Process of installation of elastomeric bearing, Civil Engineering

Assignment Help:

The process of installation of elastomeric bearing differs in case of precast vis-a-vis cast-in-situ girders. For precast girders, the bearing may be fixed to the underside of the girder by application of epoxy resin adhesives after specified surface preparation. Care should be taken to guard against faulty application and consequent behaviour of the adhesive layer as a lubricant.

The adhesive is considered merely as an installation device and is not an adequate anti- creep measure.

The process of installation of elastomeric bearing in a cast-in-situ girder is more complex. It involves the following stages:

1. Placing and adjusting the bearings on the bed block with required accuracy.

2. Preparation of a formwork sideframe all around the bearing.

3. Filling up the space between the bearing and the formwork frame by clean sand.

4. Placement of top forms over the side frame and sand with an opening matching the size and position of the bearing.


Related Discussions:- Process of installation of elastomeric bearing

Calculate the diameter of the stockpile, 1. On a 5-acre level terrain build...

1. On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft su

Use scattered lighting for underwater inspection of bridge, Define Use of s...

Define Use of scattered lighting for Underwater inspection of Bridge In this arrangement, a very high powered, tight beam spot light (beam angle less than 10°) is used. The lam

R.c.c, solution of point of contraflexure

solution of point of contraflexure

Survey, how can find forebearing

how can find forebearing

Foundation, Explain briefly shallow foundation?

Explain briefly shallow foundation?

Classification of timber based on availability:, Classification Based on Av...

Classification Based on Availability: Forest departments categorized timbers based on the availability as X=Most common. 1415 m 3 or more per year Y=Common. 355 m 3 to 1415

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd