Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Barriers to implementing tqm, BARRIERS TO IMPLEMENTING TQM: The implem...

BARRIERS TO IMPLEMENTING TQM: The implementation of TQM in library organisations provides an opportunity to update and enhance the abilities of the staff to work effectively,

Describe the product and service, 1. Which product /service you propose to ...

1. Which product /service you propose to work on this quarter? From which company? Which product category does it belong to? Describe the product/service you will market briefly.

PERT Network Analysis, Solve the following CPM/PERT Network Analysis proble...

Solve the following CPM/PERT Network Analysis problem: Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slac

The Roles and responsibilities of a project manager, what are the Roles an...

what are the Roles and responsibilities of a project manager in the construction sector

What are the primary objectives of transferring risks, Question : (a) ...

Question : (a) Define risk as per the Public Private Partnership Guidance Manual. (b) What are the primary objectives of transferring risks from a contracting authority to

Management, Ask question #MinimumIn its first year, “ABC Co” had the follow...

Ask question #MinimumIn its first year, “ABC Co” had the following experience Sales = 50,000 units Selling price = br. 50 TVC = br. 1,000,000 TFC = br. 250,000 Required: A. Devel

Sequence activities and milestones , This assignment is designed to demonst...

This assignment is designed to demonstrate your understanding of project scheduling, time and cost estimation. Assignment: Update your group's WBS created in Assignment 1

What do you mean by improving productivity, What do you mean by Improving P...

What do you mean by Improving Productivity? Improving Productivity: The concentrate of production is creation of goods, might be by the transformation of raw materials or

IT Project Management Task #1, IT Project Management Task #1, I need help w...

IT Project Management Task #1, I need help with my course.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd