Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Directing-process management, Directing (leading) This is the function ...

Directing (leading) This is the function concerned with influencing organizational members to carry out their assigned roles and activities. This function includes motivation,

Quantitative layout analysis - travel chart, Quantitative Layout Analysis -...

Quantitative Layout Analysis - Travel Chart A basic tool that is primarily used to analyze the material handling cost or in certain cases number of moves in a process layout i

Process control, All processes are subject to various influences such as ...

All processes are subject to various influences such as mechanical electrical and environmental changes which is tend to deviate the process from its initial setting. The

Strategic project assignment, #question your team has been retained to help...

#question your team has been retained to help the company launch it''s products into the global marketplaace. each team is assigned to investigate one country market. The primary o

Managing project quality as per pmi, M a n a ging Project Quality as pe...

M a n a ging Project Quality as per PMI Project Management Institute (PMI) is a global organisation for the project management profession; it is engaged in setting professi

Tool of total quality improvement, Question: As the Managing Director o...

Question: As the Managing Director of your organization, you have been analyzing other institutions that you regard as competitors. Extrapolating your current position up to t

Earliest time the recruitment campaign can start, ST is the operations dire...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

Downward communication from the superior to the subordinate, How must be th...

How must be the downward communication from the superior to the subordinate? There formal communication in between subordinate and superior, here the superior sends directions

Continuous improvement - total quality management, Do it Right First Tim...

Do it Right First Time : TQM adopt the policy of zero defect. There is no scope for rework and rejection. The right first time or zero defect is the result of an empha

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd