What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

Define project scheduling - types of methods, Define Project Scheduling - T...

Define Project Scheduling - Types of Methods Project Scheduling - Distinction between the Major Types of Schedule Diagrams Precedence Diagrams (PDM)   a) Activ

Radial contour, how to calculate distance for radial contour

how to calculate distance for radial contour

Define bank volume to be stockpiled and used for backfill, An earthwork con...

An earthwork contract was awarded to excavate and backfill the foundation of a proposed 50-ft by 50-ft office building.  The existing grade elevation is 437.5-ft while the sub-base

Surveying, WCB from included angle

WCB from included angle

Determine the head loss due to friction, Determine the Head Loss Due To Fri...

Determine the Head Loss Due To Friction Determine the head loss due to friction using the Darcy-Weisbach equation. The water is pumped at 3.0 gallons per minute, has a temperat

Determine the amount of excavated material, The footprint of a proposed off...

The footprint of a proposed office building is overlaid on the existing contours topographic map of a sloping site as shown in the figure. The structural bays which are 65-ft by 65

Show the continuous piezocone penetration test, Q. Show the Continuous Piez...

Q. Show the Continuous Piezocone Penetration Test? Continuous piezocone penetration test essentiallycomprises standard cone penetration test and a measurement of pore water pre

Explain the toxic characteristics - hazardous waste, Explain the Toxic Char...

Explain the Toxic Characteristics - Hazardous Waste - From the results of either  - Extraction Procedure(EP) toxicity (prior to March 1990) or Toxicity Characteristic Leachi

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd