Principle of adding cooling pipes, Civil Engineering

Assignment Help:

Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

How can designer cater for stability of minor slips, Question Soil nail...

Question Soil nails are mostly designed for stabilization of key slips . How can designer cater for stability of minor slips? Answer There are many methods to treat mi

Centroid, how tofind centroid of cercular arc

how tofind centroid of cercular arc

Direction of approaching velocities of ships during berthing, Q. Direction ...

Q. Direction of approaching velocities of ships during berthing? One of the key effects of angle of approaching velocities of ships is its influence of energy to be absorbed by

Determine the limit state of serviceability, Determine the Limit State of S...

Determine the Limit State of Serviceability Cracking Cracking of concrete should not affect the appearance or durability of the structure. The criteria of limit state of cracki

State average increase of pressure in the clay stratum, A building was to b...

A building was to be constructed on a clay stratum. Preliminary analysis showed a settlement of 60 mm in 6 years and an ultimate settlement of 250 mm. The average enhance of pressu

Determine the natural frequencies - shear building, For the shear building ...

For the shear building shown, determine the natural frequencies (RAD/SEC) and the modal matrix. Also, sketch the deflected buildings in their normal modes using the top floor as th

Water treatment, The transmission main from the well field to the community...

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

Define categories of scaling-underwater inspection of bridge, Define the Ca...

Define the Categories of Scaling? Scaling is classified into following three categories: i. Light scale - loss of surface mortar up to 5 mm deep, with surface exposure of co

Is kerb necessary in road pavements, Question Is kerb necessary in road...

Question Is kerb necessary in road pavements? Answer In universal, kerbs are crucial in road pavements due to next cause- (i) They supply strength to sides of road

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd