How should reservoir floors be designed, Civil Engineering

Assignment Help:

Question

In designing of service reservoirs, how should reservoir floors be designed to avoid leakage of water because of seasonal and shrinkage movements?


Answer

In general two core approaches designing floors of service reservoirs as follows-

(i) In first method, movement joints are designed in each section of reservoir floors so they are able to expand and contract freely. Each section is entirely isolated from one an additional and sliding layer is placed under them to aid in sliding.

(ii) Second means, on contrary, does not make provision to free movement. Because seasonal and shrinkage movements, cracks are designed to happen in reservoir floors such that very tiny cracks are spread in excess of floor and these cracks are also small to initiate corrosion or leakage. However, in case, amount of reinforcement used is much larger than first come near.

 

 


Related Discussions:- How should reservoir floors be designed

Determine equipment purchase yields a minimum 15% return, A contractor esta...

A contractor established a policy to purchase equipment over leasing only if the return is a minimum of 15%. Given the following conditions, the contractor's decision based on the

Working from whole to part in survey, a clear illustration about working to...

a clear illustration about working to part principle and some examples

Determine the uses of screw connectors, Determine the uses of Screw connect...

Determine the uses of Screw connectors Screw connectors are normally used  to splice large-diameter high-tensile strength bars. The bars are threaded at the ends and a sheet-me

Design of the aeration basin based on solids retention time, Design of the ...

Design of the Aeration Basin Based on Solids Retention Time - sewer construction: You are provided the following information about a municipal wastewater treatment plant. That

Elastic curve, elastic curve of a simply supported beam with triangular loa...

elastic curve of a simply supported beam with triangular load

Compute the ultimate settlement, A 2 m wide strip footing is to be constru...

A 2 m wide strip footing is to be constructed in a sandy stratum of 2 m thick. The depth of the footing is 1 m below ground surface. The sand layer is underlain by lm thick cla

Main functions of slip joints in block work seawalls, Question What are...

Question What are main functions of slip joints in block work seawalls ? Answer Slip joints are joints that are formed during a complete vertical plane from cope

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd