Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

How is economic order quantity depended on costs, How is Economic Order Qua...

How is Economic Order Quantity depended on costs? Economic Order Quantity depends on two costs as illustrated below: - Inventory procurement costs that consist of expenditur

Feasibility study for the exploitation of the oil reserves, Question: I...

Question: In the year 2015, the price of petrol has gone up so much that the oil reserves of the Republic of Mauritius start to look interesting to exploit. The oil reserves ar

Explain the development phase in the project management, Explain about the ...

Explain about the development phase in the project management. Development phase During the development phase, everything that will be needed to implement the project is

Project management the managerial process, Are you able to assist with assi...

Are you able to assist with assignments mid terms finals at a masters level

What is the conclusion about liberalization, What is the conclusion about l...

What is the conclusion about liberalization? As a conclusion, we can say only that liberalization is superior and desirable but which does not strengthen the case for privatiza

Housekeeping, what is the thumb rule to calculate the housekeeping manpower...

what is the thumb rule to calculate the housekeeping manpower requirement in office

Pareto charts, P areto charts It is a very helpful tool to identify th...

P areto charts It is a very helpful tool to identify the greatest opportunity for improvement among  various  possibilities  and  to  identify  the  small number  of  most inf

What if i need more time in my project, Q. What if I need more time in my p...

Q. What if I need more time in my project? A competent as well as professional project manager is always up front with the sponsor or senior management. The meeting perhaps unc

Disadvantages of product layout - heavy capital expenditure, Disadvantages ...

Disadvantages of Product Layout - Heavy capital Expenditure This layout requires heavy capital investment in machines and equipment and for providing specialized facilities to

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd