Hazard identification in plant layout, Mechanical Engineering

Assignment Help:

Risks associated with identified hazards can be reduced to a reasonable level through the application of good design principles that are focused on integrating safety into the overall considerations of the design process. This is achieved by reducing the probability of occurrence of risk events, conditions and sources, and minimizing their consequences.

Risks are inherent to any human activity and cannot be totally eliminated. The risk management process is based on the systematic identification of hazards and their associated causes in order to define the extent and likelihood of the potential loss.

This is used to prioritize and assign appropriate actions or treatments appropriate to the level of risk. These treatments are then used to reduce the risks to the project. The guiding principle shall be that the project shall be able to demonstrate that risks have been reduced to As Low As Reasonably Practicable (ALARP).

ALARP principles and Cost Benefit Analyses are used to judge the adequacy at each stage of the risk management process and to ensure that the design meets the criterion of maximum protection of the personnel, environment and assets.

The first step should be the elimination of potential hazards by improving the inherent safety of the design concept, subsequently relying on engineering controls, and finally on administrative controls where fundamental design mitigation is not technically or economically feasible.

Hazards in plant facilities can sometimes be exacerbated by the general requirements for the location of the facilities to be remote of inhabited areas. This can on occasions affect support activities due to the location of support services and the nature of the products being handled. These hazards impact on the total life cycle design requirements of a plant; including its construction, installation, its operation and maintenance , and ultimately the de-commissioning and disposal of the plant.

A preliminary risk assessment should be done to determine the level of importance for each potential hazard and associated risks. This should involve key project personnel, and where possible experienced plant operational and maintenance personnel.


Related Discussions:- Hazard identification in plant layout

Refrigeration cycle, 1.5kw/ton of refrigeration is required to maintain tem...

1.5kw/ton of refrigeration is required to maintain temp of -40c in the refrigerator.if the cycle works on carnot cycle.determine 1.cop,2.sink temp 3. heat rejejected to the sink/to

Locomotive boiler, What are the advantages and disadvantaged of locomotive ...

What are the advantages and disadvantaged of locomotive boilers

Ventilation process of plant, Q. Ventilation process of plant? Due to t...

Q. Ventilation process of plant? Due to the possibility of accidental discharges of flammable gas and flashing liquid (e.g. leaks, incorrect valve opening, sampling, etc.); ade

Explain the machining processes, Machining Processes In machining proce...

Machining Processes In machining processes, also known as Metal cutting or chip forming processes, material is removed from a work piece to get the final shape of the product.

Find the out value of force - cantilever truss, A cantilever truss is loade...

A cantilever truss is loaded and supported as shown in the figure given below. Find the out value of P , which would produce an axial force of magnitude 3KN in member AC .

Determine the maximum stress, The cross-section of two angles attached tog...

The cross-section of two angles attached together are shown on the left below. The properties of angles are given in the table with reference to the diagram on the right. The ma

What is hydraulic press, (i) Hydraulic press:   This can be used...

(i) Hydraulic press:   This can be used to lift a heavy load placed on the platform of larger piston or to press the things placed among the piston and the heavy platfor

Construct a plain scale, Construct a plain scale: The distance between...

Construct a plain scale: The distance between Indore and Bhopal is 180 kilometer. It is represented on the map via 9 centimeter. Construct a plain scale for such map, illustra

Homogeneous and isotropic material, Homogeneous and isotropic material: ...

Homogeneous and isotropic material: A homogeneous material implies that elastic properties like modulus of elasticity and Poisson's ratio of material are same everywhere in

Determine the instantaneous hydrostatic force, A 6 cm diameter rubber ball ...

A 6 cm diameter rubber ball weighing 5 g is used to plug a 4 cm hole in the base of a tank. The tank is in use and is gradually emptying. At approximately what depth will the ball

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd