Question

What is key principle of adding cooling pipes or yet using cold water for concrete in concreting operation?


Answer

These methods aim at reducing placing temperature and falling thermal cracks induced during concreting of enormous pours. Because final concreting temperature has to be ambient temperature, reducing initial placing temperature will also lower peak hydration temperature. Therefore, temperature divergence between hydration peak and ambient temperature is reduced so and subsequently thermal effect to concrete structure can be abridged by controlling placing temperature.

 

 


Related Discussions:- Principle of adding cooling pipes

Cement, manufacture of cement by dry process

manufacture of cement by dry process

Advantages and dis advantages of timber, WHAT ARE THE ADVANTAGES AND DISADV...

WHAT ARE THE ADVANTAGES AND DISADVANTAGES OF TIMBER FOR CIVIL ENGINEERING

Finite Element Analysis- MATLAB problem, I am currently enrolled in a gradu...

I am currently enrolled in a graduate Civil Engineering course in Finite Element Analysis. The final assignment and project both deal with coding in MATLAB and I am having great di

Show the settlement due to vibration, Q. Show the Settlement due to Vibrati...

Q. Show the Settlement due to Vibration? The foundation resting on cohesionless soil and subjected to vibrations will result in settlements of higher magnitude. In sandy soil

Differentiate between concrete and tendons, Differentiate between concrete ...

Differentiate between concrete and tendons In the case of pre-tensioned concrete members, the transfer of prestress takes place due to the bond between concrete and tendons. In

Define categories of scaling-underwater inspection of bridge, Define the Ca...

Define the Categories of Scaling? Scaling is classified into following three categories: i. Light scale - loss of surface mortar up to 5 mm deep, with surface exposure of co

Explain the design criteria for sedimentation basin, Explain the Design Cri...

Explain the Design Criteria Sedimentation basin Surface Loading rate (or overflow rate), Vo = Q/A (flow rate/surface area) Detention time t or ? = V/Q (Volume /Flow rate)

Acidity and alkalinity - chemical characteristics of water, Acidity and Alk...

Acidity and Alkalinity - Chemical Characteristics of Water Acidity: Capacity to neutralize bases and is a measure of acids in water. Acidity is measured by titrating the s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd