Question

Why are transitional jacks designed in pipe jacking projects?


Answer

While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation.
For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks

 


Related Discussions:- Transitional jacks designed in pipe jacking projects

Fluids, FLUID substance which deforms continuously when subjected to a shea...

FLUID substance which deforms continuously when subjected to a shear stress  LIQUID no fixed shape deforms under gravity to container shape virtually incompressible = const

Compute the stresses at top and bottom fibres, Compute the stresses at top ...

Compute the stresses at top and bottom fibres in a simply supported pre-stressed concrete beam with a rectangular cross section, 200 mm wide and 400 mm deep at sections A-A, B-B an

One-way pre stressing vs two-way pre stressing, Q. One-way pre stressing vs...

Q. One-way pre stressing vs two-way pre stressing? At the time of pre-stressing operation at one end, frictional losses will take place and the prestressing force decreases alo

Flash point test, Flash Point Test: The flash point is the temperatur...

Flash Point Test: The flash point is the temperature at which the bitumen gives off vapours which ignite in the presence of a flame. The flash point temperature gives the cri

PLANKING AND STRUTING FOR SHALLOW EXCAVATION, DEFINITION TYPE STEP OF CON...

DEFINITION TYPE STEP OF CONSTRUCTION STEP OF SAFETY

Convert the azimuth reading of 273.34 to a land bearing, Convert the azimut...

Convert the azimuth reading of 273.34º to a land bearing:  Solution: Convert 273.34º to degrees minutes and seconds = 273º 20' 24" Next, convert the angle to orient to IV

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd