One-way pre stressing vs two-way pre stressing, Civil Engineering

Assignment Help:

Q. One-way pre stressing vs two-way pre stressing?

At the time of pre-stressing operation at one end, frictional losses will take place and the prestressing force decreases along the length of tendon till reaching the other end. These frictional losses involve the friction induced because of a change of curvature of tendon duct and also the wobble effect because of deviation of duct alignment from the centreline. Thus the prestress force in the mid-span or at the other end would be greatly decreased in case the frictional loss is high. Thus prestressing, from both ends for a single span which implies prestressing one-half of total tendons at one end and remaining half at the other end is carried out to enable an even distribution and to provide symmetry of prestress force along the structure. 

As a matter of fact stressing at one end only has the potential advantage of lower cost when compared with stressing from both ends. For multiple spans (for example two spans) with unequal span length, jacking is generally carried out at the end of the longer span so as to provide a higher prestress force at the location of maximum positive moment. On contrary jacking from the end of shorter span will be conducted if negative moment at the intermediate support controls the prestress force. Though if the total span length is sufficiently long, jackingfrom both ends must be considered.


Related Discussions:- One-way pre stressing vs two-way pre stressing

Show the application of concrete crash barriers, Q. Show the application of...

Q. Show the application of Concrete crash barriers? Concrete crash barriers aren't considered as the best barrier design due to the following reasons when compared with flexibl

Surveying, A pre- engineering base line was run down a very steep hill.rath...

A pre- engineering base line was run down a very steep hill.rather than measure horizontaily down hill with steel tape: surveyor measured the vertical angle with the theodolite and

Loading and unloading cycles for soil nails, In carrying out pull-out tests...

In carrying out pull-out tests for soil nails, it generally requires the unloading and loading of soil nails of several cycles up to 80% of ultimate tensile strength of soil nails.

Explain the selected bridges - underwater inspection, Explain the Selected ...

Explain the Selected Bridges - Underwater Inspection? Those bridges, which require underwater inspection must be noted for individual inspection and inventory records as well b

State the term axial prestressingin - Concrete, State the term Axial Prestr...

State the term Axial Prestressingin Concrete If the centroid of cross-sectional areas of tendons is at the location of the centroid of the cross-section of the concrete member,

Determine the project duration and critical path, Critical Path - Activity ...

Critical Path - Activity on Node The project precedence table shown below provides the relationships and durations of all activities. Based on end-of-day calculations for start

Wires in gabion walls, Gabions are wire mesh boxes that are filled with sto...

Gabions are wire mesh boxes that are filled with stones and they areplaced in an orderly pattern to act as a single gravity retaining wall. Meshes or Lacing wires are designed t

Compute the maximum allowable concentrated live load, Given for the section...

Given for the section shown in Figure, M * = 250 kNm, f sy = 500 MPa and f c ′ = 25 MPa. Compute A st and (if necessary) A sc . You may assume that eac

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd