In the middle third of the base of precast concrete pipes, bedding layers are suggested to be left Uncompacted since it helps to decrease the reaction force at the invert of the pipes and intensifies the effect of shear forces. Furthermore bending moment at pipe invert is increased by compaction of bedding layer. General rule for this region of bedding layer is that it must be firm enough for the pipes to rest on. 

Sides of haunch and bedding directly under the haunch must be compacted since this will decrease the bending moment at the invert that is the critical failure location for pipes. The compacted haunch helps to resist the pipe load and sustain level and alignment.


Related Discussions:- Uncompacted bedding for concrete pipes

Show the excessive movement joints in bridges, Q. Show the Excessive moveme...

Q. Show the Excessive movement joints in bridges? Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from

Usage of double air valves and single air valves, Question In designig ...

Question In designig of watermains, how to decide usage of double air valves and single air valves ? Answer Single air control device let squeezing air out of p

Explain the perception reaction time, Explain the Perception Reaction Time ...

Explain the Perception Reaction Time A significant variable in the successful processing and use of information is the speed with which this is done. Perception-Reaction Time (

Torpedo splice triple wedges, Torpedo splice triple wedges In a Torpedo...

Torpedo splice triple wedges In a Torpedo splice triple wedges, shown in Figure, are provided to firmly hold tendon wires. Whole assembly of the splice is housed in a sleeve. L

Beam to column connection, what are the characteristics of the beam to colu...

what are the characteristics of the beam to column connection?

Solis mensuration, the two side are 17 cm and 28 cm long. and the lenght of...

the two side are 17 cm and 28 cm long. and the lenght of the drawn to the third side is equal to 19.5cm. find tghe distance from an endpoint of this medianto the longest s8ide

Building construction drawings, I need a drawing detail of expansion joints...

I need a drawing detail of expansion joints in building and different sizes

Principles and Practices of Management, How Will You Influence People to St...

How Will You Influence People to Strive Willingly for Group Objectives in Your Organization (Target Based Industry)? Apply Your Interpersonal Influence Through Communication Proces

Dynamic force transfer test of shock transmission unit, Define Dynamic Forc...

Define Dynamic Force Transfer Test of Shock Transmission Unit? This test mainly prove the lock up capability of the device. The STU shall be loaded in tension from zero to the

What is rail lubricators, Q. What is Rail Lubricators? 1. P & M type of...

Q. What is Rail Lubricators? 1. P & M type of lubricators - These lubricators can be used for lubrication of FF rails as well as BH rails. 2. Elgi grease pump - Elgi Bucket

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd