Physical tests on cement, Civil Engineering

Assignment Help:

Physical Tests on Cement

(a) Soundness Test: by sieve analysis, it is conducted. 100 gms of cement is taken and sieved throughout IS sieve No. 9 for fifteen minutes. Residue on the sieve is weighed. It should not exceed 10 %by weight of sample taken.

(b) Setting Time: Initial setting time and final setting time are 2 important physical properties of cement. Initial setting time is the time taken by the cement from adding of water to the beginning of losing its plasticity.  the time lapsed from adding of the water to full loss of plasticity is called Final setting time. Vicat apparatus is utilized for finding the setting times .Vicat apparatus consists of a movable rod to which any one of the three needles indicate in figure can be attached. An indicator is attaching to the movable rod. A vicat mould is linked with this apparatus which is in the form of split cylinder.

1365_vicat apppratus.png

                 Vicat apparatus

It is necessary to determine water to be added to get standard consistency before finding initial and final setting time. For this 300 gms of cement is mixed with approximate 30% water and cement paste prepared is filled in the mould which rests on non porous plate. The plunger is associated to the movable rod of vicat apparatus and gently lowered to touch the paste in the mould. Then the plunger is permitted to move freely. If the penetration is 5 mm to 7 mm from the bottom of the mould, then cement have standard consistency. If not, experiment will repeat with different proportion of water fill water needed for standard consistency is found. Then the tests for initial and final setting times may be carried out as described below:

Initial Setting Time: 300 gms of cement is comprehensively mixed with 0.85 times the water for standard consistency and vicat mould is fully filled and top surface is leveled. 1 mm square needle is fixed to the rod and gently placed over the paste. Then it is freely permitted to penetrate. In the starting the needle penetrates the paste fully. As time lapses the paste start losing its plasticity and offers resistance to penetration. When needle may penetrate up to 5 to 7 mm above bottom of the paste experiment is stopped and time elapsed between the addition of water and end I f the experiment is noted down as initial setting time.

Final Setting Time. The square needle is replaced with annular collar. Experiment is continued by permitting this needle to freely move after gently touching the surface of the paste. Time elapsed among the addition of water and the mark of needle but not of annular ring is found on the paste. This time is noted down as final setting time.

(c) Soundness Test: This test is conducted to find free lime in cement, which is not wanted. Le Chatelier apparatus shown in given figure is used for conducting this test. It consists of a split brass mould of height 30 mm and diameter 30 mm. On either side of the split, there are 2 indicators, with pointed ends. The ends of indicators are 165 mm from the centre of the mould.

562_le chatelier appratus.png

                                      Le Chatelier's apparatus

Correctly oiled Le Chatelier mould is placed on a glass plate and is filled fully with a cement paste with 0.78 times the water needed for standard consistency. It is then covered with another glass plate and a small weight is placed over it. Then the entire assembly is kept under water for 24 hours. The temperature of water should be between 24°C and 50°C. Note down the distance between the indicators. Then place the mould again in the water and heat the assembly like that water reaches the boiling point in 30 minutes. Boil the water for 1 hour. The mould is removed from water and permitted to cool. The distance between the 2 pointers is measured. The difference among the two readings indicates the expansion of the cement due to the presence of unburnt lime. This value should not exceed from 10 mm.

(d) Crushing Strength Test: For this 200 gm of cement is mixed with 600 gm of standard sand by confirming to IS 650-1966. After mixing comprehensively in dry condition for a minute distilled potable P/4 +3 percentage is added where P is the water needed for the standard consistency. They are mixed along with trowel for 3 to 4 minutes to get regular mixture. The mix is placed in a cube mould of 70.6 mm size (Area 5000 mm2) reserved on a steel plate and prodded with 25 mm standard steel rod 20 times within 8 seconds. Then the mould is placed on a standard vibrating table that vibrates at a speed of 12000 ± 400 vibration per minute. A hopper is safe at the top and the remaining mortar is filled. The mould is vibrated for 2 minutes and hopper removed. The top is over with a knife or with a trowel and leveled. After 24 ± 1 hour mould is removed and cube is placed under clean water for curing.

After particular period cubes are tested in compression testing machine, keeping the specimen on its level edges. Average of 3 cubes is reported as crushing strength. The compressive strength at the end of 3 days shall not be less than 11.5 N/mm2 and that at the end of 7 days not less than 17.5 N/mm2.


Related Discussions:- Physical tests on cement

Explain the activitated sludge (aeration tank), Explain the Activitated Slu...

Explain the Activitated Sludge (Aeration Tank)? The activated sludge treatment process is a biochemical oxidation process. Organic solids are stabilized through the oxidation p

Planning stage of the audit, Materiality is used only at the planning stage...

Materiality is used only at the planning stage of the audit. Ans: I disagree with the statement because: When planning the audit, the auditor considers what would make the fi

Shear lag in typical box-girder bridge, Shear lag in typical box-girder bri...

Shear lag in typical box-girder bridge For multiple-cell box girders, there are normally two arrangements. First one is that independent cells are connected by their top flang

What is the loss of prestress due to shrinkage of concrete, What is the Los...

What is the Loss of Prestress due to Shrinkage of Concrete It is the loss of prestress due to shrinkage of concrete, which takes place in the initial stage of hardening of conc

Mortar mechanism vs stone contact mechanism, "Mortar mechanism" vs. "stone ...

"Mortar mechanism" vs. "stone contact mechanism" in bituminous materials 'Stone contact mechanism' applies to well graded aggregates coated with bitumen (for example dense bit

Define role of diver in underwater inspection of bridge, Define Role of Div...

Define Role of Diver in Underwater Inspection of Bridge? Diver's role is primarily to point out a potential scour problem. The diver can use one of the following equipment to m

What is the safe bearing capacity of wide strip footing, A loading test was...

A loading test was conducted with a 300 mm square plate at depth of 1 m under the ground surface in pure clay deposit. The water table is situated at a depth of 4 m below the groun

Rb slab, #questionshow me picture..

#questionshow me picture..

Analysis of the two stage construction, A County is planning to build a new...

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widen

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd