Principle of adding cooling pipes, Civil Engineering

Assignment Help:

Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

Explain different types of texture and structure of soils, (a) Relate dissi...

(a) Relate dissimilar formations of soils to the geological aspects. (b) Explain different types of texture and structure of soils. (c) Bring out the typical characteristics

Water piped scheme, how to use mood diagram to get f and other Re

how to use mood diagram to get f and other Re

Calculate the specific gravity of the soil particles, A piece of clay taken...

A piece of clay taken from a sampling tube has a wet weight of 1.553 N and volume of 95.3 cm 3 . After drying in an oven for 24 hours at 105°C, its weight 1.087 N. Suppose the spec

Concrete, if the slump of concrete drops how to rectify it

if the slump of concrete drops how to rectify it

Verify the void ratio and water content, Derive the relation among void rat...

Derive the relation among void ratio (e), specific gravity of particles (G) and moisture content at full saturation (w). A certain sample of saturated soil in a container weighs

Pre-stress girder/ I Beam design and Triaxial lab report, I need urgent su...

I need urgent support in my assignment and also my UU triaxial lab report. thanks Maryam

Warm mix asphalt., how it different from hot mix asphalt . is it changes an...

how it different from hot mix asphalt . is it changes any performance compared to hot mix asphalt

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd