Inspection and quality control certificate, Civil Engineering

Assignment Help:

Q. Inspection and Quality Control Certificate :

A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certified. In case of any defect in the bearing, the whole 'lot' shall be rejected by the inspector and certified accordingly.

The bearings shall be transported to the bridge site after final acceptance and should be accompanied by an authenticated copy of the test certificate. An information card giving the following details should be appended to the test cerftificate:

1. Name of manufacturer

2. Date of manufacture

3. Grade of elastomer

4. Bearing dimensions

5. Production Batch No.

6. Accpetance lot No.

7. Date of testing

8. Specific bridge location

9. Explanation of markings on the bearing, if any.


Related Discussions:- Inspection and quality control certificate

Effect of bridge piers across a stream, Presence of bridge piers across a s...

Presence of bridge piers across a stream causes constricted flow in the openings due to the decrease of width of stream owing to presence of the piers. Furthermore it creates the f

Determine the ground elevation, The trigonometric levelling from the survey...

The trigonometric levelling from the surveyor's notes is shown below. The ground elevation of T (ft) is most nearly: Solution:  The elevation of point P can be found from: E

Practically the dielectric constant of air is taken as , Practically  the ...

Practically  the dielectric constant of air is taken as? Answer: The dielectric constant of air is taken as  unity.

Atomic polarisability, what is the atomic polarisibility of argon its susce...

what is the atomic polarisibility of argon its susceptibility is 273k and 1 atm is 4.35*10^-4 and n is 2.7*10^25atoms/m^3

Screw pumps and pump trough, Question In structure of pump troughs for ...

Question In structure of pump troughs for accommodation of screw pumps, what is major construction process to ensure close contact between screw pumps and pump trough ? An

Light-weight aggregate prestressed concrete, Light-weight Aggregate Prestre...

Light-weight Aggregate Prestressed Concrete The use of  light-weight aggregate concrete for prestressed concrete construction is well established. The main advantage of  light-

Mechanism of plastic settlement in fresh concrete, Q. Mechanism of plastic ...

Q. Mechanism of plastic settlement in fresh concrete? Within a few hours after placing of fresh concrete, plastic concrete can experience cracking due to occurrence of plastic

Key reasons for conducting pull-out tests, Question What are key reason...

Question What are key reasons for conducting pull-out tests for soil nails ? Answer There are largely four bases for this examination- (i) To verify and verify bo

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd