Line Balancing Procedure in Assembly Layout

  • step1: Determine what tasks must be performed to complete one unit of a finished product and the sequence in which the tasks must be performed draw the precedence diagram.
  • Step 2: Estimate the task time amount of time it takes a worker to perform each task)
  • Step 3: Determine the cycle time (the amount of that would elapse between products coming off the end of the assembly line, if the desired hourly production were being produced)
  • Step 4: Assign each task to a worker and balance the assembly line. This process results in determining the scope of each worker job or which tasks that the he or she will perform.

Related Discussions:- Line balancing procedure in assembly layout

Project management and leadership, Scenario Even ‘well run' organisations c...

Scenario Even ‘well run' organisations can fail to stay atop of their industries when they are challenged by certain market or technology change. Change is an imminent part of busi

What is the important role of planning in the management, What is the impor...

What is the important role of planning in the management? Planning: Planning can be described as deciding in advance regarding the goals to be pursued through the enterpris

Swot analysis, SWOT Analysis is constituted with strengths, weaknesses, opp...

SWOT Analysis is constituted with strengths, weaknesses, opportunities and threats. It is the analysis that to identify the internal and external factors relate to the organization

Advantages of iso standards, ISO standards give tremendous advantages to ...

ISO standards give tremendous advantages to those holding their certification. Some of these advantages are briefly discussed below for different categories of groups ins

What are the disadvantages of division of labour, What are the Disadvantage...

What are the Disadvantages of Division of Labour? Disadvantages of Division of Labour are as follows: a. Division of labour provides rise to loss of craftsmanship, workers t

Project management value initiative, Project Management Value Initiative ...

Project Management Value Initiative The project management initiative program is a six step process which is designed to bring about a measurement team from the introduction to

Selection criteria for process layout, Normal 0 false false ...

Normal 0 false false false EN-IN X-NONE X-NONE

Stakeholde, Differences between Primary and Secondary Stakeholders?

Differences between Primary and Secondary Stakeholders?

Functional organisation structure, Functional organisation In this type...

Functional organisation In this type of organisational structure people are grouped into functional divisions such as production or marketing. Every employee reports to a super

#title.Discountingw., what is the principle of discounting and what issues ...

what is the principle of discounting and what issues are critical in this process

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd