Principle of adding cooling pipes, Civil Engineering

Assignment Help:

Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

Civil and statistics, application of normal distribution in civil engineeri...

application of normal distribution in civil engineering

Bitumen, unit of kinematic viscosity

unit of kinematic viscosity

Column estimat, how maney point in columan parking estimate

how maney point in columan parking estimate

Applied physics, Write the principle of reversibility of light.

Write the principle of reversibility of light.

Why we use air valves, Q. Why we use Air Valves? Air Valves - Air valve...

Q. Why we use Air Valves? Air Valves - Air valves of proper size and pressure rating at summits. Air valves ensure the safety of the pipe line against collapse when at points o

Calculate time taken for consolidation in actual layer, A clay layer 5 m th...

A clay layer 5 m thick has double drainage. It was consolidated under a load of 127.5 kN/m2. The load is enhanced to 197.5 kN/m 2 . The coefficient of volume compressibility is 5.7

Measure the safe load on the pile, A wood pile of 10 m length is driven by ...

A wood pile of 10 m length is driven by a 1500 kg drop hammer falling by 3 m to a final set equal to 1.25 cm per blow. Measure the safe load on the pile using the Engineering Ne

Traverse, how to fill traverse computation sheet of opened traversig ..

how to fill traverse computation sheet of opened traversig ..

Afflux on account of obstruction to flow, Q. Afflux on account of obstructi...

Q. Afflux on account of obstruction to flow? Even if the river constriction on account of approach banks is not excessive and bridge waterway is wider than that causing critica

Construct the correct network for project, A project requires that activiti...

A project requires that activities A and B can be started independently and activities C and D are independent but can be started after A and B have been completed. Activity E can

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd