Q. Kicker of reinforced concrete cantilever retaining walls located at the position of largest moment and shear force - why?

Generally for reinforced concrete cantilever retaining walls, there is a 75mm kicker at the junction wall stem and base slab to facilitate the fixing of formwork for concreting of wall stems. If a higher kicker (which is more than 75mm height) is provided instead, at the time of concreting of base slab the hydraulic pressure built up at kicker of fresh concrete cause great problem in forming a uniform and level base slab.  

Even though the fact that position of kicker in a cantilever retaining wall is the place of largest shear andflexure, there isn't any option left however to provide the kicker at this position.


Related Discussions:- Kicker of reinforced concrete cantilever retaining walls

Leveling, cooke''s reversable level

cooke''s reversable level

BOLTED CONNECTIONS, compare riveted joints with welded joints

compare riveted joints with welded joints

Deformation equation for settlement, Q. Deformation Equation for settlement...

Q. Deformation Equation for settlement? When a load is applied on an elastic body, it results in strain. The summation of strain over a length is deformation or settlement. In

Rectilinear motion, A train starts from rest as A and accelerates at 1,7m/...

A train starts from rest as A and accelerates at 1,7m/s2 to full speed at which it maintains until the brakes gives it a deceleration of 1,7m/s2 to stop at B. AB=1,6km. determine

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Explain the frequency of inspection - underwater inspection, Explain the Fr...

Explain the Frequency of Inspection - Underwater Inspection? Underwater inspections must be done on every bridge identified for such inspection as per the Indian Railways Bridg

Explain the statements about the critical path method, 1. Determine a netwo...

1. Determine a network diagram method that uses only finish-to-start relationships and may use dummy activities to define logical relationships.  2.  Precedence diagr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd