and agreed upon goals and objective

Elaborate on the importance of the project closeout report, QUESTION (a...

QUESTION (a) The project organization structure clearly identifies the relationship between project team members through defining their duties, responsibilities and lines of au

Project risk profile owners, Project risk profile owners  Project risk ...

Project risk profile owners  Project risk profile owners must make sure that they deal with each and every risk of the project. The responsibilities of the project risk owners

Preliminary design, Having given the guidelines in the form of design s...

Having given the guidelines in the form of design specifications the designer should be given a free hand in developing the preliminary design of the product. However i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd