How should reservoir floors be designed, Civil Engineering

Assignment Help:

Question

In designing of service reservoirs, how should reservoir floors be designed to avoid leakage of water because of seasonal and shrinkage movements?


Answer

In general two core approaches designing floors of service reservoirs as follows-

(i) In first method, movement joints are designed in each section of reservoir floors so they are able to expand and contract freely. Each section is entirely isolated from one an additional and sliding layer is placed under them to aid in sliding.

(ii) Second means, on contrary, does not make provision to free movement. Because seasonal and shrinkage movements, cracks are designed to happen in reservoir floors such that very tiny cracks are spread in excess of floor and these cracks are also small to initiate corrosion or leakage. However, in case, amount of reinforcement used is much larger than first come near.

 

 


Related Discussions:- How should reservoir floors be designed

Calculate the amount of cubic yards of soil, A proposed building site requi...

A proposed building site requires 135,000-ft 3 of imported fill.  A borrow site is located 5-miles Northeast of the project site where the soil has a shrinkage of 16%.  The amount

Turbines, How do we get electricity even when the gates of a dam were close...

How do we get electricity even when the gates of a dam were closed?

Define fatigue load test of shock transmission unit, Define Fatigue load te...

Define Fatigue load test of shock transmission unit? This test was carried out for 100,000 cycles for maximum capacity of STU, assuming the worst case that the 'Lock Up Load' i

Design of steel structure, in compression member [strut] why no deduction o...

in compression member [strut] why no deduction of area of rivet hole?

Write short note on open foundation, Q. Write short note on Open Foundation...

Q. Write short note on Open Foundation? Broadly the foundation are classified into open i.e. shallow & deep foundations open as stated are shallow foundation where the soil str

Calculate the invert elevation of the sewer pipe, 1. The center line elevat...

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly: 2. A design engineer c

Spalling reinforcement for pre stressing works, Spalling reinforcement for ...

Spalling reinforcement for pre stressing works in anchor blocks Reinforcement of anchor blocks in prestressing works usuallycomprises equilibrium reinforcement, bursting reinfo

Use pot bearings instead of elastomeric bearings, Question Under which ...

Question Under which situation ought to engineers use pot bearings instead of elastomeric bearings ? Answer In an event of high vertical loads shared with large angl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd