Why are transitional jacks designed in pipe jacking projects?


Answer

While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation.
For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks

 


Related Discussions:- Transitional jacks designed in pipe jacking projects

What is the dry density, Q. The field density of a compacted fill is deter...

Q. The field density of a compacted fill is determined by means of a core cutter whose empty weight is 1000 g and volume is 1000 cm 3 . The cutter full of soil weights 2890 g. If

Explain situations that warrant a damage inspection, Explain Situations tha...

Explain Situations that warrant a damage inspection? - Floods - bridges located in streams, rivers and other waterways with known or suspected scour potential. - Build-up of

Surveying, what are the basic two division of surveying

what are the basic two division of surveying

Fluid Mechanics, A 4-m-long, 6-cm-diameter cylinder placed normal to the fl...

A 4-m-long, 6-cm-diameter cylinder placed normal to the flow is used to measure the velocity of an air stream. If a force of 50 N is measured, the air velocity is nearest (for air

Hoyers long line system pre-tensioning, Hoyers long line system pre-tension...

Hoyers long line system pre-tensioning When concrete attains the required strength,  jacks  are released and tendon wires in-between various units are cut.

Choice of pavement - road pavements, Choice of Pavement: The advantag...

Choice of Pavement: The advantages and drawback of the two types of pavements are summarized in Table, to enable a choice to be made. Table : Advantages and drawback of

ENGlLISH, Ask question #WHAT is presentation skill #

Ask question #WHAT is presentation skill #

Calculate the horizontal distance, Calculate the Horizontal Distance A ...

Calculate the Horizontal Distance A surveyor's total station measured slope distance near station 3245+26.35 is recorded as 437.380-m with a zenith angle of 118º 48' 07" and a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd