Traditional marine piling system of steel tubular pile, Civil Engineering

Assignment Help:

Question

What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures?


Answer

In designing of marine piles of steel tubular piles with concrete infill, loads from pier deck are occupied up by steel tubular piles before occurrence of corrosion of steel piles above seabed. It is assumed that steel piles above seabed level will all be corroded after a sure year. Load transfer mechanism after complete corrosion of steel pile over seabed is as follows-

Loads from pier deck are taken up by concrete infill above seabed level. Below seabed level, loads would be transferred to steel piles through frictional forces between concrete infill and steel casings.

Yet, substantial radial shrinkage and contraction arises after concreting of concrete infill and this would hinder load transfer from the concrete infill to steel piles because bond might be ruptured by radial shrinkage. It is in hesitation if frictional forces be able to be correctly developed in this situation. To solve this problem, shear keys can be installed at normal spacing inside steel piles to ensure their rigid connection with concrete infill. Alternatively, expanding agents could be adopted in concrete mixes to make sure that there is no shrinkage after concreting process.

 


Related Discussions:- Traditional marine piling system of steel tubular pile

Reinforced Concrete Design, Design a continuous one-way solid slab supporte...

Design a continuous one-way solid slab supported on beams spaced at 4.2m o.c. the width of the beam is 300mm, leaving clear slab spans of 3.9. The slab carries a uniform DL= 6 KPa.

Determine the thermal stress in the bar, Determine the thermal stress in th...

Determine the thermal stress in the bar: A stepped bar made of aluminum is held between two supports. The bar is 900 mm in length at 38ºC, 600 mm of which is having a diameter

Corrosion protection of lifting anchors in precast concrete, Q. Corrosion p...

Q. Corrosion protection of lifting anchors in precast concrete? Corrosion of lifting anchors in precast concrete units has to be prevented since the corroded lifting units caus

Show afflux and scour in alluvial rivers, Q. Show Afflux and scour in alluv...

Q. Show Afflux and scour in alluvial rivers? In case of alluvial rivers, the river bed comprises scourable material like sand. Constriction of bridge waterway causes increase

Tests on cement, Tests on Cement: The following tests are conducted o...

Tests on Cement: The following tests are conducted on cement in a project site: Setting Time Initial setting time Final setting time Compressive Streng

Planning stage of the audit, Materiality is used only at the planning stage...

Materiality is used only at the planning stage of the audit. Ans: I disagree with the statement because: When planning the audit, the auditor considers what would make the fi

What do you mean by depth of scour, Q. What do you mean by Depth of Scour? ...

Q. What do you mean by Depth of Scour? The maximum scour depth in a stream can be ascertained when ever possible by actual sounding at or near the site proposed for the bridge

Marine pilling, what are the problems in traditional marine pilling system ...

what are the problems in traditional marine pilling system of steel tubular pile with concrete infill

Maintenance of terminal building, Maintenance of Terminal Building: A...

Maintenance of Terminal Building: All accessories such as lighting, water, sanitation, telephone and public address system should be maintained in a good condition. Disposal

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd