Preparation for underwater inspection - tool and equipment, Civil Engineering

Assignment Help:

Preparation for Underwater Inspection - Availability of Tools and Equipment

The engineer-in-charge, before taking up the inspection, should list out the complete equipment required for the inspection and ensure that they are working properly. The following equipment would generally be necessary.

- Boats with oars, motor and life preservers

- Diving gears

- Portable flashlight

- Surface cleaning tools, e.g. brushes, scrapers

- Easy-to-read measuring tape

- Knife, hand scraper and hammer

- Sounding gear for determining depth

- Other measuring devices

- Recording devices such as still and video cameras, Plexiglas, and grease pencil.

- Safety equipment In addition to above, specialised equipment may be required to be kept ready for non-destructive testing of material. At occasions, partially destructive testing equipment and equipment for taking samples e.g. core cutting equipment may also be required.


Related Discussions:- Preparation for underwater inspection - tool and equipment

Concepts and definitions of thermodynamics, System A system (often cal...

System A system (often called a closed system) is any collectionof matter within a prescribed boundary, but no matter may enter or leave the system.  Note 1. That the bo

Application of embankment condition for drainage design, Q. Application of ...

Q. Application of embankment condition for drainage design? In considering loads on buried pipeline, there are generally two scenarios: narrow trench condition and embankment (

How do you determine specific gravity of cement, Cement is usually purchase...

Cement is usually purchased as a powdery substance that is mixed with sand, aggregate, gravel, and water to form concrete. As the cement itself is usually a powder, it is hard to c

Effect of pile installation method, Effect of pile installation method to l...

Effect of pile installation method to load carrying capacity of piles The construction of piles by driving method causes an increase in density of surrounding soils. Therefore

How to do deflection calculations, How to do deflection calculations Ba...

How to do deflection calculations Basic values of span to effective depth ratios for spans upto 10m may be taken as 7, 20 and 26 for cantilever, simply supported and continuous

Surveying, What is reciprocal ranging

What is reciprocal ranging

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd