A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certified. In case of any defect in the bearing, the whole 'lot' shall be rejected by the inspector and certified accordingly.

The bearings shall be transported to the bridge site after final acceptance and should be accompanied by an authenticated copy of the test certificate. An information card giving the following details should be appended to the test cerftificate:

1. Name of manufacturer

2. Date of manufacture

3. Grade of elastomer

4. Bearing dimensions

5. Production Batch No.

6. Accpetance lot No.

7. Date of testing

8. Specific bridge location

9. Explanation of markings on the bearing, if any.


Related Discussions:- Inspection and quality control certificate

How we can check caisson is stable or not, A box caisson, 10 m high, is 18 ...

A box caisson, 10 m high, is 18 m × 9 m at the base. The weight of the caisson is 9 MN and its centre of gravity is 4.2 m above the base. Check whether the Caisson is stable. If

Dynamics, A vehicle for landing on the moon has a mass of 4500kg. The dampe...

A vehicle for landing on the moon has a mass of 4500kg. The damped spring undercarriage system of the vehicle has a stiffness of 450kn/m and a damping ratio of 0.2. The rocket lift

Raised check rails for obtuse crossing, Raised Check Rails for obtuse cross...

Raised Check Rails for obtuse crossing In order to provide guided path way in throat portion of 1 in 8 1/2 BG obtuse diamond crossing, the check rails are raised by welding of

Surface cleaning tools for underwater inspection of bridge, Define Surface ...

Define Surface Cleaning Tools for Underwater Inspection of Bridge? To perform a thorough inspection, the marine growth on the structure must be removed. This can be done by var

..zero energy building, this is our final year project .please help me to g...

this is our final year project .please help me to guide about it

Erosion ocntrol, java program to design a SD-3 sediment pond per Georgia er...

java program to design a SD-3 sediment pond per Georgia erosion control manual

Effect of concrete placing temperature, Effect of concrete placing temperat...

Effect of concrete placing temperature on early thermal movement Rate of hydration of cement paste is related to placing temperature of concrete. Rate of heat production is giv

Determine the concept of shrink-fitting of metal tyres, Determine the conce...

Determine the concept of Shrink-fitting of metal tyres Shrink-fitting of metal tyres on the wheels of bullock carts is well known. As the hot metal tyre rings cool down, they a

State average increase of pressure in the clay stratum, A building was to b...

A building was to be constructed on a clay stratum. Preliminary analysis showed a settlement of 60 mm in 6 years and an ultimate settlement of 250 mm. The average enhance of pressu

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd