qn, Operation Management

Assignment Help:
a firm whether to make or buy a part required in its operation. cost and volume estimate are as follows annual fixed cost make $15000 buy none, variable cost make $60 buy $80, annual demand unit make 12000 buy 12000 should the firm make or buy the part?

Related Discussions:- qn

Explain a wealthy farmer owns fifty acres of land, A wealthy farmer owns fi...

A wealthy farmer owns fifty acres of land. He is going to plant each acre with sugarcane or corn. Each acre planted with sugarcane yields Rs 16,000 profit; each with corn yields Rs

Explain managers for a large retail department store, Recently the managers...

Recently the managers for a large retail department store stated that a study has revealed that female shoppers spend on average 23.5 minutes longer in the store per visit than do

What are the possible to use a ti-84 calculator, To test H0: p=.35 versus h...

To test H0: p=.35 versus h1:p Please let me know if it is possible to use a ti-84 calculator ? = Power =

Explain the first step in segmenting and targeting markets, The first step ...

The first step in segmenting and targeting markets is to recognize a need. group potential buyers into segments. create product groupings. estimate size of the overall

Explain collective bargaining and grievance procedure, When a union negotia...

When a union negotiates, with management, on behalf of its members to define and interpret employment contracts, it is known as: Answer (1) mediation. (2) Collective bargaining. (3

Productivity challenge in organisations, Productivity Challenge in Organisa...

Productivity Challenge in Organisations Productivity is the ratio of outputs (goods and services) divided by the inputs (resources: labour, capital and services). It is one of

Compute the line efficiency of longest processing time, Balance the assembl...

Balance the assembly line in Exhibit 8.12 for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an eight-hour shift, and use the rule, choose the assignab

Explain what is your assessment of the health of the project, On day 51, a ...

On day 51, a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the he

What is prime cost, What is Prime Cost? The sum of Direct Labour Cost, ...

What is Prime Cost? The sum of Direct Labour Cost, Direct Expenses and Direct Material Cost is Prime Cost.

Define what will be the average number of jobs in the system, A single mach...

A single machine work center has five jobs assigned to it. They are labelled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd