Q. Asphalt mix design - durability vs. stability?

The main aim of asphalt mix design is to achieve a mix with economical blending of aggregates with asphalt to achieve the following: 

(i) Workability to facilitate easy placement of bituminous materials without experiencing segregation;

(ii) Sufficient stability so that under traffic loads the pavement won't undergo distortion and displacement

(iii) Durability by having sufficient asphalt

(iv)  Sufficient air voids

In asphalt mix design, high durability is generally attained at the expense of low stability. Therefore a balance has to be stricken between durability and stability requirements.


Related Discussions:- Asphalt mix design – durability and stability

Define hydraulic grade line (hgl), Define Hydraulic Grade Line (HGL) Gr...

Define Hydraulic Grade Line (HGL) Graph of the sum of the pressure and potential energies at a position along a pipe or open channel. The difference between the EGL and the HGL

Define the finish to finish activity, A finish-to-finish activity is best d...

A finish-to-finish activity is best described as: The "from" activity must finish before the "to" activity can finish The "from" activity must finish before the "to" acti

Determine the uses of prestressed concrete poles, Determine the uses of Pre...

Determine the uses of Prestressed concrete poles Prestressed concrete poles are commonly mass produced and are used in most countries for power transmission, antenna masts etc

What is raft foundation, Q. What is Raft Foundation? A raft or mat is c...

Q. What is Raft Foundation? A raft or mat is combined footing that covers the entire area beneath a structure and supports all the walls and coloumn when the allowable soil pre

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

Solis mensuration, the two side are 17 cm and 28 cm long. and the lenght of...

the two side are 17 cm and 28 cm long. and the lenght of the drawn to the third side is equal to 19.5cm. find tghe distance from an endpoint of this medianto the longest s8ide

Key distinction in arranging pumps in series, Question What is key dist...

Question What is key distinction in arranging pumps in series and in parallel? Answer For same pumps with similar functions, if pumps arranged in series, total head

Assignment, How to do assignment on the basis of azetropic mixture

How to do assignment on the basis of azetropic mixture

Batching of concrete, Introdaction , volume batching , weighat batchin...

Introdaction , volume batching , weighat batching , mesaring of water

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd