Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Project, can make two project for me?

can make two project for me?

Project management, what is the nine key competencies that project manager ...

what is the nine key competencies that project manager must develop? explain in detail of each and individual for the key competencies

Explain the elements of a service level agreement, Problem 1: (a) What...

Problem 1: (a) What do you meant by Life Cycle Costing? (b) Explain briefly the methodology for Life Cycle Costing. (c) Why might a procurement officer consider procuri

Marketing project, Step 1 Advise the instructor in writing if you will be w...

Step 1 Advise the instructor in writing if you will be working on the project individually or with another class member(s). Choose your team member (s),carefully, as you will have

Quantitative Methods, A2. Unfortunately, the Capital Investment Committee r...

A2. Unfortunately, the Capital Investment Committee refused to approve your recommendation (Problem 1) since you did not consider the uncertainty inherent in these types of investm

Privatisation of public sector included undertakings, What are included in ...

What are included in the privatisation of public sector undertakings? Privatisation of public sector undertakings: It is consisting of witnessed the trend toward opening

What work goes on previous to project start-up, What work goes on previous ...

What work goes on previous to project start-up? Before project start-up, work is required to establish the things and scope of the project. This is essential to establish the d

Answer, summarise the argument for such a policy of partnering with a major...

summarise the argument for such a policy of partnering with a major supplier such as BAA and MACE HAVE DON HERE

Components of quality, Components of Quality 1. Product feature shave...

Components of Quality 1. Product feature shave a major effect on sales income ( through market share premium prices etc) . in many industries the total external cust

Disadvantages of product layout - inflexibility, Disadvantages of Product L...

Disadvantages of Product Layout - Inflexibility Inflexibility is a drawback of this type of layout. The equipment laid out is designed to perform specific operations. No machi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd