Identify the characteristics of the organisation, Project Management

Assignment Help:

M is a business that sells custom made computer-based information systems. Every customer order is for a unique system, which will contain experts from many functional areas within M. Every customer expects a high level of individual attention. Some systems take only four to six months to design and form and cost less than €50,000, whereas other systems cost various million Euros and can take up to three years to complete. Projects are continually being done and started. 

Identify the characteristics of the organisation that make it suitable for M to have a matrix structure.

The characteristics of M that are appropriate to it adopting a matrix organisational structure are as follows:

  • The business of M having of a series of projects which are custom made, which are difficult and require staff from a number of dissimilar functional areas;
  • The projects undertaken by M have dissimilar start and end dates, so the organisation is continually reassigning resources from project to project as single ends and another begins;
  • The projects undertaken by M are difficult so the staff benefit from also being assigned to a technical function (like as finance or procurement) where they can share knowledge and experience with colleagues in their functional teams;

 


Related Discussions:- Identify the characteristics of the organisation

Differences between wbs and product breakdown structure, a) Draw a work bre...

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels. b) Explain the main differences bet

Explain the objectives of a procurement development model, Problem: (a)...

Problem: (a) Explain the objectives of a Procurement Development Model. (b) Explain one Procurement Development Model you are familiar with. (c) "In certain organisation

Project for creating a restaurant utilizing electronic menu, My team's proj...

My team's project is about creating a restaurant utilizing "Electronic menu." My homework is to answer three questions about industry goals. 1. Is your industry growing? 2.

Advantages of fms, Advantages of FMS Flexible manufacturing system...

Advantages of FMS Flexible manufacturing systems are regarded as one of the most efficient methods to employ in reducing or eliminating problems in manufacturing industrie

Explain the sources of conflict, In response to changing customer demands a...

In response to changing customer demands and strong competition, the new product development team of Z Company has been working on a new product range. However, the process has not

Explain about the project management systems, Explain about the project man...

Explain about the project management systems. Project management systems: Each project must have a plan and a set of goals or performance measures to achieve this. Contro

How can improve profitability of a company, Question: Construction of t...

Question: Construction of the toy factory has been completed and it is entering its operational phase. The owners do not understand the fuss there is for quality control. (a

Strategy for project implementation, A strategy for project implementation ...

A strategy for project implementation Projects involving  small number  of  activities,  resources,  constraints  and inter-relationship can be visualized easily by the human m

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd