Unit rate contracts , Project Management

Assignment Help:

Unit rate contracts 

In a unit-rate contract, the seller commits to providing each unit of work defined by a buyer for a fixed price per unit of each work item.

Engineered materials are procured with unit-rate contracts when the design is not complete. Service contracts can use unit rate pricing provided the scope of work lends itself to the unit-rate approach.  

Unit-rate contracts are appropriate when the units of work can be well defined but the total quantities are uncertain. Certain standard materials that are procured in large quantities are provided under unit-rate contracts.  

This type of contract also requires an accurate definition of when the units of work will be delivered or installed, unless the contract contains an escalation clause. Unit-rate contractors are usually reluctant to increase personnel, overtime and shift work to accelerate the schedule of their work. 

In this scenario, the seller carries the risk of the cost per unit, and you should assume the risk of quantity growth in the number of units.  

Unit prices are fixed for normal duration contracts, but for linger duration contracts (say  2 years or more), contracts usually permit variation due to escalation based on published indices incorporated in an agreed escalation formula. Another reason for variation in unit rates that may be permitted is variation greater than (plus) or (minus) a certain percentage (say + or  - 20%) in the final contract price compared with the estimated grand total contract price. 

You must not view unit rate contracts identical to cost reimbursable type since, in unit rate contract the unit rate for all work items are fixed based on the description of the work and only the quantity is subject to variation.  

Also, when using unit-rate contracts, you should remember that:  

  •   Unit-rate and cost-reimbursable work should not be included in the same contract. 
  •   Unit-rate contracts require an accurate method of reporting completed work units. 

If the scope of a contract is well defined, stable, and the schedule for performing the work is unlikely to change, a fixed-price contract is the best approach. If the units of work can be well defined, but the total quantities are uncertain, a unit-price contract is the best approach.  


Related Discussions:- Unit rate contracts

Possible stages of a project, Project stages A project may consist of o...

Project stages A project may consist of one or more stages depending on the size of the project, its nature and client needs. Each stage has several tasks.  Possible stages

What is culture of organisation where study and work done, Consider the org...

Consider the organisation which employs you or where you study. What is the culture of this organisation? Why does this have that exacting culture? What organisational culture woul

Man power planning in human resources management, What is the importance of...

What is the importance of man power planning in human resources management? Significance of Man Power Planning within Human Resources Management is as illustrated here: a. M

Caselet, what are the objective of the project alignment session program?

what are the objective of the project alignment session program?

Steps of project manager to enhance likelihood of project, Ideally, the nee...

Ideally, the need for an IS project would be given in some detail before planning begins. When the requirement is not detailed adequate, what steps can the project manager take to

Factor affecting process planning - choice of plant layout, Factor Affectin...

Factor Affecting Process Planning - Choice of Plant Layout While deciding the sequence of operations the plant layout is to be taken into consideration. The sequence of operat

Why do projects always seem to cost more than expected, Q. Why do projects ...

Q. Why do projects always seem to cost more than expected? In general this seems to stem from three causes. The first may merely be an overly optimistic cost estimate. Sometime

Research reports and design documents, Project management-related deliverab...

Project management-related deliverables: business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status reports, final project presentation, final pro

Enterprising management, Hi dear my presentation is ready I need to do my B...

Hi dear my presentation is ready I need to do my Business Plan on it for 2500 words.. can u do it please

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd