One-way pre stressing vs two-way pre stressing, Civil Engineering

Assignment Help:

Q. One-way pre stressing vs two-way pre stressing?

At the time of pre-stressing operation at one end, frictional losses will take place and the prestressing force decreases along the length of tendon till reaching the other end. These frictional losses involve the friction induced because of a change of curvature of tendon duct and also the wobble effect because of deviation of duct alignment from the centreline. Thus the prestress force in the mid-span or at the other end would be greatly decreased in case the frictional loss is high. Thus prestressing, from both ends for a single span which implies prestressing one-half of total tendons at one end and remaining half at the other end is carried out to enable an even distribution and to provide symmetry of prestress force along the structure. 

As a matter of fact stressing at one end only has the potential advantage of lower cost when compared with stressing from both ends. For multiple spans (for example two spans) with unequal span length, jacking is generally carried out at the end of the longer span so as to provide a higher prestress force at the location of maximum positive moment. On contrary jacking from the end of shorter span will be conducted if negative moment at the intermediate support controls the prestress force. Though if the total span length is sufficiently long, jackingfrom both ends must be considered.


Related Discussions:- One-way pre stressing vs two-way pre stressing

Offset(survey)., what is meant by the offsets and explain its type?

what is meant by the offsets and explain its type?

Designing lateral resistance of piles, Question While designing later...

Question While designing lateral resistance of piles , have to engineers only use earth pressure against pile caps simply? Answer In case of designing lateral loa

Soil mechanics, Hi, i really need help to done my assignment i have done so...

Hi, i really need help to done my assignment i have done some part but in that case i need professional advice to finish my task. could you please let me know if you can help me. t

General requirement for civil engineering, Question General requirement for...

Question General requirement for Civil Engineering Works in 1992 Edition, Clause 15.09 details that tying wires for strengthening adjacent to and above Class F4 and F5 closes must

Coating on concrete – complete im-permeability to moisture, Q. Coating on c...

Q. Coating on concrete – complete im-permeability to moisture? In designing protective coating on concrete structures, stoppage of water ingress by the coating is generally req

Design the 2-span continuous center, Design the 2-span continuous center T-...

Design the 2-span continuous center T-beam, B2, for the floor syetem shown below. The girders that the beam frames into are all 24" wide. Using fc'= 5 ksi, and fy = 60 ksi. The ser

A concrete compression machine, Question In a concrete compression test , ...

Question In a concrete compression test , usually 150mmx150mmx150mm concrete cube examples are used for testing. Why isn't 100mmx100mmx100mm concrete cube samples used in test in

Chain surveying, describe setting out right angle at given point on a chain...

describe setting out right angle at given point on a chain line and when the point lies outside the chain line

Surveying, describe two fundamentals purposes of surveying.

describe two fundamentals purposes of surveying.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd