Transitional jacks designed in pipe jacking projects, Civil Engineering

Assignment Help:

Question

Why are transitional jacks designed in pipe jacking projects?


Answer

While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation.
For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks

 


Related Discussions:- Transitional jacks designed in pipe jacking projects

Define the void ratio and specific gravity of particles, Derive the formula...

Derive the formula among soil moisture content (w), degree of saturation (S), specific gravity (G), and void ratio (e). Saturated clay has a water content of 40% and bulk specif

Truss, Wind Force acting on truss

Wind Force acting on truss

Methods of contouring by grid points, the elevations of grid points for an ...

the elevations of grid points for an area as follows: 1 2 3 4 5 6 7 8 F 690 709 726 732 735 740 743 747 E 696 715 729 736 740 737 739 740 D 702 723 733 742 737 737 745 747 C 707 72

Define sample collection - clean water act, Define Sample Collection - Clea...

Define Sample Collection - Clean Water Act? The collection of the sample is able to have significant effects on the complete analytical process. Additionally, to make sure some

Ironmongery, fabrication methods of ironmongery

fabrication methods of ironmongery

What is uniformly distributed surcharge, A retaining wall with a smooth ve...

A retaining wall with a smooth vertical back, 4.5 m high, retains a dry cohesionless backfill level with the top of the wall. γ = 18.6 kN/m 3 and φ = 30°. The backfill carries a u

Survying, what aare the parts and function of steel tape ?

what aare the parts and function of steel tape ?

Guidelines for selection of site, Guidelines for Selection of Site: Th...

Guidelines for Selection of Site: The following are some of the guidelines for selecting the site of a bridge : (a) A site which is on a straight reach of the river is pref

Lime, LIME It is significant binding material utilized in building con...

LIME It is significant binding material utilized in building construction. Lime has been utilized as the material of construction from ancient time. While it is mixed with san

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd