How should reservoir floors be designed, Civil Engineering

Assignment Help:

Question

In designing of service reservoirs, how should reservoir floors be designed to avoid leakage of water because of seasonal and shrinkage movements?


Answer

In general two core approaches designing floors of service reservoirs as follows-

(i) In first method, movement joints are designed in each section of reservoir floors so they are able to expand and contract freely. Each section is entirely isolated from one an additional and sliding layer is placed under them to aid in sliding.

(ii) Second means, on contrary, does not make provision to free movement. Because seasonal and shrinkage movements, cracks are designed to happen in reservoir floors such that very tiny cracks are spread in excess of floor and these cracks are also small to initiate corrosion or leakage. However, in case, amount of reinforcement used is much larger than first come near.

 

 


Related Discussions:- How should reservoir floors be designed

Scheme of some smaller piles with same load capacity, Question Which wi...

Question Which will be a better choice, a large diameter piles or a scheme of some smaller piles with same load capacity ? Answer Choice of a large diameter pile suff

What is thermo-electric prestressing, What is Thermo-electric prestressing ...

What is Thermo-electric prestressing We know that, stretched tendons are used in prestressed concrete. Stretching of tendons may be accomplished by using jacks or by other mea

Approach span to its neighbouring inner spans, Question-Why is span length...

Question-Why is span length ratio of end span, approach span to its neighbouring inner spans typically about 0.75?   Answer-From aesthetic point of view, odd number of span

Determine the late start time for activity, For the project network shown, ...

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

Amount of borrow needed to bring area to elevation of 90-ft, Surveyed eleva...

Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most near

Advantages and disadvantages of water transport, Advantages and Disadvantag...

Advantages and Disadvantages of Water Transport: The following are the advantages of water transport: (a)        Since the vessels travel on water, no investment is needed

Estimate the probable final settlement, A bed of sand 12 m thick is underla...

A bed of sand 12 m thick is underlain by a compressible stratum of normally loaded clay, 6 m thick. The water table is at a depth of 5 m below the ground level. The bulk densities

Explain damage inspections - underwater inspection of bridge, Explain the D...

Explain the Damage inspections - underwater inspection of bridge? Sometimes referred to as post-event inspections, damage inspections are typically unscheduled inspections aime

Systems approach to diagnose and solve the chronic w, systems approach to d...

systems approach to diagnose and solve the chronic water crisis in the city.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd