What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

What do you mean by plain elastomeric pads, Q. What do you mean by Plain el...

Q. What do you mean by Plain elastomeric pads? Plain pads are used for light or moderate loadings. Plain pads have a tendency to bulge under heavy loadings. In order to reduce

Determine the limit states of serviceability, Limit States of Serviceabilit...

Limit States of Serviceability These are those limit states which point out to the inability of a structure or a structural component in functioning properly as per the intende

Calculate the natural frequency of the system, A machine weighing 500 kN is...

A machine weighing 500 kN is mounted on a concrete block resting on soil. The base area of the block is 25 m 2 , and the weight is 100 kN. The coefficient of elastic uniform com

Explain the erosion and sedimentation, Explain the Erosion and Sedimentatio...

Explain the Erosion and Sedimentation Erosion: Removal of soil or other channel material caused by the rapid movement of water over the channel surface. The removed material

#title difference, Write difference between the working stress method and l...

Write difference between the working stress method and limit step methode

Calculate distance between top and bottom chord of the truss, A W12x58 memb...

A W12x58 member, which comprises a vertical member in a truss span, is subjected to a factored axial compressive force of 163 kips.  The W12x58 section is oriented such that the st

Minimisation of differential settlement, Minimisation of Differential Settl...

Minimisation of Differential Settlement You are aware that differential settlement causes more distress to the structure, when compared with that of total settlement. The var

Vertical curves - geometric design of roads, Vertical Curves: When tw...

Vertical Curves: When two vertical gradients meet, it is necessary to provide a vertical curve. Two types of vertical curves are used: (a) Summit curve, where the point of

Beam to column connection, what are the characteristics of the beam to colu...

what are the characteristics of the beam to column connection?

Verify the total active thrust on the wall per lineal metre, A smooth backe...

A smooth backed vertical wall is 6.3 m high and retains a soil with a bulk unit weight of 18 kN/m 3 and φ = 18°. The top of the soil is level with the top of the wall and is horiz

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd