In the middle third of the base of precast concrete pipes, bedding layers are suggested to be left Uncompacted since it helps to decrease the reaction force at the invert of the pipes and intensifies the effect of shear forces. Furthermore bending moment at pipe invert is increased by compaction of bedding layer. General rule for this region of bedding layer is that it must be firm enough for the pipes to rest on. 

Sides of haunch and bedding directly under the haunch must be compacted since this will decrease the bending moment at the invert that is the critical failure location for pipes. The compacted haunch helps to resist the pipe load and sustain level and alignment.


Related Discussions:- Uncompacted bedding for concrete pipes

.., Ask questiPermanent Way:on #Minimum 100 words accepted#

Ask questiPermanent Way:on #Minimum 100 words accepted#

Stone, Explain briefly physical classifications of stone

Explain briefly physical classifications of stone

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Levelling, principles of levelling

principles of levelling

Determine the basic concepts of prestressing, Determine the Basic Concepts...

Determine the Basic Concepts  of Prestressing In the year 1904, Freyssinet tried to introduce prestresses in concrete to resist stresses developed due to external loads. Later,

Ductility test, Ductility Test: The ductility of a bituminous binder ...

Ductility Test: The ductility of a bituminous binder is its ability to deform under load and return to its original condition after removal of the load. The property is deter

Explain pressure balance method and compressed air method, Pressure balance...

Pressure balance method vs. compressed air method in pipe jacking Pressure balance method generally requires the use of mechanically operated tunnel-boring machine at its cutti

Premix road, plz tell me the ratio of sand,aggregate,and asphalt.pl tell me...

plz tell me the ratio of sand,aggregate,and asphalt.pl tell me the mm of aggregate

Colour code, in colour working drawing what are the colour code?

in colour working drawing what are the colour code?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd