Q. Scraper Launchers and Receivers?
Scraper launchers and receivers associated with the pipelines shall be located in open, well-ventilated areas with the opening directed away from pressurized or other critical equipment, where practicable. Mechanical handling facilities shall be provided for spheres, scrapers (also commonly known as "pigs") and line logging devices.
Elevations, relative to grade, of launchers and receivers shall be kept to a minimum, but shall be of sufficient height to allow contents of drain lines to be observed. Launcher and receiver areas are located close to the main pipeline entry and exit points of the plant. The loading and unloading end of these units should point away from other facilities. This equipment should be within a curbed area with wash down facilities. As launchers and receivers are operated whilst adjacent plant is still 'live', safe spacing needs to be maintained.
Slug catchers are located close to the gas pipeline entry point to the plant and are designed to accommodate slugs of liquid that may be present in the gas supply. They can be either vessel type or for larger flows a multipipe type slug catcher can be utilized, both are generally above ground. The multipipe type can occupy a considerable plot area.
Both the launcher and receiver and slug catcher areas can have their own security fence. This can act as a physical code break between on-plot process and pipeline design codes.
uses of parallelogram
A steel rod of 3 cm diameters and 5 m long is connected to two grips and the rod is maintained pull exerted when the temperature falls to 30 o C if (a) The ends do not yield, an
With neat diagram illustrate the cycle of operation of four-stroke spark ignition engine. In what respects four-stroke cycle CI engine differ from that of SI engine ?
Q. Maintenance requirement at storage tanks? Little maintenance is required at storage tanks; sometimes access is required for equipment used to remove accumulated solids (this
Wet saturated steam - thermodynamics: we t saturated steam Wet steam is a 2-phase mixture comprising of boiling water particles and dry steam in equilibrium state. Its for
The layout of a transmission shaft carrying two pulley C and B and supported on bearings A and D is shown in figure. Power is supplied to the shaft by means of vertical belt on pul
a) You were assigned to determine the production rate for a polymer extrusion process. The extruder is found to have a barrel diameter = 4.5 in and length = 11 ft. The extruder scr
If Taylor's tool life constants for a provided operation are specified of n = 0.5 and c = 400, what is the percentage increase in tool life when the cutting speed is reduced by hal
Composite Aspect Ratio The length ratio of a reinforcing fibre to its diameter is termed as aspect ratio. In the so-termed as fibre reinforced plastics or composites the aspec
Q. Handling Suspect Material? • Material or items at a Supplier's facility or those received or stored in the warehouse or other construction site location that require PMI-tes
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd