Q. Inspection and Quality Control Certificate :

A 'lot' under inspection should be accepted by the inspector when no defect is found in the acceptance level tests and so certified. In case of any defect in the bearing, the whole 'lot' shall be rejected by the inspector and certified accordingly.

The bearings shall be transported to the bridge site after final acceptance and should be accompanied by an authenticated copy of the test certificate. An information card giving the following details should be appended to the test cerftificate:

1. Name of manufacturer

2. Date of manufacture

3. Grade of elastomer

4. Bearing dimensions

5. Production Batch No.

6. Accpetance lot No.

7. Date of testing

8. Specific bridge location

9. Explanation of markings on the bearing, if any.


Related Discussions:- Inspection and quality control certificate

Cantilever beam, can i use lockfix to making cantilever beam

can i use lockfix to making cantilever beam

Designing water storage tank, Question While designing water storage t...

Question While designing water storage tank , has movement joints be installed? Answer While designing water storage tanks , group joints can be set up in similar w

Explain foundation design discharge for a bridge, Q. Explain Foundation des...

Q. Explain Foundation design discharge for a bridge? To provide for an adequate margin of safety against any abnormal flood exceeding the design discharge (Q), the foundations,

Define recommendations for ptfe, Define Recommendations for PTFE? (a) I...

Define Recommendations for PTFE? (a) It can be either of the two forms given below: (i) Dimpled large sheet It may be circular or rectangular divided maximum into four pa

Calculate the monthly payment for home mortgage, Your home mortgage is $300...

Your home mortgage is $300,000 for 30 years with a nominal annual rate of 7%. The monthly payment is most nearly: Solution: n = 360 months interest = 7%-annual ÷ 12-months/year

Explain the coefficient of permeability, A sand deposit of 12 m thick overl...

A sand deposit of 12 m thick overlies a clay layer. The water table is 3 m below the ground surface. In a field permeability pump-out test, the water is pumped out at a rate of 540

Survey, underground installations

underground installations

Example of magnetic dip, Example : Line AB was drawn with a magnetic ...

Example : Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what m

Geotech, soil sample investigation

soil sample investigation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd