Kicker of reinforced concrete cantilever retaining walls, Civil Engineering

Assignment Help:

Q. Kicker of reinforced concrete cantilever retaining walls located at the position of largest moment and shear force - why?

Generally for reinforced concrete cantilever retaining walls, there is a 75mm kicker at the junction wall stem and base slab to facilitate the fixing of formwork for concreting of wall stems. If a higher kicker (which is more than 75mm height) is provided instead, at the time of concreting of base slab the hydraulic pressure built up at kicker of fresh concrete cause great problem in forming a uniform and level base slab.  

Even though the fact that position of kicker in a cantilever retaining wall is the place of largest shear andflexure, there isn't any option left however to provide the kicker at this position.


Related Discussions:- Kicker of reinforced concrete cantilever retaining walls

Explain the perception reaction time, Explain the Perception Reaction Time ...

Explain the Perception Reaction Time A significant variable in the successful processing and use of information is the speed with which this is done. Perception-Reaction Time (

Define inspection of steel or cast iron substructures, Define Inspection of...

Define Inspection of Steel or Cast Iron Substructures? Corrosion is the principal cause of deterioration in steel waterfront substructures. On bare un-protected steel pilings,

Important parts of road pavements, Important parts of road pavements: ...

Important parts of road pavements: Prime Coat : Application of a low viscosity bituminous binder over a granular base to fill up the voids. Tack Coat : Application of b

Example of magnetic dip, Example : Line AB was drawn with a magnetic ...

Example : Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what m

Planning and scheduling tutorial, Am looking for .planning and scheduling...

Am looking for .planning and scheduling tutorial , cost engineering tutorials

Roadworks - filler and binder in bituminous pavement, Q. Roadworks - filler...

Q. Roadworks - filler and binder in bituminous pavement? In bituminous materials, course aggregates perform the bulking action of mixture and contributes to stability of result

Question, The state of stress at a point is given by the stress components ...

The state of stress at a point is given by the stress components sx = 70 MPa, sy = 10 MPa and ?xy = - 40 MPa. Using Mohr''s circle, find (i) Principal stresses, and (ii) Principal

Angle measurment, calculating included angle and bearing

calculating included angle and bearing

Timber, seasoning of timber

seasoning of timber

Significance of tailwater level in culverts, Significance of tailwater leve...

Significance of tailwater level in culverts Headwater level and tailwater level of culverts are significant parameters in hydraulic design. Headwater level can't be set too la

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd