Inspection and quality control certificate, Civil Engineering

Assignment Help:

Q. Inspection and Quality Control Certificate :

A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certified. In case of any defect in the bearing, the whole 'lot' shall be rejected by the inspector and certified accordingly.

The bearings shall be transported to the bridge site after final acceptance and should be accompanied by an authenticated copy of the test certificate. An information card giving the following details should be appended to the test cerftificate:

1. Name of manufacturer

2. Date of manufacture

3. Grade of elastomer

4. Bearing dimensions

5. Production Batch No.

6. Accpetance lot No.

7. Date of testing

8. Specific bridge location

9. Explanation of markings on the bearing, if any.


Related Discussions:- Inspection and quality control certificate

Important parts of road pavements, Important parts of road pavements: ...

Important parts of road pavements: Prime Coat : Application of a low viscosity bituminous binder over a granular base to fill up the voids. Tack Coat : Application of b

Contours, how can you draw contours of a non square grid?

how can you draw contours of a non square grid?

Explain flash butt welding, Q. Explain Flash Butt welding? In this proc...

Q. Explain Flash Butt welding? In this process the ends of two rails are kept at fixed distance apart and a mould (designed to suit the rail section ) is fitted on. The rail en

Calculate the change in volume, Calculate the change in volume: If the...

Calculate the change in volume: If the bar is 1 m long with rectangular cross section of 300 mm deep and 400 mm wide, compute the change in volume of the solid because of a lo

Surveying, Describe the two fundamental purposes of surveying

Describe the two fundamental purposes of surveying

What is bore hole, What is Bore Hole In exploration of  area of  limit...

What is Bore Hole In exploration of  area of  limited extent  the borings should preferably be located near the comers of  the area. A minimum of three holes should be made un

Show the differences between GGBS and PFA, Q. Show the Differences Between ...

Q. Show the Differences Between GGBS and PFA? The use of GGBS as substitute of cement improves smaller reliance on PFA. Particularly GGBS is supposed to be more compatible with

Block contouring, how to calculate contour surveyed area

how to calculate contour surveyed area

Calculate the daily standard production rate of equipment, Calculate the Da...

Calculate the Daily Standard Production Rate of Equipment An excavator with a bucket capacity of 3-yd 3 has a standard operating cycle time of 40 seconds. The daily standard p

What is preset mean while installation of bridge bearings, What is preset m...

What is preset mean while installation of bridge bearings ?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd