Transitional jacks designed in pipe jacking projects, Civil Engineering

Assignment Help:

Question

Why are transitional jacks designed in pipe jacking projects?


Answer

While development of pipe jacking stops, building up of confrontation is extremely fast in some soil. For example, boost in jacking force of 20 to 40 percent is necessary for a stoppage of pipe jacking for just some hours. Therefore, it is recommended that pipe jacking have to be carried out in a continuous operation.
For an extended pipeline, frictional forces recognized between jacking pipes and soil is high. From time to time, such resisting forces might be so high that they be able to barely be overcome by jacks in jacking pits. Furthermore, even if the jacks can conquer high frictional forces induced during jacking, high loads are knowledgeable in jacking pipes through driving. Jacking pipe's material for example concrete could not have enough strength to resist these stresses and so pipe strength is another factor that direct need for consideration of using transitional jacks

 


Related Discussions:- Transitional jacks designed in pipe jacking projects

Rcc flooting, Explain the simple square footing, simple squral footing an...

Explain the simple square footing, simple squral footing and slop footing with the help of drawing

State the location and spacing of borings, Location and spacing of borings ...

Location and spacing of borings The location, spacing of geophysical profiles, soundings and borings should be such that,  you will be in a position to accurately predict the

Disparity between working stress and limit state approach, Question Wha...

Question What is key disparity between working stress approach and limit state approach ? Answer Working stress approach, service loads are used in whole plan and st

Local vehicle parapet strong enough to contain vehicles, Q. Local vehicle p...

Q. Local vehicle parapet strong enough to contain vehicles? Majority of local parapets are 1.1m high in addition they are designed to resist impact from a 1.5ton car moving at

Compatibility condition, Compatibility Condition: Total strain in ste...

Compatibility Condition: Total strain in steel = Total strain in copper i.e. 3 × 10 -4 + 1.965 × 10 -5 P s   = 4.5 × 10 -4 + 1.8421 × 10 -5 P c Recognising that P

Contractor to continue concreting works, Question If on-site slump test fai...

Question If on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works ? Answer This is an extremely traditional question raised by

Explain the term- shrinkage of concrete, LOSS OF PRESTRESS DUE TO SHRINKAG...

LOSS OF PRESTRESS DUE TO SHRINKAGE OF CONCRETE We know that concrete shrinks in volume when it dries up. This volume reduction takes place in the form of reduction of all dime

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd