Question
What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures?
Answer In designing of marine piles of steel tubular piles with concrete infill, loads from pier deck are occupied up by steel tubular piles before occurrence of corrosion of steel piles above seabed. It is assumed that steel piles above seabed level will all be corroded after a sure year. Load transfer mechanism after complete corrosion of steel pile over seabed is as follows-
Loads from pier deck are taken up by concrete infill above seabed level. Below seabed level, loads would be transferred to steel piles through frictional forces between concrete infill and steel casings. Yet, substantial radial shrinkage and contraction arises after concreting of concrete infill and this would hinder load transfer from the concrete infill to steel piles because bond might be ruptured by radial shrinkage. It is in hesitation if frictional forces be able to be correctly developed in this situation. To solve this problem, shear keys can be installed at normal spacing inside steel piles to ensure their rigid connection with concrete infill. Alternatively, expanding agents could be adopted in concrete mixes to make sure that there is no shrinkage after concreting process.
how to calculate number of passes while compaction
Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac
What is the head loss in 350 ft of 12 inch diameter 20 years old cast iron pipe carrying 1.2 MGD?
What is reciprocal ranging
Q. Explain Types Of Tiles? Different types of tiles available in the market for floor and walls & dado are as under - 1. Glazed tiles , 2. Ceramic tiles , 3. Granit
Define the term - post-tensioned concret In the Prescon and B.B.R.V. systems button heads are created at the ends of tendons. In the case of Prescon system, 2 to 130 tendon wir
list some applications of quadratic equation in civil engineering
Mechanism of taking up loads for concrete paving blocks Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet
How to prepare rapid sand filter autocad drawing
Determine the stresses set up in the brass: A compound bar is constructed from three bars 50 mm wide by 12 mm thick fastened together to form a bar 50 mm wide by 36 mm thick.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd