Question

Should dolphins be designed in a rigid manner such as resting on several raking piles?


Answer

While designing dolphins, they are normally supported on a system of three to four raking piles. This in essence is a rigid arrangement and exhibits little flexibility as in movement against impact and berthing loads by vessels. In fact, this type of design might not be desirable in terms of maintenance since dolphins are readily susceptible to damage by high berthing vessels. To correct this situation, some power absorption devices like rubber or plastic fenders have to be installed to reduce impact load deriving from its own deflection. On other hand, by designing dolphins as supple structures capable for allowing slight deflection, it helps to reduce large forces generated during berthing of vessels. While connection, one way of designing dolphins as flexible structures are by provision of a single pile only.


Related Discussions:- Resting on several raking piles

Define the reservoirs - hydraulic system, Define the Reservoirs - Hydraulic...

Define the Reservoirs - Hydraulic System Typically designed for multiple functions - clean water supply, creating recreational opportunities and flood protection. Reservoirs ar

#tile.., Material for formwork and their specifications

Material for formwork and their specifications

Hydraulics, A rectangular channel, 20ft wide is shown. The channel consists...

A rectangular channel, 20ft wide is shown. The channel consists of three reaches of different slopes. The channel has a roughness coefficient of n=0.015 and carries a discharge of

Explain about noise absorptive materials, Q. Explain about Noise absorptive...

Q. Explain about Noise absorptive materials? The fundamental mechanism of noise absorptive material is to change the acoustic energy into heat energy. Amount of heat produced i

Abrasion test - tests on stones, Abrasion Test:   This test is carri...

Abrasion Test:   This test is carried out on stones used as aggregates for road construction. The test result shows the suitability of stones against   the grinding action u

Civil engineering drawing, Explain step by step procedure involved in the a...

Explain step by step procedure involved in the analysis and design of balanced cantilever bridge.

Total volume of soil that excavated from the borrow area, Project specifica...

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd