The project manager and the project owner, Project Management

Assignment Help:

X Company, a private security firm, has signed a contract to fund the design, construction and running of a local police station. This arrangement is a public private partnership agreement whereby the local police authority will pay X Company revenue to run the support services of the local police station.

Explain, with a view to successfully completing X Company's project, the relationship required between the project manager and

(i)  the project owner;

(ii)  the project sponsor;

Project manager and project owner

The local police authority has set out its needed objectives but is not responsible for giving the funds. The project manager will need to work with the authority to make sure there is no conflict between its expectations and the funds being given.

The project manager will have little direct reporting/communication with the local police authority as responsibility for project progress is mostly to the project board. However, the ultimate objectives of the local police authority need to be monitored as it will be concerned with ensuring that the entire project is not seen to waste public resources.

Project manager and project sponsor

The project board is effectively the project sponsor. The project manager is responsible for achieving the objectives set by the project board. The board is responsible for the overall running of the project and it requirements to achieve the local police authority objectives without disrupting the achievement of its own business objectives.

 


Related Discussions:- The project manager and the project owner

Risk categorisation , Risk Categorisation  Management of risk involves:...

Risk Categorisation  Management of risk involves:    Prevention: To deal with causes.    Recovery: To deal with effects.  There are three categories of project r

Discussion Question, Your brother in-law is about to submit a scope stateme...

Your brother in-law is about to submit a scope statement to the town council for the July 4th parade and picnic he has volunteered to project manage. Your town has about 6,000 hous

Calculate how much float/slack time, ST is the operations director of F Bak...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

How to measures customer satisfaction for the product, Quality ultimately i...

Quality ultimately is calculated in terms of customer satisfaction.) Surveyed before product delivery and after product delivery (and on-going on a periodic basis, using standar

Develop and agree a process model for a project, Why is it significant that...

Why is it significant that the project team and the users develop and agree a process model for a project? Any project is a cooperative venture among the clients/users and the

Aggregate planning, Aggregate planning is an operational method that does ...

Aggregate planning is an operational method that does an aggregate plan for the production procedure, in advance of 2 to 18 months, to provide an idea to management as to what amo

Threats of canon, what is the compny competitors doing?

what is the compny competitors doing?

Reduce inspection cost by acceptance planning, R educe inspection cost by ...

R educe inspection cost by acceptance planning In few cases where there are number of methods, available to protect the supplier and the customer from poor quality, it so happ

How you would estimate the project management activity, Explain how you wou...

Explain how you would estimate the project management activity. Project management: This effort is dependent onto two things as whether a full-time project manager is to be

What are the pros and cons of a pure project organisation, What are the pro...

What are the pros and cons of a ‘pure’ project organisation compared along with a project operating into a matrix structure? A ‘pure’ project organisation comprises into itself

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd