Question
What are main functions of cap block drive cap and pile cushion in driven piles?
Answer
Cap block is fit amid hammer end and drive cap to manage hammer blow in order to protect together hammer and pile from damage. When hammer hits cap block, it squeeze elastically and reduces peak forces, thereby lengthening time of hammer blow. Furthermore, it has to be capable of transmitting hammer energy effectively to piles.
Drive cap is put in at hammer tip to improve uniform distribution of hammer energy to pile. Pile cushion is positioned amid drive cap and pile top. It means to protect pile from driving stress induced during hammer blows. Furthermore, it also serves to give a uniform driving load on top of pile.
The plastic limit and liquid limit of a soil are 33% and 45% respectively. The percentage volume change from the liquid limit to the dry state is 36% of the dry volume. Likewise, t
how to convert a varying distributed load to a uniformly distributed load
effective length of the column
Define the usage of Data from Hydrographs Flow rates and volume quantities over time. Predictions based on the runoff flow rates. The characteristics of the drainage b
IS 883-1970 classifies the structural timber into 3 grades-select grade, grade I and grade II
A concrete crew will use the available steel form panels measuring 2'-6" wide x 4'-0" high to construct a 40'-6" long by 3'-2" high by 1'-6" wide concrete knee wall. The square
Demonstrate the Design of Prestressed concrete poles Prestressed concrete poles are generally designed as members with uniform prestress since they are subjected to bending mo
what is the waste utilisation?
"We have one other pressing challenge that you could review for us," Alistair Wu says. "As you know, the Shanghai plant was our first facility in China, but we also have two other
how to construct road in hilly areas
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd