Principle of adding cooling pipes, Civil Engineering

Assignment Help:

Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

What depth is the intensity of pressure zero, A retaining wall with a smoot...

A retaining wall with a smooth vertical back retains a purely cohesive fill. Height of wall is 12 m. Unit weight of fill is 20 kN/m 3 . Cohesion is 1 N/cm 2 . What is the total act

Rock reinforcement – how it works, Rock reinforcement - how it works? ...

Rock reinforcement - how it works? For rocks with widespread fractures, individual blocks resulting from these fractures can fall out and as a result slope failure can take pl

What is the group capacity, State the group efficiency of a rectangular gro...

State the group efficiency of a rectangular group of piles with 4 rows, 3 piles per row, the uniform pile spacing being 3 times the pile diameter. If the individual pile capacity i

Use Structural Analysis in Engineering, As per Australian Standard AS 1170,...

As per Australian Standard AS 1170, what are the different types of loads that can be encountered by structures which need to be taken into account for their design?

Flow, what is maximum flood level

what is maximum flood level

State the increase in earth pressure at rest, A wall with a smooth vertical...

A wall with a smooth vertical back and 9 metres high retains a moist cohesionless soil with a horizontal surface. The soil weighs 15 kN/m3 and has an angle of internal friction of

Define the term - post-tensioned concret, Define the term - post-tensioned ...

Define the term - post-tensioned concret In the Prescon and B.B.R.V. systems button heads are created at the ends of tendons. In the case of Prescon system, 2 to 130 tendon wir

Colour code, in colour working drawing what are the colour code?

in colour working drawing what are the colour code?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd