Operating characteristic curve, Project Management

Assignment Help:

Operating characteristic curve

The operating characteristic curve for a sampling plan quantifies the risks. The OC curve for an attribute plan is a graph of the percentage defective in a lot versus the probability that the sampling plan will accept a lot. The figure describes the OC curve:

1775_operating characteristic curve.png

Figure : OC curve

The figure explains that the acceptance level at A has about 98% chance of being accepted. B has 50% of defective and has 23 % chance of being accepted, C has about 30% defective and has 3% chance of being accepted.

The  OC  curve  can  be  developed  by  determining  the  probability  of acceptance for many values of incoming quality. The probability of acceptance is the probability that the number of defectives in the sample is equal to or less than the acceptance number for the sampling plan.

The OC curve for a particular plan states only the chance that a lot having certain defective percentage would be accepted by the sampling plan.

The confidence level in connection with a particular defective percentage might not be stated by OC curve, the final quality achieved post completion of inspections might not be predicted exactly by the OC curve.


Related Discussions:- Operating characteristic curve

Which tools are best for you to evaluate team performance, Q. You have been...

Q. You have been hired by a contractor, who wants you to organize a construction project for one of their clients. The project team has been working for six weeks. You need to eval

NPV, A brilliant UTM student at the end of his graduation is in presence of...

A brilliant UTM student at the end of his graduation is in presence of two opportunities and has to choosen between them.

What is brainstorming, Question 1: (a) Mr Dupuy, the Chaiperson of the ...

Question 1: (a) Mr Dupuy, the Chaiperson of the Rose Flower Senior Citizen Association having its seat at 30 Avenue Des Loisirs Pointes-aux-sables wishes to call a meeting of m

Project risk and procurement management, The management of risk is proving ...

The management of risk is proving to be one of the most difficult tasks for the project management profession. How can risk be managed effectively and who should be responsible for

Network Security and Support, Choose a case study from the readings or use ...

Choose a case study from the readings or use your own workplace or organisation to discuss these questions. 1. What are the key elements of a sustainability statement? 2. What ar

Levels of strategy, Levels of strategy There are three levels of strate...

Levels of strategy There are three levels of strategy: Corporate strategy is the overall (grand) strategy for the organization as a whole. Business strategy refers to

Define the conformance management systems, Define the conformance managemen...

Define the conformance management systems. Conformance management systems: Makes sure the output of the project for example the end product or result gathers the customer

Evaluating the design models, o Is the design understandable? o Is the desi...

o Is the design understandable? o Is the design of appropriate complexity for the task undertaken and the skill of the developer? o Is the design consistent? o Is the design mainta

Initial project plan, o Does the project plan clearly identify a set of fun...

o Does the project plan clearly identify a set of functional increments leading to project completion? o Is the sequence of objectives consistent with both the risk priority and

Checklist to compile a project scope statement, create a risk management pl...

create a risk management plan for all the formulated risks on payroll project

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd