Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

Minimum volume of sump volume for pumps, Minimum volume of sump volume for ...

Minimum volume of sump volume for pumps Maximum pumping rate = Q P Volume of sump = V Inflow Rate = Q i Cycle Time T c = t 1 + t 2 t 1 = V / Q P - Q i t 2

Assignment, How to do assignment on the basis of azetropic mixture

How to do assignment on the basis of azetropic mixture

Brigdes, infomation about differnt brigdes

infomation about differnt brigdes

How are freeway bridges built, After measuring the anticipated traffic for ...

After measuring the anticipated traffic for the bridge, cement/reinforced- with- rebar stanchions are spaced over the freeway to accommodate the bridge. An 'off-ramp' from the free

Sway porta frame, how to sway portal frame both end fixed due to eccentric ...

how to sway portal frame both end fixed due to eccentric loading with diagram

Distomat, definition,old&new modern&difference

definition,old&new modern&difference

Wall method of estimation, 1. Can you enumerate the benefits of individual ...

1. Can you enumerate the benefits of individual wall method of estimation? 2. Estimate the single room of size 3m x 4m x height 3m  using individual wall method? 3. Which met

Angle measurment, calculating included angle and bearing

calculating included angle and bearing

Increasing concrete cover beyond contractual, Question If contractor sugges...

Question If contractor suggests increasing concrete cover beyond contractual such as 40mm to 70mm shall engineers accept suggestion? Answer In contractual part, based on requir

Estimating, a 45 cm deep roof beam is provided on 30 cm wall of a room size...

a 45 cm deep roof beam is provided on 30 cm wall of a room size 3.0m*5.0m . calculate the quantity of steel required in beam on percentage basis.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd