Order sequences and order release, Mechanical Engineering

Assignment Help:

Order Sequences and Order Release

For this system, sequences of orders for particular parts (batch size 1) are produced in the following way: for each machine, here is, for each shift, a prescribed maximal load level ζ is calculated as ζ (machine type, shift number) = ζ0 (machine type) + Δ ζ (shift number) Δ ζ is arbitrary parameter, the load variation.

Because of the processing sequences structure, the average load ζ0 can only be selected freely on three of the four categories of machines. The selected values are as:

For case 1: 98 percent on HV, DOER and 98 percent on ECOC

For case 2: 98 percent on HV, DOER and 70 percent on ECOC

The load amplitude Δ ζ is understood to be either 0, - 30 percent, or + 30 percent. The actual part mix for simulation is produced from a basic random part type sequence along with average element type frequencies of 10 percent for part 1 and 9 percent for other parts. For all shift, there is a load account for all machines. An order for an exact part type is accepted as extended as the load accounts for all needed machines and for this shift it must not exceed the maximum load level ζ for this shift and these machines. Also, this is skipped. If no more element types can be accepted for this shift, the order sequence for this shift is finish. The subsequent order in the basic sequence becomes the initial new order for the subsequent shift. The actual average part frequencies are hence various from the values in the basic sequence.

As load level can be above 100 percent machine capability, there are backlogs. They are carried above to the subsequent shift. Over the initial 5, 10, 15 and so on, consecutive shifts, the average load level variations are put to zero.

The real order sequences are produced from five various basic element type sequences and five fundamental load variation sequences for all of the conditions illustrated below.

In case 1, orders are released along with equivalent spacing over the duration of a shift within every 19 minutes. In case 2, all orders are released at the starting of a shift. This offers rise to a considerably longer queues for the initial half shift, in exacting at the loading station.

Hence, the characteristics of case 1 can be summarized as: evenly distributed high loads on the machines along with temporary overload; at the stations, short to moderate queues. Within case 2, the characteristics can be specified as: part types 1-5 only need machines that are not bottlenecks; only element types 6-11 utilize machines that may be overloaded; the queues are long; the loading station is a dangerous resource.

Additionally to above conversation, the due date distribution is a critical parameter also that affects the presentation of the  scheduling policies. The due dates are produced as multiples of four hour (1/2 shift) intervals from order free. The percentage of orders for every value of this demanded throughput time was found such as under scheduling as per to FIFO a prescribed value of percentage of late jobs of as 30, 50, 70, and 85% was attained. The resulting distributions are shown in Table no.2 (a) and (b).  The  resulting  ratios  of  demanded  to  real  throughput  times  for  the various situations under the FIFO rule have also been specified in aforementioned tables.

The conditions A-D correspond to case 1, the percentage of late jobs raising from 30-85, the conditions E-H correspond to case 2 along with similar levels of late jobs under the FIFO rule.

Table no.2 (a): Due Dates Distribution for Situation A-D

Situation A : Case 1, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            10

480                            10

720                            10

960                            35

1200                          35

Average Throughput Time: 900 min

Demanded/achieved flow factor: 1.29

 

Situation  A  :  Case  1,  50%  late  jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

240                            10

480                            25

720                            30

960                            25

1200                          10

Average Throughput Time: 720 min

Demanded/achieved flow factor: 1.03

 

Situation A : Case 1, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            24

480                            34

720                            32

960                            5

1200                          5

Average Throughput Time: 559 min

Demanded/achieved flow factor: 0.80

 

Situation  A  :  Case  1,  85%  late  jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

240                            60

480                            25

720                            5

960                            5

1200                          5

Average Throughput Time: 408 min

Demanded/achieved flow factor: 0.57

 


Related Discussions:- Order sequences and order release

PRODUCTION PLANNING & CONTROL, PRODUCTION PLANNING & CONTROL Assignment 2 ...

PRODUCTION PLANNING & CONTROL Assignment 2 Kid style, International, makes furniture designed for children. Its most popular items are large and small toy boxes. Demand for toy

Aircraft characteristics - military and civil aircraft, Aircraft Characteri...

Aircraft Characteristics For planning and designing airport facilities, it is necessary to be conversant with the following important characteristics: (a) speed (b) size

Design, please help me to calculate the diameter of a brake drum for using ...

please help me to calculate the diameter of a brake drum for using in a "brake drum dynamometer engine test rig" the engine specs are as follows: - 6Hp single cylinder 4stroke engi

Special tool and cleaning of part general service tips , Special Tool: Use...

Special Tool: Use special tools wherever applicable. Special tools are designed to dismantle or assemble a specific part or assemblies without causing damage to them. Cleaning

Determine the two roots of equation , (i) Use the GOAL SEEK tool in MS EXCE...

(i) Use the GOAL SEEK tool in MS EXCEL to solve the following equation and determine the TWO roots of this equation between 0 X 4 -8x 3 -x 2 -14x+21=0 (ii). Use the SOLVER t

Find out the power - hollow shaft, Find out the power - hollow shaft: ...

Find out the power - hollow shaft: A hollow shaft of internal diameter 400 mm & external diameter 450 mm is needed to transmit power at 120 rpm. Find out the power it may tran

Define gas welding, Q. Define Gas Welding? Metal joining process in whi...

Q. Define Gas Welding? Metal joining process in which the ends of pieces to be joined are heated at their interface by producing coalescence with one or more gas flames (such a

Evaluate frequency of oscillation, (a) A spring mass system has a period 0....

(a) A spring mass system has a period 0.25 sec. What will be the new period if spring constant is increased by 50% ? (b) A vibratory system in a vehicle is to be prepared with t

Define oxidation process, Q. Define Oxidation Process? Oxidation is def...

Q. Define Oxidation Process? Oxidation is defined as a loss of electrons, as when a metal goes from the metallic state to the corroded state. When a metal reacts with oxygen,

Condition for a heat transfer process to occur, What the necessary conditio...

What the necessary condition for a heat transfer process to occur?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd