Q. Show the Settlement due to Excavation?

If  an excavation is made in a sandy soil,  the structure founded near the excavation will be affected and it will cause extra settlement. The settlement due to excavation of the cut will not extend beyond a distance equal to the depth of cut. For example,  if  the depth of cut is 5m, then the building at a distance of 5 m from the excavation  only will effect. This can be minimised by adequately providing the bracings.

When any cut is made in soft clay stratum,  the structure loaded at the sides of  the cut acts like a surcharge. Therefore  the clay near the bottom of the cut yields laterally towards the excavation under this surcharge. Hence, the ground surface above  the yielding clay starts settling.


Related Discussions:- Show the settlement due to excavation

Purposes of subdivision of tunnelling faces, Purposes of subdivision of tun...

Purposes of subdivision of tunnelling faces in Sprayed Concrete Linings (SCL) method In using sprayed concrete lining methods for lining a large tunnel in soft ground, tunnelli

Define the process of eccentric prestressing, Define the proess of Eccentri...

Define the proess of Eccentric Prestressing In this form of prestressing, the centroid of cross-sectional areas of tendons is not located at the centroid of the cross-section.

Specification of flooring for heavy repair shed, Q. Specification of Floori...

Q. Specification of Flooring for heavy repair shed? Scope for use - For flooring for heavy repair shed, Surface hardened concrete flooring can used. In this type of flooring,

Hydraulics, In this question we consider a bended outlet of pipe flow AB. E...

In this question we consider a bended outlet of pipe flow AB. End A is attached to an incoming pipe by a flange connection. The pipe diameter at A is the same as the incoming pipe,

Define the net positive suction head, Define the Net Positive Suction Head ...

Define the Net Positive Suction Head All values in the equations are in units of feet.  Note: Only use values related to the suction side of the pump.   NPSHR = Net Posi

Define deferred maintenance- underwater inspection of bridge, Define Deferr...

Define Deferred maintenance - underwater inspection of bridge? Many problems of the substructure can be traced to lack of any maintenance in time, which again can be due to lac

Foundation depth and arrangement, Foundation Depth and Arrangement: Th...

Foundation Depth and Arrangement: There are two types of foundations, viz, (a) Shallow foundations, also known as open foundations, and (b) Deep foundations. Slab cul

Explain the contracted rectangular weir, Explain the Contracted Rectangular...

Explain the Contracted Rectangular Weir Weir plate has sides which extend above the maximum water surface, directing the flow through an opening (b = weir length). Typically th

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd