Principle of adding cooling pipes, Civil Engineering

Assignment Help:

Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

The right triangle, a lighthouse standing on the cliff observed from two op...

a lighthouse standing on the cliff observed from two open boats A and B in a vertical plane thourgh the lighthouse.the angle of elevation of the top of the lighthouse viewed from B

Retaining wall, I retained the soil in my yard by brick with 3 levels to a...

I retained the soil in my yard by brick with 3 levels to avoid sliding the soil to the street. the appeared part of the bricks from each level is 3 feet and less.The hidden part o

Define recommendations for confined elastomeric pad, Define Recommendations...

Define Recommendations for confined elastomeric pad?  (a) Permissible limits for confined pressure on elastomer pad depends upon effectiveness of internal seal preventing it fr

Define the cavitation - underwater inspection of bridge, Define the Cavitat...

Define the Cavitation - underwater inspection of bridge? Cavitation damage is caused by repeated impact forces caused by collapse of vapour bubbles in rapidly flowing water. Th

Explain the term - prestressing force, Explain the term - Prestressing Forc...

Explain the term - Prestressing Force Due to the stretching of  tendons, tensile stresses develop inside tendons. Resultant prestressing force in tendons may be calculated by m

Survey, who to we calculate the RL at first point.

who to we calculate the RL at first point.

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

Bridge designing, Could someone please help me understand the basics of bri...

Could someone please help me understand the basics of bridge designing

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd