Preliminary stress analysis work will start early in the detail engineering phase after completion of equipment layout and piping study drawings. The piping required to be analyzed will be divided into systems or sub-systems with logical break points and the Mechanical Engineer will provide the stress analyst with a preliminary information package for each piping system identified as requiring stress analysis.
Some of the critical piping systems are such that any changes in vendor information or equipment layout will result in considerable rework for the stress analyst and changes in piping layout. For other piping, preliminary analysis can be carried out without information from equipment vendors and any rework due to changes in layout or equipment details will not result in significant rework. The mechanical engineer, piping design and stress analyst will work out a schedule so that piping design, stress analysis and structural/foundation work for pipe support can proceed smoothly with minimum rework. While the sequence of work will vary from one project to another, the following general suggestions have been found useful in the past.
Q. What are the Specific Issues with plant Layout? There are a large number of regulations and related material that impact the operating plant. API (American Petroleum Institu
State the Product Data Exchange Specifications In May 1984, a late night meeting of the IGES Organization Edit Committee was held. The outcome: the Boeing representative was
Define 3-D lathe Tool Dynamometer It is possible to measure three dimensional cutting tool component with the help of 3-D lathe tool dynamometer. In spite of that we are gone f
Find out the velocity of the bullet: A bullet of weight W 1 = 5 N is fired into a body B 2 of weight W 2 = 45 N suspended by a string of length L = 1 metres. Because of i
Energy - thermodynamics: The energy can be defined as the capacity of doing work. The energy possessed by system may be of two kinds. 1. Stored energy: for example potent
Ceramics, Refractory And Abrasive Materials Introduction There are some situations in practice where high temperatures are occupied. Besides creating that temperatures en
Gas Porosity Porosity is the presence of gas pockets or voids caused by the entrapment of gas evolved during weld metal solidification. This Porosity is caused due to im
Q. What do you mean by Risers and Downcomers? Risers and downcomers shall be staggered along the shell of the WHB and steam drum for uniform water/steam circulation in the syst
Constructive Solid Geometry (Csg or C-Rep) A CSG model is based on the topological notion that a physical project object can be divided into a set of primitives that can be com
Q. Material Selection for Insulation? Material for 15ºC to 650ºC temp range is Calcium Silicate, Manville Thermo-12 or approved equivalent. Material for -18ºC to 230ºC temp.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd