Define seismic isolation bearings - bridge bearing, Civil Engineering

Assignment Help:

Define Seismic Isolation Bearings  - Bridge Bearing?

Many bridges had been built before the proper seismic design specifications were known to us. These bridges require strengthening and enhancing the ductility of substructures in order to sustain the earthquake forces. Conventional retrofitting methods are costlier (more than 3 times) than providing 'Seismic Isolation Bearings' (SIB). The studies have shown that:

(a) The SIB eliminated the in-plane torsional rotation of the bridge and resulted in a more uniform distribution of seismic forces among substructures in the transverse direction.

(b) The modifications in the response of the bridge resulted as a result of use of SIB because the effective fundamental period of the bridge get elongated due to the flexibility provided by the SIB.

(c) Average retrofitting cost using SIB is calculated as only 30% of that using conventional retrofitting methods.

An isolation bearing induce sufficient lateral flexibility in a bridge structure and increase the period of vibration, resulting in a reduced force response. The increased lateral flexibility is associated with larger horizontal displacements at the bearing level. In the longitudinal direction, the stiffness of a bridge with isolation bearings is the sum of the stiffness of all piers and abutments including the bearings. In a bridge with conventional bearings. However, the longitudinal stiffness incorporates the stiffness of a fixed support alone. The isolation bearings should also include a restoring force to return the superstructure to its pre-earthquake position.


Related Discussions:- Define seismic isolation bearings - bridge bearing

Concrete , advantage and disadvantage of concrete

advantage and disadvantage of concrete

Calculate the final volume of the compacted soil, 1. 130,000-yd 3 of banke...

1. 130,000-yd 3 of banked soil from a borrow pit is stockpiled before being trucked to the jobsite. The soil has 18% swell and shrinkage of 8%.  The final volume of the compacted

Methods of constructing roads in marshy areas, Methods of Constructing Road...

Methods of Constructing Roads in Marshy Areas: The following methods are adopted for constructing roads in marshy areas: (a) Removal of soft soil and replacement with good

Average heating season outside temperature, Produce a manual determination ...

Produce a manual determination to determine the instantaneous rate of heat loss (kW) through one part of the fabric (eg roof, glazed area, wall) based on an internal building desig

Test on complete bearings, Q. Test on complete bearings? Two bearings s...

Q. Test on complete bearings? Two bearings should be selected at random from the 'lot'. Various tests should be conducted on these 'test bearings'. These bearings should be exc

Preparation for underwater inspection - tool and equipment, Preparation for...

Preparation for Underwater Inspection - Availability of Tools and Equipment The engineer-in-charge, before taking up the inspection, should list out the complete equipment req

Define wastewater treatment processes, Define Wastewater treatment Processe...

Define Wastewater treatment Processes The wastewater treatment processes that we design mimic the processes that occur in the nature (for example processes that occur in a flow

Concrete compaction in piling works, Question What is the reason that v...

Question What is the reason that vibrators not used in concrete compaction in piling works ? Answer Concrete for piles must be a high-slump self-compacting mix that i

Doors, what is door and window sizes

what is door and window sizes

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd