Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Strength of material, Draw complete shear and moment diagrams for a 3...

Draw complete shear and moment diagrams for a 3 m long cantilever beam having a uniform distributed load of 2 kN/m along its length.

Analog control system for steam generator, Q. Analog Control System for ste...

Q. Analog Control System for steam generator ? The analog (modulating) control of the Steam Generators will be performed using a Process Control System (by Buyer). Detailed fun

Direct and bending stresses, Direct and Bending Stresses: defined n...

Direct and Bending Stresses: defined neutral axis, introduced the influence of axial force and bending moment on different sections, attained the core or kernel of di

Tolerances, difference between geometric and amnufacturing tolerances

difference between geometric and amnufacturing tolerances

Determine the shear stress in each section - cells, Determine the shear str...

Determine the shear stress in each section - cells: In Figure, the mean dimensions of the two cells are 100 mm × 50 mm and 50 mm square. t 1 = 3 mm,       t 2 = 6 mm,

Frames, Frames: You have been introduced to the analysis of frames. By...

Frames: You have been introduced to the analysis of frames. By going through this unit, you may identify frames and differentiate them from trusses. The method for analyzing f

Magnetic alloy steels, Magnetic Alloy Steels: These steels are divide...

Magnetic Alloy Steels: These steels are divided into two sets. Such which retain their magnetism and that which do not. The steels which retain their magnetism are termed as

How to calculate coupling factor?, Q. Two coils with self inductances 1H an...

Q. Two coils with self inductances 1H and 4H have a mutual inductance of 1H. The RMS value of current flowing in the two coils is 4A and 1A respectively. Find  the coupling factor

Deflection, determine the vertical deflection at end A neglecting shear

determine the vertical deflection at end A neglecting shear

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd