Reinforcement of concrete in contact with internal vibrators, Civil Engineering

Assignment Help:

Reinforcement of concrete in contact with internal vibrators 

At the time of concreting, if internal vibrators are placed accidentally in contact with some of the reinforcement bars, some undesirable effects can result. The most obvious one is that reinforcement bars can become displaced or damaged if loosely tied.  

Air bubbles are likely to move towards the source of vibration. For poker vibrators touching the reinforcement bars, air pockets can be trapped in the vicinity of the reinforcement since vibration produced by internal vibrators attracts these air bubbles. Therefore the bond between the surrounding and reinforcement concrete would be impaired.

To attain good surface finish close to densely-packed reinforcement cage, workers can insert poker vibrators in the gap between reinforcement cage and formwork since reinforcement cage tend to damp down the vibration effect when vibrators are located at a distance from the formwork. Though concentrated vibration within the cover region causes migration of finer cement mortar to this area and leads to changes in concrete colour. If concrete cover is small, chance of getting the poker vibrators jammed in the gap is high and formwork is tends to be damaged by vibrators.


Related Discussions:- Reinforcement of concrete in contact with internal vibrators

Introduction to engineering mechanics, Deternim the angle A for which the m...

Deternim the angle A for which the moment of the 500N force is maximum about a point o. also find the maximum momentum

Higway engineering, Ask question Design the pavement by group index method ...

Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min

Define npdes sampling requirements, Define NPDES Sampling Requirements? ...

Define NPDES Sampling Requirements? The sampling needs under NPDES are given at 40 CFR Part 122, as part of the needs for applying for an NPDES discharge allow. The needs are b

What do by diaphragm wall, Q. What do by Diaphragm wall? For the constr...

Q. What do by Diaphragm wall? For the construction of diaphragm walls adjacent to buildings, former experience showed that excess slurry head above groundwater level had to be

Define the meaning of tensile stresses, Tensile stresses It has been po...

Tensile stresses It has been possible to introduce tensile stresses of upto 850 N/mm 2 in tendons with the use of this method. But the method is not suited in situations where

What is n-value of standard penetration test, Define and discuss the variou...

Define and discuss the various factors that help decide the number and depth of bore holes needed for subsoil exploration. What is 'N-value' of Standard Penetration Test? How do

Replacement of Expansion Joint, I want to know the necessary material list ...

I want to know the necessary material list during replacement of Expansion Joint

Determine the variation of safe bearing capacity of soi, State the algebrai...

State the algebraic equations showing the variation of safe bearing capacity of soil (for clay and sand to be given separately) in shallow foundation with: (i) depth of foundati

Fore bearing and back bearing, write a c program to calculate the included ...

write a c program to calculate the included angles for given fore bearing and back bearing.

Offset(survey)., what is meant by the offsets and explain its type?

what is meant by the offsets and explain its type?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd