Show elastomeric bearings, Civil Engineering

Assignment Help:

1. Elastomeric bearings must not be placed one behind the other along the longitudinal axis of the girder on a single line of support under any circumstances.

2. Bearings of different plan size must not be installed next to each other (on the same pier) under the same girder/span.

Different plan area will lead to different value of 'δ' for given values of H, h and G as under:

3. The contact surface between the bearing and the bed block must be horizontal to avoid tangential force due to gravity coming on to the bearing (maximum tolerance 0.2%.


Related Discussions:- Show elastomeric bearings

Linear algebra concept, Scenario: You are working for a structural engineer...

Scenario: You are working for a structural engineering firm and you have been assigned the task of computing the code checks on a new structural design. Though another commercial p

The regulations and specification that followed for compacti, what are The ...

what are The regulations and specification that followed for compaction works for earth dam in Oman.

Manhole covers finished of cast iron same as ductile iron, Question Why are...

Question Why are manhole covers finished of cast iron as same are through of ductile iron ? Answer Usually, manholes covers are made of cast iron. Though, in viewpoint of pipe

Regression, I would like to ask what is regression and its function?

I would like to ask what is regression and its function?

Define hydraulic grade line (hgl), Define Hydraulic Grade Line (HGL) Gr...

Define Hydraulic Grade Line (HGL) Graph of the sum of the pressure and potential energies at a position along a pipe or open channel. The difference between the EGL and the HGL

Define the pre-tensioned concrete construction, Define the pre-tensioned co...

Define the pre-tensioned concrete construction We understand that in the pre-tensioned concrete construction, stretched tendons are provided in the concrete moulds at the time

Residual stresses in steel after welding, Q. Residual stresses in steel aft...

Q. Residual stresses in steel after welding? Considerable residual stresses are persuaded in connecting steel members after welding operation. Local temperature of steel where

Define the cost per square foot of contact area, Define the Cost per Square...

Define the Cost per Square Foot of Contact Area The cost of concrete formwork is influenced by three factors: 1. Initial cost or fabrication cost that contains the cost of t

Parabola, how to draw a parabola

how to draw a parabola

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd