Question
Why are transitional jacks designed in pipe jacking projects?
Answer
While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation. For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks
Question In designing of watermain , regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than 600mm. Give some speci
Define the Coefficient of Permeability: (K) A measurement of the ability of the soil or an aquifer for the movement of water through it. Also termed "hydraulic conductivity", C
Define Fatigue - Materials The normative view of the stress/strain is found in the example of the paper clip wire experiment. Take a paper clip wire and try to break it by pull
Explain with lime soda process?cold lime soda process&hot lime soda process and it''s equations?
how to discussion cross section?
Explain the Principle of Working of Shock Transmission Unit? The STU consists of a machined cylinder with a transmission rod that is connected at one end to the structure and a
Figure 2 details a typical T-beam unit in a beam and slab floor with a span of L = 10 m. Determine the reliable moment capacity M ′ for the T-section shown. Take f c ′ = 32
Example. With a surveyor compass the angles observed in traversing the lines AB, BC, CD, DE and EF are as. Compute the included angles and indicate them in a neat sketch.
mixing ratio of different type of ready mix concrete.(RMC)
Q. Inspection and Quality Control Certificate : A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certif
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd