Principle of adding cooling pipes, Civil Engineering

Assignment Help:

Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

Soil compaction test, Question In soil compaction test , if test resul...

Question In soil compaction test , if test result exceeds 100%, should engineers accept result? Answer Soil compaction is method of increasing soil density by re

Define drag load test of shock transmission unit, Define Drag load test of ...

Define Drag load test of shock transmission unit? This test ensures that excessive load should not be transmitted to the structure by the STU. As per the test the STU shall hav

An alternative test to confirm concrete strength, Question If concrete comp...

Question If concrete compression test not pass, So Schmidt hammer test will be adopted as an alternative test to confirm concrete strength ? Answer Schmidt hammer test is

Material engineering assignment, select three materials metal and non meala...

select three materials metal and non mealat at least one of the selected materials shold change its property

Support, In a RC Frame what will be the support condition for a cantilever ...

In a RC Frame what will be the support condition for a cantilever edge beam i.e. fixed, pinned, encastre or knife?

Calculate the settlement at the centre of the mat, A mat foundation of 15...

A mat foundation of 15 m x 15 m and weighing 20000 N/m 2 is to be constructed on the surface of a soil strata. The profile is given in Figure. The number of squares enclosed i

Calculate the deposited amount - construction management, An engineer depos...

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-mo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd