Mixed ground with soils and boulders, Civil Engineering

Assignment Help:

Ground settlement occurs when pipe-jacking machine enters mixed ground with soils and boulders?

The rate of cutting through soils is faster than cutting through boulders for pipe-jacking machine. When pipe-jacking machine enters a region of mixed ground with boulders andsoils, machine has the tendency to move in the direction of soft soils due to the difference of rate of advancement of pipe-jacking machine for boulders andsoils. Therefore migration of soft soils take place which contributes to ground settlement. Degree of settlement is dependent of the depth of soil cover, soil property and size of boulders.


Related Discussions:- Mixed ground with soils and boulders

Advantageous to use concrete of very high power, Question Will it advantag...

Question Will it advantageous to use concrete of very high power for example exceeding 60MPa? What are potential problems connected with high strength concrete ? Answer To in

Deflection of beams, 1) A propped cantilever beam ABC is 7m long.It has th...

1) A propped cantilever beam ABC is 7m long.It has the point C fixed and Point A on a roller support.It carries a 200Kn point load at a distance 3m from A.There is a moment of 80KN

Write short notes on bulking of sand, Q. Write short notes on Bulking of Sa...

Q. Write short notes on Bulking of Sand? Volume of sand fluctuates with variations in moisture content when sand is wet then each particle sets coating of water due to surface

What do you mean by internal fiction, Q. What do you mean by Internal ficti...

Q. What do you mean by Internal fiction? Absorptive materials have some elastic fibrous or porous structures that would be extended and compressed at the time of sound wave pro

Infrastructure railway design, The objective of this module is:- - For t...

The objective of this module is:- - For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibili

What is the group capacity, State the group efficiency of a rectangular gro...

State the group efficiency of a rectangular group of piles with 4 rows, 3 piles per row, the uniform pile spacing being 3 times the pile diameter. If the individual pile capacity i

Describe the consolidation settlement, Q. Describe the Consolidation Settle...

Q. Describe the Consolidation Settlement? The resulting settlements which are time-dependent and are termed consolidation settlements. After the consolidation settlements take

Hydaurlics : pelton and francis turbine, what are the factors which influen...

what are the factors which influence the efficiency of the turbine?

Differences between open shield and closed shield, Q. Differences between o...

Q. Differences between open shield and closed shield? Open shield type TBM refers to those providing lateral support only. They can be further classified into single shield and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd