Preparation for underwater inspection - tool and equipment, Civil Engineering

Assignment Help:

Preparation for Underwater Inspection - Availability of Tools and Equipment

The engineer-in-charge, before taking up the inspection, should list out the complete equipment required for the inspection and ensure that they are working properly. The following equipment would generally be necessary.

- Boats with oars, motor and life preservers

- Diving gears

- Portable flashlight

- Surface cleaning tools, e.g. brushes, scrapers

- Easy-to-read measuring tape

- Knife, hand scraper and hammer

- Sounding gear for determining depth

- Other measuring devices

- Recording devices such as still and video cameras, Plexiglas, and grease pencil.

- Safety equipment In addition to above, specialised equipment may be required to be kept ready for non-destructive testing of material. At occasions, partially destructive testing equipment and equipment for taking samples e.g. core cutting equipment may also be required.


Related Discussions:- Preparation for underwater inspection - tool and equipment

Rehabilitation of Concrete Roads, Step by step rehabilitation strategies wi...

Step by step rehabilitation strategies with drawing, figures, and illustrations

Purpose of setting minimum amount of longitudinal steel area, Q. Purpose o...

Q. Purpose of setting minimum amount of longitudinal steel areas for columns? In some design codes it specifies that area of longitudinal steel reinforcement must be not less

Define seismic isolation bearings - bridge bearing, Define Seismic Isolati...

Define Seismic Isolation Bearings  - Bridge Bearing? Many bridges had been built before the proper seismic design specifications were known to us. These bridges require strengt

Distomat, Ask quetypes of stion #Minimum 100 words accepted#

Ask quetypes of stion #Minimum 100 words accepted#

Foundation recommendation, what are the necessary data required for foundat...

what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?

Retaining wall, I retained the soil in my yard by brick with 3 levels to a...

I retained the soil in my yard by brick with 3 levels to avoid sliding the soil to the street. the appeared part of the bricks from each level is 3 feet and less.The hidden part o

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Forensic structural engineering, i need journals or articles of forensic st...

i need journals or articles of forensic structural engineering

What is load carrying capacity of a pile, Q-  What are loads and forces ta...

Q-  What are loads and forces taken into account for designing a pile and what is load carrying capacity of a pile. Ans. For designing a pile the following loads and force ar

Yugty, #quesjjhjhhjtion..

#quesjjhjhhjtion..

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd