Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Explain the working of die casting, Q. Explain the working of Die Casting? ...

Q. Explain the working of Die Casting? In the die casting process the, mould used for a casting is permanent called a die casting. it is shown in figure. It is thus quite diffe

Used engine oil and hot engine parts , Used Engine Oil: Used engine oil ma...

Used Engine Oil: Used engine oil may cause skin disease if repeatedly in contact with the skin for prolonged time. It is advisable to thoroughly wash the hands with soap and water

Determination of wind-induced forces on pressure vessels, Q. Determination ...

Q. Determination of Wind-Induced Forces on Pressure Vessels? ASCE does not provide the complete methodology needed to account for wind-induced forces on common appurtenances to

Impact testing, Charpy impact tests, when required shall comply. Impact ...

Charpy impact tests, when required shall comply. Impact tests shall be conducted at the minimum design metal temperature or at a lower temperature and shall meet or exceed energ

Screw jack, give equivalence of screw jack and friction on an inclined plan...

give equivalence of screw jack and friction on an inclined plane

Maximum stress in each material, The maximum stress in each material: ...

The maximum stress in each material: A copper tube of external diameter 60 mm and internal diameter 40 mm is closely fitted to a steel rod of 40 mm diameter to compose a compo

Bond, What is bond and the types..

What is bond and the types..

Vessels resting on concrete foundations, Q. Vessels resting on concrete fou...

Q. Vessels resting on concrete foundations? For vessels resting on concrete foundations, the allowable concrete bearing stress shall be 750 psi (5 MPa). The design loadings fo

Evaluate power transmitted by shaft, Evaluate power transmitted by shaft: ...

Evaluate power transmitted by shaft: How do you evaluate power transmitted by shaft (P)? Sol.: Consider force 'F' Newton's acting tangentially on shaft of radius ' R '.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd