One-way pre stressing vs two-way pre stressing, Civil Engineering

Assignment Help:

Q. One-way pre stressing vs two-way pre stressing?

At the time of pre-stressing operation at one end, frictional losses will take place and the prestressing force decreases along the length of tendon till reaching the other end. These frictional losses involve the friction induced because of a change of curvature of tendon duct and also the wobble effect because of deviation of duct alignment from the centreline. Thus the prestress force in the mid-span or at the other end would be greatly decreased in case the frictional loss is high. Thus prestressing, from both ends for a single span which implies prestressing one-half of total tendons at one end and remaining half at the other end is carried out to enable an even distribution and to provide symmetry of prestress force along the structure. 

As a matter of fact stressing at one end only has the potential advantage of lower cost when compared with stressing from both ends. For multiple spans (for example two spans) with unequal span length, jacking is generally carried out at the end of the longer span so as to provide a higher prestress force at the location of maximum positive moment. On contrary jacking from the end of shorter span will be conducted if negative moment at the intermediate support controls the prestress force. Though if the total span length is sufficiently long, jackingfrom both ends must be considered.


Related Discussions:- One-way pre stressing vs two-way pre stressing

An alternative test to confirm concrete strength, Question If concrete comp...

Question If concrete compression test not pass, So Schmidt hammer test will be adopted as an alternative test to confirm concrete strength ? Answer Schmidt hammer test is

Linear algebra concept, Scenario: You are working for a structural engineer...

Scenario: You are working for a structural engineering firm and you have been assigned the task of computing the code checks on a new structural design. Though another commercial p

Stone soling - road pavements, Stone Soling: One of the early practic...

Stone Soling: One of the early practices in road construction was to provide a stone soling 150-225 mm in thickness. The stones are laid by manual labour, and stone spalls ar

How do you measure concrete, We can measure concrete by Cubic feet, Cubic y...

We can measure concrete by Cubic feet, Cubic yards, Cubic Meter

Design nominal reinforcement for staircase, Question Given a 1meter hig...

Question Given a 1meter high staircase resting on solid concrete, could it be adequate to design nominal reinforcement for staircase? Answer For design of staircase,

Traditional marine piling system of steel tubular pile, Question What i...

Question What is problem in traditional marine piling system of steel tubular pile with concrete infill and what are key possible remedial measures? Answer In design

Brick masonry., an opening of width 3m and height 2.7 in a brick masonary h...

an opening of width 3m and height 2.7 in a brick masonary has to be provided with door cum window. plan, elevation, section and 2 joining details

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Cumulative error, diffrence between cumilative compensative error

diffrence between cumilative compensative error

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd