Transitional jacks designed in pipe jacking projects, Civil Engineering

Assignment Help:

Question

Why are transitional jacks designed in pipe jacking projects?


Answer

While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation.
For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks

 


Related Discussions:- Transitional jacks designed in pipe jacking projects

Properties of elastomer, An elastomer is a polymeric substance obtained aft...

An elastomer is a polymeric substance obtained after vulcanization of rubber. Vulcanization is the process of improving the properties of rubber by heating with sulphur. A normal r

Door, types of door with sketches

types of door with sketches

Define facilities that discharge wastewater to a potw, Facilities that disc...

Facilities that discharge wastewater to a publicly owned treatment works? Facilities that discharge wastewater to a POTW (publicly owned treatment works) are known as subject t

Define non-destructive inspection of concrete substructures, Define Non-des...

Define Non-destructive inspection of Concrete Substructures? If there is evidence of significant deterioration, then a Level III inspection, involving either non-destructive or

Mapping, how to understand maps easily?

how to understand maps easily?

Precast pile, when a precast pile is single point lifting and when double p...

when a precast pile is single point lifting and when double point lifting- what are the moment coefficient of them?

Explain about vierendeel girder, Q. Explain about Vierendeel girder? Vi...

Q. Explain about Vierendeel girder? Vierendeel girder design is sometimes adopted in design of footbridges. Traditionally truss design, triangular shape of truss is generally u

Water treatment, The transmission main from the well field to the community...

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd