Principle of adding cooling pipes, Civil Engineering

Assignment Help:

Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

Constraction, sir what is means by share force

sir what is means by share force

Desirable properties of bitumen, Desirable Properties of Bitumen: For...

Desirable Properties of Bitumen: For performing as a good binder for road works, bitumen should have the following desirable properties: (a) When heated to the mixing temp

Deck that you can park a car under, I wish to build a deck that is 4.7m wid...

I wish to build a deck that is 4.7m wide and 7m long alongside my house. I need to park a car under it so there can be no supports in the middle. Attached to the wall on one side a

Mechanical, Define varigions principle of moments and write about system of...

Define varigions principle of moments and write about system of forces?

Pycnometer., To determine the specific gravity of fine aggregate (sand) by ...

To determine the specific gravity of fine aggregate (sand) by Pycnometer.

Explain the process of directed track maintenance, Q. Explain the process o...

Q. Explain the process of Directed Track Maintenance? DTM is a method to maintain the track is directed every day and not as a prescribed routine. DTM essentially consists of n

Define unit hydrograph - hydrology, Define Unit Hydrograph UNIT HYDROGR...

Define Unit Hydrograph UNIT HYDROGRAPH: The hydrograph developed for a drainage basin (watershed) from the runoff of a 1 in or 1 cm storm. It is the base hydrograph from which

Precast concrete jacking pipes, Question While precast concrete jackin...

Question While precast concrete jacking pipes , from time to time grout holes are calculated inside these precast pipes. Give specific and key reasons? Answer Grout h

What is raft foundation, Q. What is Raft Foundation? A raft or mat is c...

Q. What is Raft Foundation? A raft or mat is combined footing that covers the entire area beneath a structure and supports all the walls and coloumn when the allowable soil pre

Explain the coefficient of permeability, A sand deposit of 12 m thick overl...

A sand deposit of 12 m thick overlies a clay layer. The water table is 3 m below the ground surface. In a field permeability pump-out test, the water is pumped out at a rate of 540

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd