Q. Inspection and Quality Control Certificate :

A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certified. In case of any defect in the bearing, the whole 'lot' shall be rejected by the inspector and certified accordingly.

The bearings shall be transported to the bridge site after final acceptance and should be accompanied by an authenticated copy of the test certificate. An information card giving the following details should be appended to the test cerftificate:

1. Name of manufacturer

2. Date of manufacture

3. Grade of elastomer

4. Bearing dimensions

5. Production Batch No.

6. Accpetance lot No.

7. Date of testing

8. Specific bridge location

9. Explanation of markings on the bearing, if any.


Related Discussions:- Inspection and quality control certificate

Principle for conducting surface regularity test, Question What is dist...

Question What is distinction in principle for conducting surface regularity test and sand test? Answer Purpose of surface regularity test is to assess riding quality

What is multiple-cell box girder, Q. What is Multiple-cell box girder? ...

Q. What is Multiple-cell box girder? Multiple-cell box girder: cells connected by top flanges vs. cells connected both by top and bottom flanges When the depth of a box gi

Surveying, How to read verniers and main scale readings on theodolite of 10...

How to read verniers and main scale readings on theodolite of 10"?

Unloaded propped, Ask questa) In an unloaded propped cantilever, the proppe...

Ask questa) In an unloaded propped cantilever, the propped end sinks vertically relative to the fixed end by an amount ? due to poor construction of the foundation of the prop. Wha

Corrosion, Distinguish between dry and wet corrosion

Distinguish between dry and wet corrosion

Dissimilarity b/w air chamber and surge tank, Question What is dissimil...

Question What is dissimilarity between air chamber and surge tank ? Answer Air chambers and surge tanks are usually set up in watermain to ease stress on schem

Major drawbacks of using inverted siphons, Question What is key application...

Question What is key application of inverted siphons? What are major drawbacks of using inverted siphons ? Answer Inverted siphons are planned at locations in which sewer s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd